Nature and pricing rules of statutory safety provisions (GB/T 50500-2024: non-competitive item, whole-process constraints, and the change in normative force)
GB/T 50500-2024 Clause 3.2.5 states that the statutory safety provisions in the bill of preliminaries "shall be priced per the relevant provisions of the state, provincial, and industry authorities" and "are a non-competitive item" — their standard is not formed by market competition. Clause 2.0.4 defines them as the special fee safeguarding construction production safety; Clauses 5.2.5/6.2.6/9.3.1/9.3.4 enforce "compliance with authority provisions + ring-fenced (earmarked) use of funds, no diversion" across the tender price ceiling, tenders, and interim payments. The old GB 50500-2013 Clause 4.1.5 (mandatory provisions of codes: "must... shall not be a competitive fee") lost its mandatory force when the standard changed to a recommended GB/T; current binding force rests on administrative documents of the authorities and tendering supervision practice.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准(第2.0.4、3.2.5、5.2.5、6.2.6、9.3.1、9.3.4条,App. ETable E.3.2)
- GB 50500-2013 建设工程工程量清单计价规范(第4.1.5条,已随版本更新)
- 建办〔2005〕89号 建筑工程安全防护、文明施工措施费用及使用管理规定
- TB 10801-2024(第3.11.11条)、TB 10811-2024(第2.11.9条,铁路口径对照)
- JTG 3830-2018(第3.1.11条,公路口径对照)
Topic Positioning
This card interprets the nature and pricing rules of the "statutory safety provisions" (termed the "mandatory health, safety and environmental (HSE) provisions" in GB 50500-2013) in GB/T 50500-2024, the China national pricing standard for BOQ (GB/T 50500): the term definition (2.0.4), the non-competitive characterization (3.2.5), the constraints at the tender price ceiling, tender, and interim payment stages (5.2.5, 6.2.6, 9.3.1, 9.3.4), and the change of normative force between editions. For housing, municipal, and similar projects priced on a bill of quantities basis under the GB/T 50500 system.
Core Conclusions
- Nature (Clause 2.0.4): the statutory safety provisions are "the cost incurred by the contractor in adopting measures to safeguard construction production safety in carrying out and completing the works per the state, industry, and local safety requirements", and "include the safety requirements stipulated by the employer in the tender documents and agreed in the contract". They are a protective special fee within preliminaries (input for non-physical safety objectives), not consideration for work sections.
- Pricing characterization (Clause 3.2.5): "the statutory safety provisions in the bill of preliminaries shall be priced per the relevant provisions of the state, provincial, and industry authorities", and they "are a non-competitive item; their pricing shall comply with the relevant provisions" — the standard is not formed by competition: the employer may not demand discounts, and bidders may not undercut.
- Whole-process constraints:
- Tender price ceiling (5.2.5): preliminaries may be determined from the tender documents and bill of quantities (BOQ), implementation requirements and conventional methods, contract terms, Appendix E Table E.3.2 measures composition analysis, similar projects, and market cost information — "the statutory safety provisions shall be computed per the provisions of the state, provincial, and industry authorities".
- Tender (priced offer) (6.2.6): bidders price preliminary items autonomously per their implementation scheme and programme — "the statutory safety provisions shall comply with the relevant provisions of the state, provincial, and industry authorities" — autonomy is bounded by the authorities' provisions.
- Interim payment and use (9.3.1, 9.3.4): the provisions "shall be subject to ring-fenced (earmarked) use of funds and satisfy the provisions of the state, provincial, and industry building authorities and the safety requirements of local departments and the project"; the contractor "shall not divert them and shall list them separately in the accounts for inspection" — otherwise the employer may order rectification within a time limit, and failing that, order suspension of the works, "with the increased costs and/or delays borne by the contractor".
- Why non-competitive (underlying logic): (1) safety-baseline nature — the fee level directly determines edge protection, safety nets, safety training, and monitoring of sub-divisional works involving significant hazards; competition would compress safety input and externalize accidents — a market-failure domain requiring government-priced restraint; (2) percentage rates set by government — the rates/calibers are issued by state and provincial cost agencies, outside enterprise pricing (continuing the compulsory management of Jian Ban [2005] No. 89); (3) earmarked funds — ring-fenced use, separate accounting, and suspension sanctions show the contractor has only use rights, not free disposal — they cannot be competitive consideration.
- Edition comparison (force): old GB 50500-2013 Clause 4.1.5 (mandatory provisions of codes): "the mandatory health, safety and environmental (HSE) provisions must be computed per state or provincial/industry provisions and shall not be a competitive fee" — a bold-type mandatory clause then; the new GB/T 50500-2024 Clause 3.2.5 renames the term "statutory safety provisions", the standard becomes recommended GB/T with no mandatory provisions of codes, using "non-competitive item" wording; current binding force rests mainly on the authorities' fee-extraction and use measures, percentage rate documents, and tendering supervision practice.
Applicable Boundaries
- Applies to tender price ceilings, tenders, interim payments, and settlement of building and municipal projects priced on a bill of quantities basis under GB/T 50500-2024.
- Notes: (1) where industry authorities provide otherwise, follow them — railway "statutory work safety levy (earmarked funds)" per TB 10811-2024 Clause 2.11.9 and TB 10801-2024 Table 3.11.11; highway works per JTG 3830-2018 Clause 3.1.11 (cost of works (construction and installation) excluding the levy x percentage rate, >=1.5%). (2) This card is the 2024-edition caliber; the 2013 clause 4.1.5 lost mandatory force with the GB-to-GB/T change — mind the edition. (3) No specific percentage rates here — take the project location's current authority rate documents; in practice bill and list them separately, never merged into other preliminaries for discounting.
Further Reading
- GB/T 50500-2024: Clause 2.0.4 (term), 3.2.5 (basic provision), 5.2.5 (tender price ceiling), 6.2.6 (tender), 9.3.1 and 9.3.4 (interim payment), Appendix E Table E.3.2.
- Old edition: GB 50500-2013 Clause 4.1.5 (mandatory provisions of codes).
- Industry counterparts: railway TB 10801-2024 Clause 3.11.11 (ten classes of safety-levy uses, no double counting elsewhere); TB 10811-2024 Clause 2.11.9 (3.0% of the cost of works (construction and installation)); highway works JTG 3830-2018 Clause 3.1.11.