Winter concreting: mixer-discharge and placing temperatures and critical strength against freezing (GB 50666-2011, JGJ/T 104-2011, DB11/T 1832.3-2021)

In winter, the mixer-discharge temperature of concrete should not be below 10 degrees C (ready-mixed/long-haul concrete preferably not below 15), and the placing temperature shall not be below 5 degrees C; the critical strength against freezing is graded by method and conditions: thermal storage/heated enclosure/heating methods — 30% of the design strength grade value (Portland/ordinary Portland cement) or 40% (slag/fly-ash/pozzolanic/composite); comprehensive thermal storage/negative-temperature curing — 4.0MPa when the outdoor minimum is not below -15 degrees C and 5.0MPa when not below -30; C50 and above preferably not below 30%; impermeable concrete preferably not below 50%; freeze-thaw durability concrete not below 70%. GB 50666-2011 cl. 10.2.7/10.2.12 and JGJ/T 104-2011 cl. 6.2.6/6.1.1 match numerically; Beijing DB11/T 1832.3-2021 cl. 34.4.14/34.4.6 is identical.

Applicable Codes

  • GB 50666-2011 混凝土结构工程施工规范 第10.2.7、10.2.12条
  • JGJ/T 104-2011 建筑工程冬期施工规程(备案号 J 1189-2011)第6.1.1、6.2.6条、App. A
  • DB11/T 1832.3-2021 建筑工程施工工艺规程 第3部分:混凝土结构工程 第34.4.6、34.4.14条

Topic Positioning

This card consolidates the two core temperature-control parameter sets of winter concreting: (1) lower limits of mixer-discharge and placing temperatures (GB 50666-2011 cl. 10.2.7; JGJ/T 104-2011 cl. 6.2.6); (2) the graded critical strength against freezing (GB 50666-2011 cl. 10.2.12; JGJ/T 104-2011 cl. 6.1.1 — the two codes agree numerically and link up), plus the corresponding Beijing local clauses. For winter concreting schemes, disclosure and site quality checks.

Core Conclusions

I. Discharge and placing temperatures

  • GB 50666-2011 cl. 10.2.7: "The discharge temperature of the concrete mix should not be below 10 degrees C and the placing temperature shall not be below 5 degrees C; for ready-mixed concrete or concrete requiring long hauls, the discharge temperature may be set by thermal calculation per distance but should not be below 15 degrees C."
  • The placing temperature of mass concrete may be appropriately lowered, provided insulation measures ensure the fresh concrete does not freeze after placement and before the hydration-heat rise.
  • Commentary points: with 10 degrees C discharge, transport and conveying losses leave only 5 degrees C at placing; ready-mixed concrete travels far and long with high losses, so discharge is generally raised above 15 degrees C; trucks and pump lines shall be insulated; multiple transfers during transport, conveying and placing shall be minimized in winter.
  • JGJ/T 104-2011 cl. 6.2.6: temperatures during transport and placing and the insulation cover materials shall be determined by thermal calculation per Annex A of that specification, with placing temperature not below 5 degrees C, adjusting where non-compliant. Placing temperature governs the initial heat storage of curing and freeze prevention.
  • Beijing DB11/T 1832.3-2021 cl. 34.4.14: discharge temperature not below 10 degrees C, placing temperature not below 5 degrees C.

II. Critical strength against freezing (GB 50666-2011 cl. 10.2.12 = JGJ/T 104-2011 cl. 6.1.1, 7 items) Definition: the minimum strength winter-placed concrete must reach before freezing without suffering frost damage; once reached, freezing does not affect later strength and performance. Insulation/enclosures may be removed and steam or electric heating stopped only after reaching it. 1 Thermal storage, heated enclosure or heating methods: concrete with Portland or ordinary Portland cement — not below 30% of the design strength grade value; with slag Portland, fly-ash Portland, pozzolanic Portland or composite Portland cement — not below 40%. 2 With outdoor minimum temperature not below -15 degrees C, concrete by comprehensive thermal storage or negative-temperature curing — critical strength not below 4.0MPa; with outdoor minimum not below -30 degrees C, negative-temperature curing — not below 5.0MPa. 3 Strength grade C50 and above: preferably not below 30% of the design strength grade value. 4 Impermeable concrete: preferably not below 50%. 5 Concrete with freeze-thaw durability requirements: not below 70%. 6 Where an accelerator is added in heated-enclosure concreting, the comprehensive thermal storage value may be adopted. 7 Where the strength grade is raised for construction needs, the critical strength follows the raised grade.

  • Beijing DB11/T 1832.3-2021 cl. 34.4.6: winter concrete preferably by thermal storage/comprehensive thermal storage; with outdoor minimum not below -15 degrees C, comprehensive thermal storage critical strength not below 4.0MPa; C50+ preferably not below 30%; impermeable preferably not below 50%; freeze-thaw durability not below 70%. Early strength may be estimated by the maturity method and confirmed by site same-condition cured specimen reports, per JGJ/T 104.

Applicable Boundaries

  • GB 50666-2011 and JGJ/T 104-2011 are general building-system codes; DB11/T 1832.3-2021 is Beijing local — other regions execute their current local standards, using these values as reference.
  • The critical strength must be taken separately by method (storage/enclosure/heating vs comprehensive storage/negative-temperature curing), cement type, outdoor minimum temperature, strength grade and impermeability/frost requirements — no single blanket value; 4.0/5.0MPa apply only to comprehensive thermal storage and negative-temperature curing, split by outdoor minimum temperature.
  • Values based on current versions: GB 50666-2011, JGJ/T 104-2011 (record J 1189-2011), DB11/T 1832.3-2021.
  • Entry/exit of the winter season (outdoor daily mean below 5 degrees C for 5 consecutive days to enter, above for 5 days to exit) is JGJ/T 104-2011 cl. 1.0.3, used with this card.

Further Reading

  • GB 50666-2011 cl. 10.2.7 and cl. 10.2.12 with commentary (Chapter 10 winter, hot and rainy season); the basis of critical-strength values (21%-34% research on high-strength concrete, P6-P8 impermeability converted to 50%, domestic/foreign comparisons) in the commentary.
  • JGJ/T 104-2011 Specification for Winter Construction of Building Engineering, cl. 6.1.1 and 6.2.6; thermal calculations for transport/placing temperatures and insulation per Annex A.
  • DB11/T 1832.3-2021 cl. 34.4.6 and 34.4.14 (Chapter 34 winter construction).
  • Winter-season criteria and winter-construction cost calibers in the cited cards (JGJ/T 104-2011 cl. 1.0.3 definition; highway/building pricing systems).