Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-25

Choosing among the three bases of material price adjustment (bid price / base-period published information / jointly confirmed price): statutory sources, defaults, difference-rate versus risk-band linkage and item-by-item locking (GB/T 50500-2024 term 2.0.21, Appendix A.2, G.2.1)

Per GB/T 50500-2024 Appendix A.2.1, the base price C0 is 'the market price level at the base date (28 days before the tender deadline; non-tendered, 28 days before contract signature)' with only three statutory sources: the market prices used for the tender price ceiling, the cost authority's current-quarter (month) published information, and award prices of like works from the trading centre of the same period and conditions - the tenderer must state the source, publisher and specific quarter (month). The bid price is thus not a statutory C0 source (Table G.2.1-1: base price and risk band by the tenderer, bid price by the bidder), and the confirmed price corresponds in A.2.1 to a source of the current period price Ci - both rise to C0 only by express contract. Difference rate = (Ci - C0) / C0 x 100%; against the risk band r only the excess adjusts: rising, unit difference = Ci - C0 x (1 + r); falling, = C0 x (1 - r) - Ci; the amount x Q carries VAT only, never overheads or profit (3.3.5); absent an agreed band, swings beyond 5% adjust (8.7.2).

Applicable Codes

  • GB/T 50500-2024 术语第2.0.21条(合同基准日)
  • GB/T 50500-2024 App. A.2.1(基准价三来源与价差公式)
  • GB/T 50500-2024 App. A.2.2(暂按信息价计算后按实调整)
  • GB/T 50500-2024 App. A.2.4(报价与基准价三种关系的计算基数)
  • GB/T 50500-2024 App. A.2.5(采购前报发包人核对确认)
  • GB/T 50500-2024 App. G.2.1 Table G.2.1-1/Table G.2.1-2
  • GB/T 50500-2024 第8.7.1条
  • GB/T 50500-2024 第8.7.2条
  • GB/T 50500-2024 第3.3.5条

Positioning

Practice names three bases for C0 - bid price, base-period published information, confirmed price. This card fixes their statutory standing, election and agreement requirements, defaults absent agreement, the difference-rate and risk-band computation, and base-price locking and item-by-item rules - for adjustment disputes and contract drafting.

Core conclusions

1. The statutory standing of the three (the premise of choice)

A.2.1 defines C0 as 'the market price level at the base date', sourced only from: (1) the market prices used by the employer in fixing the tender price ceiling; (2) the current-quarter (month) published information of the cost authority; (3) award prices of like works, same period (within one month), same conditions, published by the local trading centre. All 'shall represent the market level 28 days before the tender deadline (non-tendered, 28 days before signature); the tenderer shall state in the tender documents the source, publisher and specific quarter (month)'. So the three are unequal: the bid price is an offer (the priced in-contract rate), not a statutory C0 source - Table G.2.1-1 note 1: 'the tenderer fills in the number, name, specification, unit, base price and risk band; the bidder fills the bid price'; the confirmed price corresponds in A.2.1 to a source of Ci ('the market price of the measurement period confirmed by the parties'). Only express contract terms elevate the bid rate to C0 or the confirmed price of unlisted materials to C0 - the watershed of settlement disputes.

Basis Standing When used Agreement essentials Main risks
(1) Bid price Not statutory in A.2.1; the comparison side in A.2.4; the 'bid price' column by the bidder Special / custom materials outside published information; own-procurement lump-sum materials; contracts expressly adjusting on priced rates State 'the bid rate is the adjustment base'; complete the tender appendix and G.2.1-1; fix VAT-inclusive or not, freight and custody content; fix the band Discounted bids depress the base - adverse on falls; confusing with A.2.4's bid-versus-base rules mis-sets the base
(2) Base-period information Source 2 of C0; dual-information cases under A.2.4 Government-funded works; steel, cement, concrete, aggregates; strong auditability Name the publisher; the exact quarter (month); base date = 28 days before tender close (non-tendered, signature); Ci and C0 same source, same period, net of VAT (8.7.1) Wrong period, mixed publishers, tax mixing; large gaps to market inviting market-price claims
(3) Confirmed price A lawful Ci source; procedure per A.2.5 (pre-purchase submission; silence deems approval) Materials without published information; published prices plainly off market; provisionally priced, imported or custom materials Agree the procedure and reply period; submit quantity, price, brand and supplier quotes before purchase; form a price record; traceable to the period After-the-fact signing; substituting invoices - invoices prove cost only, never a basis without confirmation; A.2.2 allows provisional published-price posting on disputes

