Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Taking and weighting published price information for materials across multiple months: default per-period adjustment; weight only when one measurement period spans price issues (GB/T 50500-2024 Appendix A.2)

Per GB/T 50500-2024: for construction spanning measurement periods (e.g., monthly), measure in segments per the agreed adjustment cycle, take each period's market price Ci separately, compute differences and sum — no prior weighting needed, with the base price C0 locked throughout; only when one measurement period spans multiple price issues (e.g., quarterly measurement with monthly published price information) does Appendix A.2.3 weighting apply — one of three options (arithmetic mean / quantity-weighted mean / main-consumption construction-period price), the method and priority to be agreed in the contract. Weighting is merely the means to determine Ci; the choice of method can flip the conclusion from "adjustable" to "not adjustable".

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准(第7.1.3条、App. A.2.1~A.2.5、App. GTable G.2.1-1、第8.7.2条、第3.3.5条)

Topic Positioning

How to take and weight published price information for materials when construction spans several months: distinguish "spanning measurement periods -> adjust per period" from "spanning price issues within one period -> only then weight", and the impact of the weighting method on the adjustment conclusion (GB/T 50500-2024 Appendix A.2).

Core Conclusions

  1. Main path: measure in segments per the agreed adjustment cycle, take each period's market price Ci, compute differences separately and sum (Clause 7.1.3 + Appendix A.2.1) — no prior weighting; the base price C0 is the price 28 days before the bid deadline, locked throughout.
  2. Weighting applies only when one measurement period spans multiple price issues (e.g., quarterly measurement with monthly published price information): Appendix A.2.3 offers three options — arithmetic mean, weighted mean by completed quantities, or the main-consumption construction-period price; the method and its priority must be agreed in the contract.
  3. Weighting is only a means to determine Ci: the beyond-band judgment compares the weighted composite price with the base price. With the same base price and band, an arithmetic mean may exceed the band (adjustable) while a quantity-weighted mean may not (not adjustable) — the method decides "adjust or not".

Applicable Boundaries

Applies to the method of adjustment based on published price information (Appendix A.2); the price-index method (A.1) is analogous but differs in formula; where the contract has agreed a weighting method, it prevails. Does not expand on purchase-price confirmation (A.2.5) or temporary adjustment with later truing (A.2.2). Before weighting, unify tax-inclusive/exclusive, specification grade, and delivered/ex-factory calibers.

Further Reading

See GB/T 50500-2024 Clause 7.1.3, Appendices A.2.1-A.2.5, Appendix G Table G.2.1-1; the risk-band fallback is Clause 8.7.2 (beyond 5% when not agreed or unclear); the difference carries VAT only, no management fee or profit, per Clause 3.3.5.