risk band (no-adjustment tolerance, e.g. ±5%)
- 01
Rules for handling contract price adjustment for cost fluctuation in final account review and construction cost expert assessment: routing by contract type, price-dating principles for delay periods, the exception for government-priced materials, and the eight categories of costs not adjusted for changes in costs listed in GB/T 50500-2024 clause 8.7.6
Final account review and expert assessment proceed on two levels. (i) Ro…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第3.3.6条、第8.7.2条、第8.7.3条、第8.7.6条GB/T 51262-2017 · Code for Construction Cost Appraisal 第5.6.2条T/ZBD 100.5-2023 · Work Guideline for Settlement Audit of Construction Works 第3.1.7条2026-10-29 - 02
Choosing among the three bases of material price adjustment (bid price / base-period published information / jointly confirmed price): statutory sources, defaults, difference-rate versus risk-band linkage and item-by-item locking (GB/T 50500-2024 term 2.0.21, Appendix A.2, G.2.1)
Per GB/T 50500-2024 Appendix A.2.1, the base price C0 is 'the market pri…
GB/T 50500-2024 术语第2.0.21条(合同基准日)GB/T 50500-2024 App. A.2.1(基准价三来源与价差公式)GB/T 50500-2024 App. A.2.2(暂按信息价计算后按实调整)2026-10-25 - 03
The step chain of adjusting on published price information: fix the adjustable list -> lock base price C0 -> take period prices Ci -> difference x adjustable quantity Q -> adjust the excess over the risk band -> book into progress and settlement, with fallbacks for missing periods and items and the Q test (GB/T 50500-2024 Appendix A.2; against superseded GB 50500-2013 Appendix A.2)
Six steps: (1) fix the adjustable material / labour list (2024: 3.3.5 it…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第 3.3.5 条、第 8.7.2 条、第 8.7.4 条、第 8.7.6 条、第 8.1.6 条、第 9.4.6 条GB/T 50500-2024 App. A.2.1~A.2.5(价格信息调差法)GB/T 50500-2024 App. G Table G.2.1-1、Table G.2.1-22026-10-25 - 04
Direction-specific base rules in the price adjustment method based on published price information when the contractor's tender price deviates from the base price (GB/T 50500-2024 Annex A.2.4, corresponding to Section 9.7 of the superseded GB 50500-2013): rises judge on the higher of the two prices, falls on the lower, a two-way disadvantage that blocks arbitrage, with the selection boundary against the Annex A.1 index method
Under GB/T 50500-2024 Annex A.2.4, the published-price-information adjus…
GB/T 50500-2024 建设工程工程量清单计价标准 App. A.2.4(价格信息调差法 报价偏离基准价的涨跌幅判定基数)GB/T 50500-2024 App. A.2.1(价差公式与基准价、计量周期价格、数量、风险幅度系数定义)GB/T 50500-2024 App. A.2.3(计量周期多个市场价格的取定方法)2026-10-25 - 05
The relationship between the risk allowance inside the all-in unit rate and contractual price adjustment for fluctuation: within the band the risk allowance absorbs the movement, beyond the band only the excess is adjusted, and the two are never counted twice
The risk allowance and contractual price adjustment are a two-stage allo…
GB 50500-2013 建设工程工程量清单计价规范 第2.0.8条(综合单价)、第2.0.9条(风险费用)、第3.4.3条、第5.2.2条、第6.2.2条、第9.8.1~9.8.3条、App. A.2.3、App. L.2/L.3GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.9条、第3.1.6条、第3.2.2条、第3.3.1条、第3.3.3条、第3.3.5条、第8.7.2条、第8.7.6条、App. A.1、App. A.2.4、App. G.22026-10-25 - 06
Rules for determining the material adjustment base price (C0): base date, one-of-three sources and the adjustment computation base (GB/T 50500-2024)
The base price C0 = the market price level 28 days before the bid closin…
GB/T 50500-2024 建设工程工程量清单计价标准 App. A.2.1GB/T 50500-2024 术语2.0.21GB/T 50500-2024 App. A.2.42026-09-25 - 07
Can published price information directly serve as the basis for material price adjustment: legality + three preconditions (listing / beyond band / tax) (GB/T 50500-2024)
Published price information (government guidance prices) is a price sour…
GB/T 50500-2024 建设工程工程量清单计价标准2026-09-25 - 08
Price adjustment (for fluctuation) calculation for ready-mixed (commercial) concrete: whole-factor adjustment per m³, adjustment to actual beyond the risk band, and tax treatment (GB/T 50500-2024 Appendix A.2 adjustment based on published price information)
