Why the all-in unit rate under GB/T 50500-2024 excludes VAT: price-exclusive tax character, separation of net price and VAT, the rationale for listing taxes and duties (VAT under the current standard) separately, and practical reasons
Under GB/T 50500-2024, the all-in unit rate = labour cost + material cost + plant and small tools cost + management fee + profit + risk costs within the agreed scope and risk band (no-adjustment tolerance, e.g. ±5%) (incl. auxiliary work costs), excluding VAT. Four reasons: (1) VAT is a price-exclusive tax (2.0.9), not a production-factor cost of completing the billed (BOQ) item; (2) separation of net price and VAT — unit rates and totals are fully inclusive prices excluding VAT, with taxes and duties (VAT under the current standard) reflected in VAT (3.1.6); (3) taxes and duties listed separately and calculated uniformly — VAT = (bills of work items + bill of preliminaries + bill of provisional sums and other charges, except provisional sums for nominated specialist subcontract works) × the prescribed VAT rate (3.2.11); (4) practically, avoiding "tax on tax" and interfacing with the input VAT credit chain.
Applicable Codes
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works
- GB/T 50875-2013 · Standard glossary of project costs
Topic Positioning
This card answers "what costs compose the all-in unit rate under GB/T 50500-2024 and why VAT is excluded", giving the complete reasoning chain from the price-exclusive tax character and separation of net price and VAT to the separate listing and unified calculation of taxes and duties. For the composition detail, see the referenced card (all-in unit rate definition and cost composition).
Core Conclusions
(1) Composition. Per term 2.0.9, the all-in unit rate is "the cost of completing one unit quantity of a billed (BOQ) item, taking into account technical standards, duration, sequence, conditions, geography and climate, and risks within the agreed scope and risk band (no-adjustment tolerance, e.g. ±5%)", "including labour cost, material cost, plant and small tools cost, management fee, profit, and risk costs within a certain range, excluding VAT", expressly stating "VAT is a price-exclusive tax; the all-in unit rate excludes VAT". 3.1.6 adds: unit rates and totals shall be "fully inclusive prices excluding VAT", additionally "including the risk costs within the agreed or reasonable risk band for the corresponding billed (BOQ) item, and the costs required for indispensable auxiliary work".
(2) Why VAT is excluded — four layers of logic: (1) Price-exclusive tax character (qualification): VAT is levied in circulation and ultimately borne by the buyer (employer); it is not a production-factor cost the contractor incurs to complete the item, hence not part of the all-in unit rate composition. (2) Separation of net price and VAT (pricing basis): 3.1.6 requires unit rates and totals to be "fully inclusive prices excluding VAT" with "the corresponding taxes and duties (VAT under the current standard) reflected in VAT, not included in the unit rate, its amounts, or amounts for items priced by item" — the whole bill of quantities uniformly adopts "net price + separately listed taxes and duties"; the all-in unit rate is always net of VAT. (3) Taxes and duties listed separately, calculated uniformly (method of calculation): 3.2.11 — "VAT shall take the combined amounts of the bill of work items, the bill of preliminaries, and the bill of provisional sums and other charges (except provisional sums for nominated specialist subcontract works) as the calculation base, multiplied by the VAT rate prescribed by the competent government department" ; "the total amount of the bill of provisional sums and other charges used to calculate VAT shall deduct the provisional sums for nominated specialist subcontract works it contains" — because those provisional sums are estimated amounts already including VAT (3.1.6); not deducting them would result in double taxation. (4) Practical reasons: spreading VAT into individual all-in unit rates inflates the bases for management fee and profit — "tax on tax"; and under the general VAT scheme the contractor can credit input VAT invoices, so the tax is not its actual cost. Separation of net price and VAT keeps the calculation base consistent, makes net price and VAT transparent, and interfaces with the input VAT credit chain after the VAT reform.
Applicable Boundaries
The above is the GB/T 50500-2024 basis (recommended national standard, replacing the former mandatory GB 50500-2013), applicable to pricing on a bill of quantities basis for building and general installation works; the 2024 edition has removed the separate item for statutory levies and fees (social insurance and housing fund are estimated by bidders and spread into labour unit rates and management fee percentage rates), producing an "incomplete-cost" all-in unit rate excluding statutory levies and fees and taxes and duties. In highways and other sectors (e.g. DB14/T 1319 highway bill of quantities specification), the all-in unit rate may be a fully loaded basis including permanent equipment procurement cost, preliminaries, statutory levies and fees, and taxes and duties — always confirm the sectoral/local pricing basis before citing; do not mix them. Under the simplified VAT scheme, VAT is calculated at the deemed levy rate; the logic of listing taxes and duties separately and not including them in the unit rate is the same.
Further Reading
See the China national pricing standard for BOQ (GB/T 50500-2024): 2.0.9 (term; VAT as a price-exclusive tax), 3.1.6 (fully inclusive price excluding VAT; taxes and duties reflected in VAT; provisional sums for nominated specialist subcontract works include VAT), 3.2.11 (VAT calculation base and deduction of provisional sums for nominated specialist subcontract works), 4.2.8 (VAT listed separately); GB/T 50875-2013 "Standard for construction cost terminology" 2.2.58 same basis. The continuation of separation of net price and VAT in price adjustments is set out in Section 8.4 (after the actual price of a provisional sum for specified materials / nominated works is determined, VAT is calculated only on the price difference, with the adjustment calculated separately).