Taking and weighting published price information for materials across multiple months: default per-period adjustment; weight only when one measurement period spans price issues (GB/T 50500-2024 Appendix A.2)
Per GB/T 50500-2024: for construction spanning measurement periods (e.g., monthly), measure in segments per the agreed adjustment cycle, take each period's market price Ci separately, compute differences and sum — no prior weighting needed, with the base price C0 locked throughout; only when one measurement period spans multiple price issues (e.g., quarterly measurement with monthly published price information) does Appendix A.2.3 weighting apply — one of three options (arithmetic mean / quantity-weighted mean / main-consumption construction-period price), the method and priority to be agreed in the contract. Weighting is merely the means to determine Ci; the choice of method can flip the conclusion from "adjustable" to "not adjustable".
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准(第7.1.3条、App. A.2.1~A.2.5、App. GTable G.2.1-1、第8.7.2条、第3.3.5条)
Topic Positioning
How to take and weight published price information for materials when construction spans several months: distinguish "spanning measurement periods -> adjust per period" from "spanning price issues within one period -> only then weight", and the impact of the weighting method on the adjustment conclusion (GB/T 50500-2024 Appendix A.2).
Core Conclusions
- Main path: measure in segments per the agreed adjustment cycle, take each period's market price Ci, compute differences separately and sum (Clause 7.1.3 + Appendix A.2.1) — no prior weighting; the base price C0 is the price 28 days before the bid deadline, locked throughout.
- Weighting applies only when one measurement period spans multiple price issues (e.g., quarterly measurement with monthly published price information): Appendix A.2.3 offers three options — arithmetic mean, weighted mean by completed quantities, or the main-consumption construction-period price; the method and its priority must be agreed in the contract.
- Weighting is only a means to determine Ci: the beyond-band judgment compares the weighted composite price with the base price. With the same base price and band, an arithmetic mean may exceed the band (adjustable) while a quantity-weighted mean may not (not adjustable) — the method decides "adjust or not".
Applicable Boundaries
Applies to the method of adjustment based on published price information (Appendix A.2); the price-index method (A.1) is analogous but differs in formula; where the contract has agreed a weighting method, it prevails. Does not expand on purchase-price confirmation (A.2.5) or temporary adjustment with later truing (A.2.2). Before weighting, unify tax-inclusive/exclusive, specification grade, and delivered/ex-factory calibers.
Further Reading
See GB/T 50500-2024 Clause 7.1.3, Appendices A.2.1-A.2.5, Appendix G Table G.2.1-1; the risk-band fallback is Clause 8.7.2 (beyond 5% when not agreed or unclear); the difference carries VAT only, no management fee or profit, per Clause 3.3.5.
Keywords
- 信息价加权
- material price adjustment
- measurement period
- 算术平均
- 量加权平均
- 主要用量施工期价
- adjustment based on published price information
- 逐期调差