2. Defaults absent agreement

  • Base date: term 2.0.21 - tendered, 28 days before the tender deadline; non-tendered, 28 days before signature; the anchor of price and policy adjustments 'where the tender documents (enquiry documents) and the contract are silent'.
  • Source: A.2.1 lays the statement duty on the tenderer with no default clause; practice falls back on the base-date published information (most verifiable; A.2.4 completes the dual-information arithmetic) - a practical, not textual, default, best fixed in a supplement.
  • Missing period prices: A.2.2 - provisional use of the authority's period information, trued later to actual market prices.
  • Band: 8.7.2 - absent or unclear agreement, swings beyond 5% adjust.

3. Difference rate and risk-band deduction

Difference rate = (Ci - C0) / C0 x 100%. Variables (A.2.1): Ci - the period market price (confirmed price, current published information, or same-period trading-centre award price, representing the current level); C0 - the base price; Q - the adjustable factor quantity (per the contractual rule); r - the risk-band coefficient, positive when the difference is positive, negative when negative; dP - the adjustment cost of the period; dC - the factor difference; i - the purchase time. Test and deduction: |rate| <= r, no adjustment; |rate| > r, only the excess adjusts - rising, unit difference = Ci - C0 x (1 + r); falling, = C0 x (1 - r) - Ci; amount = unit difference x Q, carrying VAT only, never overheads or profit (3.3.5 item 4: 'the risks of overheads and profit sit in the bid as risk costs'). With both C0 and Ci from published information, A.2.4 sets the base three ways (against high-low arbitrage): (1) bid below base - rises tested on the base, falls on the bid, the excess on actuals; (2) bid above base - falls on the base, rises on the bid; (3) equal - both on the base. 8.7.1 compares the net-of-VAT labour, material and fuel information of the base date and the adjustment window before adjusting.

4. Locking: award discounts never cut C0

Three strands: (1) Table G.2.1-1 note 1 - the tenderer fills base price and band; discounts touch only the bid column; (2) A.2.1 - C0 represents the 28-day market level, regardless of later award discounts; (3) A.2.4 uses the bid only to set direction and base - never replacing C0. Discounts surface only inside A.2.4 (bids below the base test falls on the bid - adverse to the contractor). This is reasoned from the clauses, not stated; best written into the particular conditions.

5. Item-by-item locking

Table G.2.1-1 lists by number, name, specification, unit, base price and band; quantities per the contractual rule; A.2.1's Q is per factor. Different materials (even grades of one) lock their own base date, price and band - tested and computed item by item, then totalled; no composite or weighted average for the whole project. Table G.2.1-2 note 3 likewise fills the adjustment amount per item with a total.

Applicable boundaries

  • Only for contracts adjusting on price moves (labour, materials, fuel / power), the adjustable scope tabled per Appendix G.2 as a contract annex; outside scope, within band, or contractor-fault costs never adjust.
  • The price-information method uses Table G.2.1-1; the index method Table G.2.1-2 (Appendix A.1, C0 = base index) - this card's formulas do not carry over; contract terms prevail, this card giving statutory and practical defaults.
  • Elevating the bid or confirmed price to C0 needs express contract; absent terms, never take rates, purchase prices or invoices as C0.
  • The 'when used' and 'essentials' columns and the defaults of parts 2 and 4 are practice or reasoning, not text - fix them in supplements.

Further reading

GB/T 50500-2024 term 2.0.21; Appendix A.2.1 (formula, three sources, statement duty), A.2.2 (provisional posting), A.2.4 (bid-versus-base bases), A.1 with Table G.2.1-2 (index method), G.2.1 with Table G.2.1-1 (fillers and columns); clauses 8.7.1, 8.7.2, 3.3.5; companion cards on base-price fixing, excess computation and settlement price precedence.

Keywords