Charging night-work and sectional-construction additional fees: percentage-rate and measured-quantity frameworks
Night-work additional fee = night-shift allowance + nighttime efficiency loss + lighting amortization and electricity: percentage-rate method = norm-based labour cost of the nighttime portion × percentage rate; measured-quantity method itemizes each element. Night work within a reasonable programme due to continuous operations is usually already included in the quota norms; only night work forced by the programme or traffic conditions is charged separately. Sectional construction is the policy norm and does not of itself generate fees; its additional fee decomposes into traffic interference + traffic diversion + construction efficiency loss + multiple mobilizations, each charged item by item; the railway sector merges it into preliminaries as a lump sum. Percentage rates differ by province and industry — use the current pricing bases.
Applicable Codes
- GB/T 50875-2013 工程造价术语标准
- SJG 84-2020 市政维修工程消耗量标准
- TB 10801-2024 铁路基本建设工程设计概(预)算编制办法
- DB63/T 2011-2022 公路养护工程预算编制指南
- DB37/T 5299-2024 建设工程文明施工标准
- GB 50861-2013 城市轨道交通工程工程量计算规范
Topic Positioning
This card covers the charging frameworks for two easily confused items of municipal construction additional fees: the night-work additional fee (a standard preliminaries item) and the sectional-construction additional fee (no unified percentage rate; charged by decomposition), covering the percentage-rate method and the measured-quantity method, plus special calibers for railways and Shenzhen.
Core Conclusions
(1) Night-work additional fee = night-shift allowance + nighttime construction efficiency loss + lighting equipment amortization and electricity (GB/T 50875-2013, Clause 2.2.53). Two charging paths: percentage-rate method = norm-based labour cost of the nighttime portion × percentage rate (rate per the current pricing base of the location, e.g., Qinghai highway maintenance bridge category 2.008%); measured-quantity method = Σ(night-shift headcount × days × allowance) + lighting facility amortization and electricity + efficiency-loss. Key caliber: night work within a reasonable programme due to process continuity is usually already included in the quota norms (explicitly stated in Shenzhen SJG 84-2020, Clause 0.4.20); only night work necessitated by the contract programme, site traffic, etc. is charged separately; the railway system does not list it separately but merges it into preliminaries = (base-period labour cost + base-period plant and small tools cost) × percentage rate (TB 10801-2024, Section 3.6). (2) Sectional construction is the policy norm — "excavate a section, construct a section, restore a section, reopen a section" (DB37/T 5299-2024, Clause 5.2.1); it does not of itself generate fees, and the additional fee decomposes into four items: traffic-interference additional fee = (norm-based labour cost + machinery cost) of the interfered section × percentage rate (expressway class I one-way three-lane × 0.65, four-lane × 0.35, classes II–IV × 1.13, DB63/T 2011-2022, Clause 6.1.5.3); traffic diversion / traffic management provisions per project execution plan (construction methodology and site organization) quantities, with the Shenzhen fallback of 2% of the divisional-work total absent a scheme (SJG 84-2020, Clause 0.4.18); construction efficiency loss estimated per the project execution plan (construction methodology and site organization); multiple mobilizations/demobilizations per actual certified records.
Applicable Boundaries
Percentage-rate values differ by province and industry — use the current pricing bases of the project location; the sample values must not be applied directly. Night work requires a permit first and must meet boundary noise limits (night ≤ 55 dB(A)); otherwise charging lacks compliance support. The traffic-interference rate comes from the highway maintenance caliber and is for municipal reference only; the sectional-construction additional fee has no unified national item and must be supported by project execution plan (construction methodology and site organization) schemes and certified records for settlement.
Further Reading
GB/T 50875-2013 Clause 2.2.53; SJG 84-2020 Clauses 0.4.20, 0.4.18, 0.1.12; TB 10801-2024 Section 3.6 (rates per TB 10811); DB63/T 2011-2022 Clause 6.1.5 and Tables 1~9; DB37/T 5299-2024 Clause 5.2.1; GB 50861-2013 Table N.10; T/SZCA 5-2022 Table 0.3.8; noise limits GB 12523.