Building a material published-price-information vs actual purchase-price comparison table: four-segment table structure, deviation analysis, and the four-party certification and sign-off process

The comparison table = base segment (name/specification precise to the grade, unit, work location and period) + price segment (published price information stating the issuing agency, period, and tax-inclusive/delivered basis; purchase price on the same basis, side by side) + analysis segment (deviation rate = (purchase price − published price information)/published price information × 100%, each deviation explained and checked against the contract risk band) + signature segment (applicant/supervision/employer signatures and seals). Based on the GB/T 51095-2015 Appendix E.0.4 enquiry (price verification) form, extended with "published price information (agency + period)" and "deviation rate" columns; process: ≥ 3 enquiries → comparison → supervision price verification → employer confirmation before purchase (failure to reply within the time limit deemed acceptance) → contract at the approved price → archive into the price library. The signed and sealed comparison table is the certified record of agreed material prices — a basis for preparing the settlement.

Applicable Codes

  • GB/T 51095-2015 建设工程造价咨询规范
  • GB/T 50500-2024 建设工程工程量清单计价标准
  • GB/T 51262-2017 建设工程造价鉴定规范
  • T/ZBD 100.1-2022 建设工程造价数据建设通用标准

Topic Positioning

A general method for building a "material published price information vs actual purchase price comparison table": table structure design, deviation analysis, and the price certification and sign-off process — for the employer's approval of material prices, price adjustment (for fluctuation) pricing, and settlement records.

Core Conclusions

The table is organized in four segments, one row per material: ① base segment — name consistent with the BOQ features, specification precise to the grade, marked with the work location and usage period; ② price segment — published price information stating the issuing agency + period + tax-inclusive/tax-exclusive + delivered/ex-factory basis, purchase price stating its composition (ex-factory price + freight and handling charges), ≥ 3 enquiries, the two columns comparable only on the same basis; ③ analysis segment — deviation rate = (purchase price − published price information)/published price information × 100%, every deviation must be explainable (volume/payment terms/haul distance/brand/period lag), and checked against the contract-agreed risk band (no-adjustment tolerance) to judge whether the band is exceeded; ④ signature segment — applicant, supervision, and employer signatures and seals. Official form as the base: GB/T 51095-2015 Appendix E.0.4 "Material (equipment) enquiry (price verification) form" (supply mode and unit price, what the unit price includes, three-level sign-off columns), recommended to be extended with the "published price information (agency + period)" and "deviation rate" columns. Process: ≥ 3 enquiries → comparison with the current published price information → supervision price verification → employer confirmation before purchase (failure to reply within the time limit deemed acceptance, Appendix A.2.5) → contract at the approved price → voucher archiving. The sealed comparison table is the certified record of agreed material prices; settlement priority: contract agreement > mutual price confirmation > published price information > market price enquiry.

Applicable Boundaries

Applies to the employer's approval of material (equipment) prices, price adjustment, and settlement pricing records; where the published price information lacks an item, fill by "contract agreement → substitute channel → market price enquiry → employer's approval of material prices"; this table governs only price comparison and price approval — adjustment amounts are computed separately by the adjustment based on published price information; price data must be classified into the market-price/published-price-information/vendor-quote channels and never mixed (T/ZBD 100.1-2022).

Further Reading

GB/T 51095-2015 Appendix E.0.4; GB/T 50500-2024 Appendix A.2 adjustment based on published price information, A.2.5 purchase-price approval, 8.7.2 5% fallback absent agreement, Appendix G schedule of price-adjustable key materials; GB/T 51262-2017 Clause 5.6.4 material price dispute appraisal; T/ZBD 100.1-2022 Clause 7.2.3 three-channel classification of price data.