Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Costing temporary access roads (temporary bridges) during road construction: preliminary items listing and three rate build-up paths

Temporary access roads are preliminaries: municipal works list them as "item" per GB/T 50857-2024 Appendix M (041201008 access road / 041201009 temporary bridge), with rate build-up quantities per the approved project execution plan (construction methodology and site organization); three paths — applying quota items (highway JTG/T 3832-2018 7-1-1 truck access road per 1 km, maintenance per 1 km-month charged separately), quantity takeoff (earthwork + pavement + drainage + maintenance + removal and restoration), percentage rate fallback (no special scheme: charge as incurred per the project execution plan; some regional standards allow 2% of the total of the divisional and subdivisional works); temporary bridges amortized with recoverable-material credits; maintenance is the most easily missed.

Applicable Codes

  • GB/T 50857-2024 市政工程工程量计算标准
  • JTG/T 3832-2018 公路工程预算定额
  • GB/T 50903-2013 市政工程施工组织设计规范
  • SJG 84-2020 市政维修工程消耗量标准

Topic Positioning

How to cost temporary access roads and bridges during road (municipal/highway) construction: BOQ listing attribution, three rate build-up paths, cost composition, and easily missed items — generic pricing knowledge.

Core Conclusions

Temporary access roads are preliminaries. The municipal BOQ lists them per GB/T 50857-2024 Appendix M: 041201008 access road, 041201009 temporary bridge (unit "item"; work content includes laying, compaction, and removal/cleanup). Although the BOQ lists by "item", rate build-up quantities must follow the approved project execution plan (construction methodology and site organization). Three rate build-up paths: (1) BOQ + quota norms: apply local municipal quota norms for temporary-road sub-items; for highways apply JTG/T 3832-2018 Chapter 7 7-1-1 truck access road (unit 1 km, subgrade width 7.0 m/4.5 m in two grades, including passing bays), maintenance charged separately per 1 km-month; (2) quantity takeoff: where work items are not covered by the quota manuals, take off quantities per the scheme — cut/fill earthwork, gravel pavement, drainage ditches, maintenance, removal and restoration; (3) percentage rate fallback: without a special scheme, charge as incurred per the project execution plan; some regional standards (SJG 84-2020) allow 2% of the total of the divisional and subdivisional works as "traffic management provisions". Six cost elements: subgrade earthwork, pavement structure, drainage facilities, maintenance, removal and cleanup, restoration to original state. Key points: temporary bridges are amortized (7-1-2 is compiled for 4 m clear bridge-deck width and 4-month equipment amortization; different usage periods adjust proportionally); recoverable materials are credited per rules; maintenance fees are the most easily missed.

Applicable Boundaries

Applies to costing temporary traffic access roads and bridges in municipal/highway works. River/creek-crossing temporary bridges are separately billed items, not merged into access roads; removal-and-restoration responsibilities follow the contract to avoid double charging; quota norms and percentage rates differ by region — apply the current local standards and published price information (government guidance prices). This card is a method framework without specific amounts.

Further Reading

GB/T 50857-2024 Appendix M preliminary items (041201008 access road, 041201009 temporary bridge); JTG/T 3832-2018 Chapter 7 7-1-1 truck access road, 7-1-2 temporary bridge, 7-1-3 temporary wharf; GB/T 50903-2013 Clause 6.7.1 traffic organization measures; SJG 84-2020 general provisions (traffic-relief costs charged per the design or the project execution plan (construction methodology and site organization)).

Keywords

Cited By