price adjustment (for fluctuation)
- 01
Composition of multi-month construction material published price information (government guidance prices): three methods for determining multiple market prices within a measurement period (GB/T 50500-2024 Appendix A.2.3 — arithmetic mean / quantity-weighted / price for the main consumption period)
Multi-month construction does not automatically mean weighting: when mea…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works App. A.2.1、A.2.3、A.2.5、A.1.5GB/T 50500-2024 第3.3.5条、8.7.1~8.7.6条GB/T 50500-2024 App. GTable G.2.1-12026-09-25 - 02
Price adjustment (for fluctuation) calculation for ready-mixed (commercial) concrete: whole-factor adjustment per m³, adjustment to actual beyond the risk band, and tax treatment (GB/T 50500-2024 Appendix A.2 adjustment based on published price information)
Ready-mixed concrete is adjusted as one whole adjustable factor per m³ (…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works App. A.2(价格信息调差法)GB/T 50500-2024 第3.3.5条GB/T 50500-2024 第8.7.2条2026-09-25 - 03
Matching material specifications in price information with actual materials: four-element matching, grade/unit conversion, and adjustment-specification locking
Price-taking from price information matches precisely by the four elemen…
GB/T 50500-2024GB/T 50875-2013T/ZBD 100.1-20222026-09-25 - 04
Adjustment of the contract price (GB/T 50500-2024 Chapter 8): eleven triggering events, mechanism by section, and FIDIC mapping
Adjustment of the contract price is the mechanism for changing the contr…
GB/T 50500-2024 建设工程工程量清单计价标准(第8.1.1/8.1.2条、第8.2~8.11节、第7.5节、App. A、App. G)FIDIC Red/Yellow Book 2017(第13.3、13.4、13.6、13.7、20.2.1 条〔对照〕)GB/T 50875-2013 工程造价术语标准2026-09-25 - 05
Handling rules when the price-information issue and the construction month are misaligned (GB/T 50500-2024 Appendix A adjustment)
Price-information adjustment takes the issue corresponding to the measur…
GB/T 50500-2024 App. A.2.1~A.2.5GB/T 50875-2013 第2.1.16条T/ZBD 100.1-2022 第7.2.3条2026-09-25 - 06
Priority of price bases for construction payment settlement: contract agreement > price confirmed by both parties > published price information > market price enquiry (purchase contract / invoice prices require the employer's approval of material prices)
Bases for settlement by priority: ① contract-agreed price (fundamental b…
GB/T 50500-2024 建设工程工程量清单计价标准T/ZBD 100.5-2023 建设工程结算审核作业指引DB42/T 823-20212026-09-25 - 07
Price-taking rules when one material has multiple published prices / original prices: weighted average by supply quantity at compilation, three agreed methods at adjustment, unified caliber
When one material has multiple prices, take prices by scenario: at compi…
TB 10811-2024 铁路基本建设工程设计概(预)算费用定额GB/T 50500-2024 建设工程工程量清单计价标准T/ZBD 100.1-2022 建设工程造价数据建设通用标准2026-09-25 - 08
Determining the pricing risk scope within the all-in unit rate: contract agreement first + statutory fallback of GB/T 50500-2024 Sections 3.3/8.7
Risk-scope determination follows 'contract agreement first, statutory fa…
GB/T 50500-2024 建设工程工程量清单计价标准 第3.3.1~3.3.6条GB/T 50500-2024 第8.7节GB/T 50500-2024 App. A2026-09-25 - 09
Rules for determining the construction-period price (measurement-period market price Ci) in material adjustment (GB/T 50500-2024 appendix A.2)
The construction-period price is the measurement-period market price Ci…
GB/T 50500-2024 App. A.2.1~A.2.5GB/T 50500-2024 第8.7.2/8.7.4条GB/T 50500-2024 App. A.1.52026-09-25 - 10
Handling paths when published price information clearly deviates from actual market prices: unify the bases of comparison first to exclude illusions, then correct by scenario (temporary adjustment with later true-up / price certification / expert assessment as fallback)
Published price information is only a reference guide price issued by th…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 51262-2017 建设工程造价鉴定规范GB/T 50875-2013 工程造价术语标准2026-09-25 - 11
Overview of the full-chain use rules for construction cost published price information: nature, price calibers, stage-by-stage pricing, and frequent misconceptions
Published price information means reference guide prices issued by cost…
GB/T 50875-2013 工程造价术语标准GB/T 50500-2024 建设工程工程量清单计价标准TB 10801-2024 铁路基本建设工程设计概(预)算编制办法2026-09-25