Composition of multi-month construction material published price information (government guidance prices): three methods for determining multiple market prices within a measurement period (GB/T 50500-2024 Appendix A.2.3 — arithmetic mean / quantity-weighted / price for the main consumption period)
Multi-month construction does not automatically mean weighting: when measuring monthly (or per agreed measurement period), each period takes its own market price Ci, differences computed and accumulated period by period — no prior weighting needed; only when one measurement period spans multiple price issues (e.g., quarterly measurement, monthly published price information (government guidance prices)) is Ci composed per A.2.3's three methods: (1) arithmetic mean, (2) weighted average with completed quantities, (3) price during the main-consumption construction period — method and priority order must be contractually agreed. Method choice directly flips threshold triggering — the same data can show +8.75% (arithmetic, exceeds the 5% risk band, adjustable) vs +4.13% (weighted, within the risk band, no adjustment); the composed Ci enters dP = sum[(Ci - C0(1 +/- r)) x Q] x (1 + VAT rate), with price differences subject to value added tax (VAT) only, not management fee or profit (3.3.5).
Applicable Codes
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works App. A.2.1、A.2.3、A.2.5、A.1.5
- GB/T 50500-2024 第3.3.5条、8.7.1~8.7.6条
- GB/T 50500-2024 App. GTable G.2.1-1
Topic Positioning
Answering “how to weight/compose material published price information (government guidance prices) when construction spans multiple months”: per GB/T 50500-2024 Appendix A.2.3, first distinguish “per-period adjustment” from “within-period composition”, then, when composition is genuinely needed, choose among three methods to set the measurement period’s market price Ci.
Core Conclusions
- Determine the scenario first — do not start with weighting: when measuring per the contractual adjustment period (e.g., monthly), each measurement period takes its own Ci, differences computed and accumulated — no prior weighting; the base price C0 stays locked throughout (market price 28 days before the tender deadline [= FIDIC Base Date]; 28 days before contract signing for non-tendered works). Only when one measurement period contains multiple price issues (e.g., quarterly measurement with monthly published price information (government guidance prices)) must the months be composed into one Ci.
- A.2.3 original: “Where multiple market prices form within a measurement period due to cost fluctuation, the arithmetic mean of the period’s market prices, the weighted average of market prices and corresponding completed quantities, or the market price during the main-consumption construction period may be used as the current price in the adjustment formula. The parties shall agree on the method or the priority order of methods in different situations.”
- Three composition methods: (1) arithmetic mean Ci = (P1 + P2 + P3)/3 — when period consumptions differ little; (2) quantity-weighted Ci = sum(PiQi)/sum(Qi) — when consumptions differ markedly, closest to actual purchasing structure; (3) main-consumption-period price — when most quantity concentrates in one period.
- The composed Ci enters the formula (A.2.1 adjustment based on published price information): dP = sum[(Ci - C0 x (1 +/- r)) x Q] x (1 + VAT rate), adjusting at actual values only the portion beyond the risk band r (no-adjustment tolerance, e.g. ±5%); price differences are subject to value added tax (VAT) only, not management fee or profit (3.3.5). Ci must share the same basis as the base price: mutually confirmed market prices, the cost management authority’s current published price information (government guidance prices), or contemporaneous winning prices at trading centers — all representing the measurement period’s current price level.
- Method choice flips threshold outcomes: example (a quarter of 3 months, high-price month with tiny quantity, main month near base price, risk band 5%): arithmetic mean Ci = +8.75% > 5% -> adjustable; quantity-weighted Ci = +4.13% < 5% -> not adjustable — opposite conclusions from the same data. This is why A.2.3 requires agreeing the method or priority order; unclear agreement is itself a settlement dispute point.
- Under per-period adjustment, each period independently tests the threshold (|Ci - C0|/C0 > r); periods within the risk band get no adjustment — no “smoothing” with an annual average.
Applicable Boundaries
Applies to composing multiple prices within a measurement period under the adjustment based on published price information (Appendix A.2, adjustable main materials listed per Appendix G Table G.2.1-1 as contract annex). Premises: the contract specifies adjustable scope, base price source, and risk band (fallback: >5% triggers when unspecified or unclear, 8.7.2); composition method, priority, and alternative quantity rules for Q must be detailed in tender documents and special clauses; objecting contractors must seek clarification before bidding. Not applicable to: monthly per-period adjustment (no composition), index method (A.1.5 has its own rules), construction consumables/small tools/preliminaries/management fee and profit (8.7.6).
Further Reading
GB/T 50500-2024 (China national pricing standard for BOQ) Appendix A.2.1 (formula, base price and Ci sources, risk band confirmation), A.2.3 (multi-price composition — this card’s subject), A.2.5 (purchase-price method), A.1.5 (index-method counterpart); 3.3.5 (VAT on price differences), 8.7.1-8.7.6 (risk band, delay pricing, non-adjustable scope); Appendix G Table G.2.1-1 (schedule of price-adjustable key materials provided by the contractor). Related: rules for determining construction-period prices, steel price adjustment formulas, four elements of material price adjustment.