Division of bases for winter construction: definition per JGJ/T 104-2011, cost measurement per the pricing system (highway JTG 3830-2018 / building-municipal Jian Biao [2013] No. 44)

JGJ/T 104-2011 remains in force (record no. J 1189-2011); Article 1.0.3 defines: winter construction begins when the daily mean outdoor temperature stays below 5C for 5 consecutive days and ends when it stays above 5C for 5 consecutive days; sudden cold snaps dropping below 0C before winter requires emergency protection per winter rules. But that code is a workmanship specification with no fee rates—winter-increase costs follow the pricing system: highway per JTG 3830-2018 Article 3.1.6 (quota labor + quota machinery) x temperature-zone rate, amortized annually, greening excluded; building/municipal per Jian Biao [2013] No. 44 and local bases as preliminary-item costs; terminology per GB/T 50875-2013 Article 2.2.55.

Applicable Codes

  • JGJ/T 104-2011 建筑工程冬期施工规程
  • JTG 3830-2018 公路工程建设项目概算预算编制办法
  • GB/T 50875-2013 工程造价术语标准
  • 建标〔2013〕44号 建筑安装工程费用项目组成

Topic Positioning

Clarifies a common misconception about "the latest basis for winter construction": definition and cost measurement are two systems—when it counts as winter follows workmanship code JGJ/T 104-2011; how to cost it follows the pricing system (highway JTG 3830-2018; building/municipal Jian Biao [2013] No. 44 and local quotas).

Core Conclusions

  1. Definition standard: JGJ/T 104-2011 Specification for Winter Construction of Building Engineering remains in force (record no. J 1189-2011, not superseded). Article 1.0.3: per multi-year local meteorological statistics, winter construction begins when the outdoor daily mean temperature stays below 5C for 5 consecutive days, and ends when it stays above 5C for 5 consecutive days; if a cold snap drops the temperature below 0C before winter begins, emergency protection per winter construction requirements shall also be taken.
  2. Division of bases: that code is a workmanship specification governing only technical measures—insulation, heating, temperature measurement—with no fee rates; measuring winter-increase costs turns to the pricing system.
  3. Highway: JTG 3830-2018 Article 3.1.6—base = quota labor cost + quota construction machinery cost, rate per temperature zone in Appendix D Table 3.1.6-1, amortized over the whole year (regardless of actual winter work); greening excluded; across temperature zones, split by sections or weight by work quantity.
  4. Building/municipal: winter-and-rainy-season increase costs are preliminary items; base and rates per Jian Biao [2013] No. 44 and the project location's current pricing bases. Terminology per GB/T 50875-2013 Article 2.2.55.

Applicable Boundaries

This card answers "where to find the basis"; specific rates must follow the project location's current temperature-zone/local-quota edition; railway works follow the TB 10811 construction-measures fee system (see the referenced card); where individual discipline codes (e.g., masonry) supplement the winter period, those prevail.

Further Reading

  • Definition principle and cold-snap emergency clause: JGJ/T 104-2011 general provisions, Article 1.0.3
  • Highway rates: JTG 3830-2018 Measures for Compiling Estimates and Budgets of Highway Construction Projects, Article 3.1.6, Appendix D temperature zones, Table 3.1.6-1
  • Cost composition: Jian Biao [2013] No. 44 Composition of Building and Installation Cost Items
  • Terminology: GB/T 50875-2013 Standard for Construction Cost Terminology, Article 2.2.55