The step chain of adjusting on published price information: fix the adjustable list -> lock base price C0 -> take period prices Ci -> difference x adjustable quantity Q -> adjust the excess over the risk band -> book into progress and settlement, with fallbacks for missing periods and items and the Q test (GB/T 50500-2024 Appendix A.2; against superseded GB 50500-2013 Appendix A.2)
Six steps: (1) fix the adjustable material / labour list (2024: 3.3.5 item 2 + Appendix G Tables G.2.1-1/-2; 2013: 9.8.2 agreed scope, else over 5% adjusts the excess) -> (2) lock C0 = the market price 28 days before the tender deadline (non-tendered: signature), source, publisher and quarter (month) stated (A.2.1; 2013 A.2.3) -> (3) take Ci per measurement period; several prices within a period take the arithmetic mean, the quantity-weighted mean or the main-consumption-period price (A.2.1, A.2.3) -> (4) difference x Q (2024 A.2.1 formula; 2013 has only the 'excess on actuals' principle, no explicit formula) -> (5) adjust only beyond the agreed band r (rising Ci - C0(1+r), falling C0(1-r) - Ci; absent a band, over 5% - 8.7.2 / 2013 9.8.2) -> (6) book into cumulative progress and pay with progress and interim settlements (9.4.6, 8.1.6). Missing periods fall back in order: contract rule -> same-period alternative source -> in-period averaging -> provisional posting on current information with later truing (A.2.2) -> employer-recognised purchase price (A.2.5; 2013 A.2.3 item 4: 3 working days' silence deems approval; unreported self-purchase refused by the employer never adjusts) -> market enquiry by three parties; 'carry the last period forward' has no national-text basis outside the index method (2013 A.1.2). Q follows the contractual quantity rule; the default is the consumption of measured completed work - never signed list quantities or purchase / invoice totals; differences carry VAT only (3.3.5 item 4).
Applicable Codes
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第 3.3.5 条、第 8.7.2 条、第 8.7.4 条、第 8.7.6 条、第 8.1.6 条、第 9.4.6 条
- GB/T 50500-2024 App. A.2.1~A.2.5(价格信息调差法)
- GB/T 50500-2024 App. G Table G.2.1-1、Table G.2.1-2
- GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第 9.8.1 条、第 9.8.2 条、App. A.1.2、App. A.2.1~A.2.4(已废止,已被 GB/T 50500-2024 替代)
- DBJ41/T 208-2018 · Standard for Construction Project Supervision Work (Henan) 第 7.3.4 条
- T/ZBD 100.5-2023 · Work Guideline for Settlement Audit of Construction Works 第 3.1.7 条
- http://zjw.wuhai.gov.cn/zjj/879643/879725/879730/879750/2421354/index.html
- http://zjw.wuhai.gov.cn/zjj/879643/879725/879730/879750/2417599/index.html
- http://zjw.wuhai.gov.cn/zjj/879643/879725/879730/879750/2441133/index.html
Positioning
The complete step chain of published-information adjustment from price-taking to booking, clause by clause, with the two frequent sticking points - fallbacks for missing periods or items, and whether Q runs on list or measured quantities. Current text: GB/T 50500-2024 Appendix A.2, against superseded GB 50500-2013 Appendix A.2.
Core conclusions
1. Editions first
GB 50500-2013 is superseded; new contracts run 2024, 2013 serving legacy comparison only. Structural gap: 2013 Appendix A.2 states principles and 'excess on actuals' without an explicit formula; dP = sum(dC x Q) enters with 2024 A.2.1 - under 2013 the formula is a common algorithm, not a clause.
2. The six-step chain
| Step | 2013 (superseded) | 2024 (current) |
|---|---|---|
| (1) adjustable list | 9.8.2: agreed scope; absent, over 5% adjusts the excess | 3.3.5 item 2 + Appendix G: Tables G.2.1-1 (information method) / G.2.1-2 (index method) as contract annexes; tenderer fills name, specification, unit, base price, band; bidder the price |
| (2) lock C0 | A.2.3: the 'base unit price' of Table-21 | A.2.1: the market price 28 days before the tender deadline (non-tendered: signature), from ceiling prices, the authority's quarterly (monthly) information, or same-period like-work award prices; tender documents state source, publisher, quarter (month) |
| (3) take Ci | A.2.1: labour and plant per authority indices / shift rates; material prices and quantities confirmed by the employer | A.2.1: confirmed period price, authority information or award prices; A.2.3: in-period plurality -> arithmetic mean, quantity-weighted mean or main-consumption-period price, method and priority agreed |
| (4) dC x Q | A.2.3: three bands by bid versus base, 'excess on actuals' | A.2.4 three bands + A.2.1 formula dP = sum(dC x Q) |
| (5) band split | A.2.3 three bands; 9.8.2 5% fallback | 8.7.2: absent or unclear band, beyond 5% adjusts; within band, no adjustment |
| (6) booking | 9.8 adjustment paid with progress | 9.4.6: confirmed adjustments enter cumulative progress; 8.1.6: paid with progress and interim settlements |
3. Hard constraints per step
- C0 is the locked base-date price (28 days before tender close / signature), never 'the earliest price'; tender documents state source, publisher, period; objections before tendering.
