Sources, bases and regional treatment of night-work additional cost rates: highways under JTG 3830-2018 Table 3.1.6-3 as a separate item; railways folded into the composite construction-measures rate of TB 10811-2024 Table 2.6.1 (16 works classes x regions 1-8); building and municipal works per provincial fee norms on base x rate

No unified national rate exists for night-work additional cost; the taking follows each sector's pricing system: 1) highways - JTG 3830-2018 clause 3.1.6 item 3 and Table 3.1.6-3, on the base of norm labour plus norm plant of the night-work items: structures II 0.903%, structures III 1.702%, technically complex major bridges 0.928%, steel and steel structures 0.874%, rates not regionalised; 2) railways - no separate item, folded into construction-measures cost per TB 10811-2024 Table 2.6.1's 16 works classes x regions 1-8 composite rates on base-period labour plus plant; 3) building / municipal works - the provincial fee norm's 'night-work addition = base x rate', the base being norm base price, norm labour or labour plus plant as the local pricing authority fixes - no cross-province borrowing.

Applicable Codes

  • TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第3.6.1~3.6.4条
  • TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works 第2.6.1条、Table 2.6.1、App. B
  • JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.6条第3款、Table 3.1.6-3
  • GB/T 50875-2013 · Standard glossary of project costs 第2.2.53条
  • 省级建筑安装工程费用定额(2024 版)措施项目费—不宜计量措施项目取费条文

Positioning

The night-work addition is a "not-readily-measurable" preliminaries item with no national rate: the source, base and regional treatment all depend on the sector's pricing system. This card gives the taking paths for highways, railways and building/municipal works with the original texts - which table to check, on what base, and how region enters the price.

Core conclusions

1. Highways: one national rate table, listed separately (JTG 3830-2018 clause 3.1.6 item 3)

"The night-work addition covers night-shift allowances, night-work efficiency loss, amortisation of lighting equipment and lighting power arising where design, technical specifications and sound construction organisation require night work or round-the-clock continuity. It is computed on the sum of norm labour and norm plant of the night-work items at the rates of Table 3.1.6-3." Table 3.1.6-3 (%): structures II 0.903; structures III 1.702; technically complex major bridges 0.928; steel and steel structures 0.874. Note: "equipment installation and metal signboards, crash barriers, anti-glare screens (nets), fencing and protective nets bear no night-work addition." Points: 1) the table is national - rates are not regionalised, regional differences entering through labour prices, winter temperature zones and levies; 2) only the four listed classes attract it - ordinary earthworks, haulage and pavements do not; 3) the base is the norm labour and plant of "the night-work portion", not the whole unit works or line.

2. Railways: folded into the composite construction-measures rate, never listed separately

Definition (TB 10801-2024 clause 3.6.2 item 2): "The night-work addition covers efficiency loss and night-shift allowances arising in continuous night work or track ballasting and laying in tunnels, cable laying, catenary erection etc., plus added lighting facilities (including their erection and removal, amortisation, maintenance and fuel/power)." It is one of the seven items of construction-measures cost (clauses 3.6.1-3.6.2). Computation (clause 3.6.3): "construction-measures cost = (base-period labour + base-period plant) x the construction-measures rate"; clause 3.6.4: the rates follow TB 10811. Rates (TB 10811-2024 clause 2.6.1): "construction-measures cost is computed on the sum of base-period labour and base-period plant of each works class x its rate, per the regional division table (Appendix B) and Table 2.6.1." Table 2.6.1 gives rates (%) by 16 works-class codes x regions 1-8 - e.g. class 4 major bridge substructures 4.9/4.3/6.0/6.7/7.1/7.1/7.8/7.9; class 1 hand-worked earthworks 5.8~10.7; class 5 precast concrete beams 9.9~18.8; class 13 ballastless track and related works 11.9~20.9. The highest and lowest regions differ by about 1.8x - look up the project's region in Appendix B, never by guesswork. Table notes: 1) heavy temporary works take the corresponding formal-works rate x 0.45; 2) transition works take the corresponding formal-works rate. Key point: within the railway system the night-work addition has no standalone rate - applying the composite rate suffices, and listing it again is double pricing.

3. Building / municipal works: provincial fee norms, three possible bases

Term (GB/T 50875-2013 clause 2.2.53): night-work addition - "preliminaries costs of night-shift allowances, night-work efficiency loss, lighting equipment amortisation and lighting power arising from night work." Method (for items not readily measurable): "night-work addition = base x rate (%)", the base being the norm base price (norm work-item cost plus measurable preliminaries), norm labour, or labour plus plant, with rates fixed by the cost administration per discipline. Which base and what rate are set by the current provincial fee norm of the project location - no national value. Path: current provincial fee norm - "preliminaries - night-work addition" - take that table's rate and base. At tender, free quotation; at settlement per the contract (fixed rate, or actual per the approved night-work scheme). On actuals: night-shift allowances = actual night shifts x standard; efficiency loss and lighting = the night portion's labour x factor, or equipment amortisation plus power - always scoped to the night-work portion, not the whole unit works.

Applicable boundaries

  1. No cross-system borrowing: highway rates never apply to railways (already inside the composite), railway composites never to building/municipal works, provincial rates never across provinces.
  2. Railways list no separate night-work item (double pricing with construction-measures cost); highways charge only the four listed classes (ordinary earthworks, haulage etc. excluded).
  3. Bases differ: highways - norm labour + plant of the night-work items; railways - base-period labour + plant (base-period prices, excluding material costs and price differentials), unlike the special-construction addition based on current-period labour and plant.
  4. Exclusions follow each system: on highways, equipment installation and metal signboards, crash barriers, anti-glare screens, fencing and nets are excluded - a different exclusion set from the rainy-season addition (indoor, tunnel and installation works) - never cite one for the other.
  5. Rates are current-edition values - re-verify after any quota revision.