Definition of winter construction and calculation of the winter construction cost increment

Winter construction begins when the outdoor daily mean temperature stays stably below 5 °C for 5 consecutive days and ends when it stays above 5 °C for 5 consecutive days; the winter construction increment is charged under the industry quota — railway folds it into construction measure fees as (base-period labor cost + base-period construction plant usage cost) × rate (16 project classes × 8 region codes, Table 2.6.1); highway uses (quota labor cost + quota construction machinery usage cost) × temperature-zone rate, amortized over the whole year.

Applicable Codes

  • JGJ 104-97 建筑工程冬期施工规程
  • GB/T 50875-2013 工程造价术语标准
  • TB 10811-2024 铁路基本建设工程设计概(预)算费用定额
  • JTG 3830-2018 公路工程建设项目概算预算编制办法
  • GB/T 50900-2016 村镇住宅结构施工及验收规范

Topic Positioning

The start/end definition of winter construction, and how the winter construction increment is calculated under the railway, highway, and other quota systems, plus the actual-cost approach when no rate basis exists.

Core Conclusions

  1. Definition: winter construction begins when the outdoor daily mean temperature stays stably below 5 °C for 5 consecutive days, and ends when it stays above 5 °C for 5 consecutive days (uniformly stipulated by JGJ 104, Specification for Winter Construction of Building Works). The daily mean is the average of the day's maximum and minimum; start/end dates shall be determined from multi-year local meteorological statistics; "stably" is the key word — a cold snap dropping to 0 °C followed by a warm-up does not start winter construction, and isolated warm days do not end it.
  2. Cost nature (GB/T 50875-2013): expenses for reduced construction efficiency and increased inputs caused by winter/rainy-season weather, and for measures such as insulation and rain protection.
  3. Railway (TB 10811-2024): the winter/rainy-season increment is folded into preliminaries: preliminaries = (base-period labour cost + base-period plant and small tools cost) × preliminaries rate; rates are looked up in Table 2.6.1 by 16 project classes × 8 region codes; heavy temporary works take the same-class formal works rate × 0.45, and transition works the same-class formal works rate.
  4. Highway (JTG 3830-2018): winter construction increment = (norm-based labour cost + norm-based plant cost) × temperature-zone rate (Appendix D zoning, Table 3.1.6-1), amortized over the whole year — charged at the rate regardless of whether construction actually occurs in winter; greening works are excluded.
  5. Where no rate basis exists, calculate from the approved winter construction method statement at actual cost: insulation materials, heating/curing energy, labour inefficiency compensation, temperature monitoring, and other special costs.

Applicable Boundaries

The definition applies to all disciplines in China's continental monsoon climate zones; individual codes add supplements (e.g., masonry codes: works outside the winter period where the day's minimum falls below 0 °C shall also follow winter-construction rules). The rate method applies only to projects under the corresponding industry quota system; rates are updated with standard revisions and local cost information, and the current valid pricing basis governs; building and municipal local quotas usually list the winter/rainy-season increment under preliminary items, with the base to which percentage rates are applied and rates per the current rules of the project location.

Further Reading

  • Definition principle and argumentation (temperature statistics table, cross-country code comparison): JGJ 104, Specification for Winter Construction of Building Works, general provisions; GB/T 50900-2016, Clause 3.3.5.
  • Railway rates: TB 10811-2024, Quota of Fees for Design Estimates (Budgets) of Railway Capital Construction Works, Clause 2.6.1, Table 2.6.1, Appendix B (preliminaries regional zoning).
  • Highway rates: JTG 3830-2018, Measures for Compiling Estimates and Budgets of Highway Construction Projects, Clause 3.1.6, Appendix D (winter temperature-zone zoning), Table 3.1.6-1.
  • Terminology: GB/T 50875-2013, Standard for Construction Cost Terminology, Clause 2.2.55.