- Ci runs per measurement period, never once at completion; in-period plurality needs an agreed method.
- Direction: rising dC = Ci - C0 x (1 + r); falling dC = C0 x (1 - r) - Ci; A.2.1 defines r signed by dC.
- Only the excess adjusts; within band the contractor carries it in the bid.
- Tax: differences 'carry VAT, never overheads or profit' (3.3.5 item 4).
- Never-adjust list (8.7.6): consumables; small tools; preliminaries; plant other than the fuel / power of 8.7.1~8.7.4; materials outside agreed items save 8.7.3 swings; moves beyond agreed scope or band; overheads and profit; contractor-cause costs.
4. Fallbacks for missing periods / items (in order)
| # | Fallback | Basis |
|---|---|---|
| 1 | contract rule (may itself say 'last period') | 3.3.5 item 1 |
| 2 | same-period alternative sources (award prices, confirmed prices) | A.2.1's three Ci options |
| 3 | in-period averaging (arithmetic / weighted / main-consumption) | A.2.3 |
| 4 | provisional posting, later truing | A.2.2 |
| 5 | employer-recognised purchase price (with forfeiture) | A.2.5; 2013 A.2.3 item 4: 3 working days' silence deems approval; unreported self-purchase the employer refuses never adjusts |
| 6 | market survey, three-party agreement | DBJ41/T 208-2018 clause 7.3.4; T/ZBD 100.5-2023 clause 3.1.7 |
Key judgement: 'carry the last period forward' has no national text - only the index method (2013 A.1.2) says so expressly; contracts may agree it, else it fails at settlement.
5. The quantity Q
- Contract first: A.2.1 - 'quantities per the contractual calculation rule'; Table G.2.1-1 note 2 the same.
- Default: the material consumption of measured completed work (completed measured quantity x list / quota consumption), tied to chapter 7 measurement.
- Two nevers: signed list quantities (unbuilt work carries no difference); purchase / invoice totals (wastage, stock and cross-project use inflate the base).
- 2013 rests quantities on procedure: employer review of unit prices and quantities (A.2.1) and pre-purchase reporting with the 3-day forfeiture (A.2.3 item 4).
6. Inside versus outside the band
| Case | Treatment | Basis |
|---|---|---|
| within agreed r | no adjustment, contractor risk in the bid | 8.7.2(2); 9.8.2 |
| beyond r | only the excess: +-[Ci - C0 x (1 +- r)] x Q | A.2.1 / A.2.4; A.2.3 |
| no agreed band | beyond 5% adjusts | 8.7.2; 9.8.2 |
| bid < base | rises test on base, falls on bid | A.2.4-1; A.2.3-1 |
| bid > base | falls on base, rises on bid | A.2.4-2 |
| bid = base | both on base | A.2.4-3 |
| delay (2024) | employer cause: later-work prices at the higher of plan and actual; contractor cause: the lower; neither: per 8.7.2 save agreement | 8.7.4 |
| plant shift rates | 2013: per the authority's scope; 2024: only fuel / power adjusts (8.7.6-4) | 2013 A.2.4; 3.3.5-3 |
Applicable boundaries
- Only contract-listed adjustable factors (Appendix G tables) - everything in 8.7.6 never adjusts.
- Lump-sum contracts: generally no price-move adjustment absent agreement; claims handle hardship (T/ZBD 100.5-2023 clause 3.1.7). This chain serves unit-rate contracts.
- Adjustment differs from estimate-stage differences and provisional-price replacement - separate bases, never mixed.
- Published information is regional guidance - take the project's location and period; no cross-region borrowing.
- 2013 serves legacy contracts only.
Further reading
GB/T 50500-2024 clauses 3.3.5, 8.7.2, 8.7.4, 8.7.6, 8.1.6, 9.4.6; Appendix A.2.1~A.2.5; Appendix G Tables G.2.1-1/-2; GB 50500-2013 clauses 9.8.1-9.8.2, Appendix A.1.2 and A.2.1~A.2.4 (superseded); DBJ41/T 208-2018 clause 7.3.4; T/ZBD 100.5-2023 clause 3.1.7; provincial information pages (e.g. Wuhai housing bureau columns) for current release bases.