ring-fenced (earmarked) use of funds
- 01
The advance payment guarantee for works: amount, validity, step-down with recovery and return rules (GB/T 50500-2024 clause 9.2.5; Jian Ban Shi Han [2004] No. 390 Article 22)
Where the contract requires an advance payment guarantee, the employer p…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第9.2.5条GB/T 50500-2024 第9.2.1条GB/T 50500-2024 第9.2.6条2026-10-18 - 02
Railway work safety fee (mandatory health, safety and environmental (HSE) provisions): calculation rate, non-competitive nature, and earmarked-fund management rules
The railway work safety fee is accrued at 3.0% of the construction and i…
TB 10811-2024 铁路基本建设工程设计概(预)算费用定额TB 10801-2024 铁路基本建设工程设计概(预)算编制办法交通运输部令2017年第25号 公路水运工程安全生产监督管理办法2026-09-25 - 03
Work safety levy for non-railway works (building / municipal / highway / water conservancy): accrual basis, non-competitive nature, and ring-fenced use rules
Building/municipal: the mandatory health, safety and environmental (HSE)…
JTG 3830-2018 公路工程建设项目概算预算编制办法GB/T 50500-2024 建设工程工程量清单计价标准GB 50722-2011 城市轨道交通建设项目管理规范2026-09-25 - 04
Nature and pricing rules of statutory safety provisions (GB/T 50500-2024: non-competitive item, whole-process constraints, and the change in normative force)
GB/T 50500-2024 Clause 3.2.5 states that the statutory safety provisions…
GB/T 50500-2024 建设工程工程量清单计价标准(第2.0.4、3.2.5、5.2.5、6.2.6、9.3.1、9.3.4条,App. ETable E.3.2)GB 50500-2013 建设工程工程量清单计价规范(第4.1.5条,已随版本更新)建办〔2005〕89号 建筑工程安全防护、文明施工措施费用及使用管理规定2026-09-25