Estimating rainy-season construction inputs: rate-based charging basis vs quantity-based scheme configuration
The rainy-season construction increment is charged as (quota labor cost + quota construction machinery usage cost) × rainfall-zone/rainy-season rate, amortized over the whole year (highway JTG 3830-2018 Clause 3.1.6; railway folds it into construction measure fees at TB 10811 rates); the construction scheme / flood-control plan uses the quantity method: drainage discharge = catchment area × maximum daily rainfall × runoff coefficient, on which pumps, covering materials, and watch labor are configured.
Applicable Codes
- JTG 3830-2018 公路工程建设项目概算预算编制办法 第3.1.6条、App. E
- JTG 3820-2018 公路工程建设项目投资估算编制办法 App. F
- TB 10801-2024 铁路基本建设工程设计概(预)算编制办法 第3.6条
- TB 10811 铁路基本建设工程设计概(预)算费用定额
- JGJ 180-2009 建筑施工土石方工程安全技术规范 第4.2.2条
Topic Positioning
The two calculation paths for rainy-season construction costs: the rate-charging method for the "rainy-season construction increment" under estimate/budget conventions, and the quantity configuration method for drainage, covering, and labor under the construction scheme / flood-control plan — applicable to highway, railway, and building/municipal earthworks.
Core Conclusions
- Pricing basis (rate method): rainy-season increment = (quota labor cost + quota construction machinery usage cost) × rate. The rate is looked up by the rainfall zone and rainy-season period of the project location and amortized over the whole year — charged whether or not construction occurs in the rainy season; where one route crosses several zones/periods, calculate separately or weight-average by work quantity. Cost contents include rainy-season efficiency loss, temporary drainage ditches and pit strutting/splash boards, material damp damage, rain- and moisture-proofing equipment, etc. The railway basis folds it into construction measure fees: measure fee = (base-period labor cost + base-period construction plant usage cost) × rate.
- Scheme basis (quantity method): first compute the discharge Q = catchment area × maximum daily rainfall × runoff coefficient (plus groundwater inflow), with the maximum daily rainfall based on meteorological data and chosen per the importance of the works; round up pumps as n = Q ÷ (unit pump capacity × daily running hours × efficiency) and add standby pumps; meanwhile provide drainage ditches (bottom width ≥0.3 m, slope ≥0.1%) and sump pits (diameter ≥0.6 m, floor ≥0.5 m below ditch bottom); covering area = protected area × (1 + lap wastage 10%–15%); labor by watch/patrol/emergency posts, or by quota labor contents (e.g., man-days per 10 m³ of wet soil for pit pumping).
Applicable Boundaries
The rate method is only for estimate/budget pricing and does not itemize equipment/materials; the quantity method is for construction schemes, flood-control plans, and cost budgeting — the two must not be mixed. Rate values vary by region, industry, and project class and must follow the current local quota; catchment area, rainfall, and runoff coefficient must be taken from project conditions and meteorological data — the demo values cannot be applied directly.
Further Reading
Highway: JTG 3830-2018, Measures for Compiling Estimates and Budgets of Highway Construction Projects, Clause 3.1.6 and Appendix E (rainfall-zone and rainy-season zoning, Table 3.1.6-2 rates); JTG 3820-2018, Measures for Compiling Investment Estimates of Highway Construction Projects, Appendix F, same basis. Railway: TB 10801-2024, Measures for Compiling Design Estimates (Budgets) of Railway Capital Construction Works, Clause 3.6 (construction measure fees), rates per TB 10811, Quota of Fees for Design Estimates (Budgets). Discharge basis: JGJ 180-2009, Code for Safety of Earthwork and Blasting Works in Building Construction, Clause 4.2.2. Local maintenance works follow the corresponding rate tables of the local maintenance budget quota.
Keywords
- 雨季施工增加费
- 雨季施工
- preliminaries
- 泄排量
- 汇水面积
- 雨量区
- 排水设备
- 覆盖材料