Ready-mixed concrete is adjusted as one whole adjustable factor per m³ (…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works App. A.2(价格信息调差法)GB/T 50500-2024 第3.3.5条GB/T 50500-2024 第8.7.2条2026-09-25 - 09
Three-layer playbook for locking in the prices of bulk materials: contract-side price-adjustment mechanism + procurement-side price-locking methods + material-differentiated strategy (GB/T 50500-2024)
Locking the price of bulk materials = on the contract side, first fix th…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50358-2017 建设项目工程总承包管理规范DB37/T 5096-2017 建设工程项目管理咨询规范2026-09-25 - 10
Overview of material price adjustment in construction works: applicable conditions, base price (reference price for adjustment), risk band, and calculation methods (GB/T 50500-2024 Sections 3.3/8.7 and Appendices A, G)
Four indispensable elements of material price adjustment: ① adjustable s…
GB/T 50500-2024 建设工程工程量清单计价标准T/ZBD 100.5-2023 建设工程结算审核作业指引建设部令第107号 建筑工程施工发包与承包计价管理办法2026-09-25 - 11
Steel price adjustment calculation: price-information adjustment formula, per-specification per-period threshold checks with adjustment on actual basis, and tax treatment (GB/T 50500-2024 Appendix A.2)
Steel price adjustment uses the price-information adjustment method (GB/…
GB/T 50500-2024 App. A.2GB/T 50500-2024 第3.3.5条GB/T 50500-2024 第8.7.2条2026-09-25 - 12
Appendix A price adjustment (for fluctuation) methods for changes in costs, GB 50500-2013 vs GB/T 50500-2024: weighting coefficient basis and adjustment threshold differences
The two editions share the same formula skeleton in Appendix A (index-ba…
GB/T 50500-2024 建设工程工程量清单计价标准(App. A、第8.7节、App. G)GB 50500-2013 建设工程工程量清单计价规范(App. A、第9.8节)2026-09-25 - 13
Price-difference calculation method after material prices exceed the risk band (price-information adjustment method, GB/T 50500-2024 Appendix A.2)
The excess beyond the risk band is adjusted per actuals: when prices ris…
GB/T 50500-2024 建设工程工程量清单计价标准 App. A.2.1~A.2.5GB/T 50500-2024 第8.7.1~8.7.4条GB/T 50500-2024 第3.3.5条2026-09-25 - 14
Mechanism for material price changes under fixed unit-price contracts: unit price locked + quantities at actuals + beyond-band adjustment (GB/T 50500-2024)
Under unit-price contracts the all-in unit rate is fixed within the cont…
GB/T 50500-2024 建设工程工程量清单计价标准T/ZBD 100.5-2023 建设工程结算审核作业指引T/ZBD 100.4-2023 建设工程造价鉴定作业指引2026-09-25 - 15
Cement price adjustment calculation: determining the adjustment object by usage path (site-mixed / ready-mixed concrete / direct purchase) + price-information adjustment method formulas and caliber points (GB/T 50500-2024 Appendix A.2)
Cement adjustment first fixes the object by usage path: site-mixed concr…
GB/T 50500-2024 建设工程工程量清单计价标准 App. A.2.1~A.2.5GB/T 50500-2024 第3.3.5条GB/T 50500-2024 第8.7.1~8.7.6条2026-09-25 - 16
Selecting the contract pricing form when material prices fluctuate sharply: the hybrid mode of fixed unit rate + price adjustment clauses
With sharp fluctuations, neither a pure fixed price (quotes carry risk p…
建设部令第107号 建筑工程施工发包与承包计价管理办法 第十二条GB/T 50500-2024 建设工程工程量清单计价标准 第3.3.1/3.3.5/8.7.2~8.7.6条及App. A、App. GGB/T 50875-2013 工程造价术语标准 第3.3.6~3.3.8条2026-09-25 - 17
Order of applicable bases for material price adjustment: contract agreement prevails, pricing standard as fallback (GB/T 50500-2024 "agreement governs" and the 5% band rule)
Material price adjustment follows the contract agreement first (agreemen…
GB/T 50500-2024 建设工程工程量清单计价标准 第1.0.3、3.3.5、3.4.4、8.7.2条及App. A、App. G2026-09-25 - 18
Material price adjustment channels under fixed lump-sum contracts: no adjustment within the agreed risk band, adjustment beyond the risk band, mandatory adjustment for statutory causes
Under a fixed lump-sum contract, cost fluctuations within the agreed ris…
GB/T 50500-2024 第3.3.1~3.3.3、3.3.5、8.7.1~8.7.6条GB/T 50500-2024 App. A、App. G.2建设部令第107号 第12条2026-09-25