A six-dimension framework for unifying cost-data calibers across projects (cost composition / quantities / tax / time / allocation / tagging)
Caliber unification = fixing one set of "comparable benchmarks" across six dimensions: (1) cost composition unified to the fully loaded all-in rate basis (covering labour, materials, plant, overheads, profit, statutory levies and fees and taxes); provincial quota systems often state only that it "should" be adopted, so a conversion comparison table must be built and kept on file as an audit trail; (2) quantities unified to BOQ quantities or quota quantities and labelled; (3) prices stored uniformly tax-exclusive with the taxation method recorded; (4) time basis: the feasibility-stage estimate, the preliminary estimate and the tender price ceiling take the date the deliverable was completed, the contract price takes the commencement date, and the settlement price takes the completion date, with cross-period conversion via construction cost indices (base date 2017-01-01, index 1000); (5) allocation rules unified by project-type templates; (6) labelling across four dimensions: region – project type – cost type – time. Basis: GB/T 51095-2015, GB/T 50500-2024, GB/T 51290-2018, etc.
Applicable Codes
- GB/T 51095-2015 建设工程造价咨询规范
- GB/T 50500-2024 建设工程工程量清单计价标准
- GB/T 51290-2018 建设工程造价指标指数分类与测算标准
- DBJ/T 15-153-2019 广东省建设项目全过程造价管理规范
- DB42/T 823-2021 建设工程造价咨询质量控制规范
Topic Positioning
A general methodology for unifying cost-data calibers across projects: converting each project's cost data onto the same set of "comparable benchmarks", solving the problem that "everything seems comparable on the surface but actually is not". Used for cost-indicator database building, horizontal comparison of historical data, and pre-processing before cost forecasting.
Core Conclusions
Caliber unification = fixing comparable benchmarks across six dimensions: (1) cost composition — unified to the fully loaded all-in rate basis (covering labour, materials, plant, overheads, profit, statutory levies and fees and taxes); note that provincial quota systems often state only that all-in prices "should" be adopted (e.g., DB42/T 823-2021, Clause 6.3.8), so a "cost-composition conversion table" must be built and kept on file as an audit trail; (2) quantities — unify to BOQ quantities or quota quantities, calculated per the appendix rules of each discipline's method of measurement and labelled with the caliber; (3) tax in prices — store uniformly as tax-exclusive prices with the taxation method recorded; VAT takes as its base the aggregate of the billed (BOQ) items, the bill of preliminaries and the bill of provisional sums and other charges (less the provisional sum for nominated specialist subcontract works); (4) time basis — the feasibility-stage estimate, the preliminary estimate and the tender price ceiling take the date the deliverable was completed, the contract price takes the commencement date, and the settlement price takes the completion date; cross-period comparison uses cost-index conversion (base date 2017-01-01, index 1000, two decimal places); (5) allocation rules — set indicator-analysis templates and cost-allocation rules by project type, unifying allocation principles and keeping indicator scope and content consistent; (6) tagging system — four-dimension labelling by region (down to county/district), project type, cost type, and time.
Applicable Boundaries
Applies to construction cost data management and horizontal indicator comparison; it does not clean "dirty" data (that is data cleaning) nor replace specific pricing-standard provisions. Caliber differences exist between national BOQ/consultancy standards and provincial quota systems, and the 2013 and 2024 versions list statutory levies differently (the 2024 version removes the separate statutory-levy line item and absorbs it into the all-in unit rate), so the version caliber must be confirmed before unifying.
Further Reading
GB/T 51095-2015 Clauses 5.2.9, 5.3.8 (fully loaded all-in rate and cost composition of the preliminary estimate); GB/T 50500-2024 Clause 3.2.11 (VAT calculation base); GB/T 51290-2018 Clauses 3.0.2, 3.0.3, 6.0.2 (time caliber, four-dimension classification, index base period); DBJ/T 15-153-2019 Clauses 8.3.3, 8.3.4 (indicator templates and cost allocation); DB42/T 823-2021 Clause 6.3.8 (provincial-quota vs national-standard caliber difference).
Keywords
- 口径统一
- 造价数据
- 可比基准
- fully loaded all-in rate (incl. taxes and specified on-costs)
- 造价指标
- 数据清洗