Defining the scope of adjustable (price-adjustable) materials: locked by contract annex tables, not share thresholds; auxiliary and low-value materials outside adjustment (neither coefficient-merged nor overheads-lumped); the negotiation channel for unlisted materials' abnormal swings (GB/T 50500-2024 clauses 3.3.1, 3.3.5, 8.7.3, 8.7.5, 8.7.6; Appendix G.2, A.2.1)

GB/T 50500-2024 sets no material-cost share threshold: the adjustable scope locks item by item in annex Tables G.2.1-1 / G.2.1-2 (Appendix G.2) - tenderer filling name, specification, unit, base price and risk band, bidder the price, quantities per the contractual rule (3.3.5, G.2.1). Auxiliary and low-value materials (consumables, small tools, preliminaries, non-agreed materials) plus overheads and profit never adjust for price moves (8.7.6) - there is no national channel 'merging auxiliaries by coefficient', nor are they an overheads lump: their price risk sits inside the material cost of the all-in rate. Unlisted materials adjust in principle never; only on abnormal, unforeseeable-at-contracting moves making performance plainly inequitable may the parties negotiate band or sharing per equitable allocation (8.7.3). Free-issue and provisionally priced items sit outside 8.7.2~8.7.4 (8.7.5). Local share-threshold practices are local documents - verify current numbers.

Applicable Codes

  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第 3.3.1 条
  • GB/T 50500-2024 第 3.3.5 条
  • GB/T 50500-2024 第 8.7.2 条
  • GB/T 50500-2024 第 8.7.3 条
  • GB/T 50500-2024 第 8.7.5 条
  • GB/T 50500-2024 第 8.7.6 条
  • GB/T 50500-2024 App. A.2.1
  • GB/T 50500-2024 App. G.2 Table G.2.1-1/Table G.2.1-2
  • TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第 4.1.2 条
  • http://zjt.hubei.gov.cn/zfxxgk/fdzdgknr/qtzdgknr/hygq/202008/t20200805_2738953.shtml
  • https://hunan.gov.cn/hnszf/xxgk/wjk/szbm/szfzcbm_19689/szfcxjst/gfxwj_19835/202005/t20200526_12171677.html
  • https://zjj.zhuhai.gov.cn/zjj/hygl/ywgsgg/jgzz/content/post_3863584.html

Positioning

Three practical questions of boundary: who defines the adjustable (key) materials, where and on what basis; whether auxiliary and low-value materials join price adjustment (and whether they are 'an overheads lump'); and whether unlisted materials swinging wildly still have a channel. Basis: GB/T 50500-2024 clause sets 3.3 and 8.7 with Appendices A and G, plus a railway parallel.

Core conclusions

1. No national share threshold; scope locks in annex tables. 3.3.5 item 2: 'the parties shall fix the scope of adjustable key materials and complete Appendix G.2 Tables G.2.1-1 or G.2.1-2 as contract annexes.' Table essentials (G.2.1 notes): G.2.1-1 (information method) - tenderer fills number, name, specification, unit, base price, risk band; bidder the price; 'quantities per the contractual calculation rule'; G.2.1-2 (index method) - tenderer fills name / specification and base index, labour included where indexed. So adjustable scope = the annex table's items - no national rule makes materials adjustable above any cost share. Item 1 requires fixing weights or amounts, bands, and index / information derivation rules.

2. Auxiliaries and low-value materials never adjust - neither coefficient-merged nor overheads-lumped. 8.7.6: save as agreed, never adjusting - (1) consumables; (2) small tools; (3) preliminaries; (4) plant save the fuel / power of 8.7.1~8.7.4; (5) non-agreed materials save 8.7.3 swings; (6) moves beyond agreed scope and band or within the 8.7.2 band; (7) overheads and profit; (8) contractor-cause costs. So auxiliaries price into the rates' material cost with the contractor carrying the risk; there is no 'coefficient merger' channel, and no text lumps them into overheads - overheads and profit are a separate never-adjust class (item 7). 3.3.5 item 4: differences 'carry VAT, never overheads or profit; the risks of overheads and profit sit in the bid'.

3. Unlisted materials: no adjustment in principle; the 8.7.3 negotiation is the exception. 8.7.3: 'where market prices of materials outside the agreed adjustable classes move abnormally - a major change unforeseeable at contracting making continued performance plainly inequitable - the parties may negotiate the band or sharing ratio per equitable allocation, bearing the relevant plus-or-minus difference or adjusting on actuals.' Three requisites (abnormal move; unforeseeable major change; plain inequity); the outcome is negotiation / actuals, never automatic full adjustment. The 5% fallback of 8.7.2 serves 'agreed factors, missing band' only - it never pulls unlisted materials in.

4. Two classes expressly excluded. 8.7.5: 'the material adjustments of 8.7.2~8.7.4 are not suited to employer-supplied and provisionally priced items. Employer-supplied items may adjust on the employer's actual changes but not enter the contract total; provisionally priced items follow 8.4.'

5. Essentials for particular conditions (one missing invites disputes). Lock simultaneously: (1) names, specifications, units and linked items; (2) base price C0 with source, publisher and quarter (month) - the market level 28 days before the tender deadline (non-tendered: signature) from ceiling prices, published information or award prices (A.2.1); (3) band r; (4) the quantity rule for Q; (5) price sources and adjustment windows; (6) treatment beyond scope and band. 3.3.1 draws the line: 'risk content and scope shall be stated in tender documents and contracts; uncapped risk, all risk or similar wording is forbidden.'

6. Local share thresholds. Some provincial offices once divided key from non-key materials by cost share with banded risk treatments - valid only within their territory, local guidance; never read back as national rules; cite current numbers only.

7. Railway parallel: positive listing. TB 10801-2024 clause 4.1.2: labour difference = quota labour consumption x (compilation-period rate - base-period rate); material difference = consumption x (compilation price - base price), adjustable materials limited to those listed (water, power; cement, timber, steel, pipes, bricks, tiles, sand, stone, lime, geosynthetics, rails, turnouts, sleepers, fastenings, bearings, tunnel waterproof sheet, explosives, catenary and power wire, optical cable, fuels); plant difference = shifts x (period rate - base rate). Unlisted materials never enter. Contract-annex locking and quota listing are two mechanisms - never interchanged.

Applicable boundaries

  • For BOQ projects under GB/T 50500-2024 (recommended; contract prevails, the standard as fallback); not for estimate-stage sectoral differences (see railway 4.1.2).
  • Adjustable factors: labour, key materials (equipment per contract), fuel / power only; preliminaries, consumables, small tools, other plant, overheads and profit never adjust.
  • 8.7.3 is after-the-fact relief, never a design device; the claimant proves abnormality and unforeseeability.
  • Free-issue and provisional-price items sit outside 8.7.2~8.7.4 (employer's actual changes outside the total; 8.4 rules).
  • No specific lists, thresholds or amounts here; local thresholds from current originals.

Further reading

GB/T 50500-2024 clauses 3.3.1, 3.3.5, 8.7.1, 8.7.2, 8.7.3, 8.7.5, 8.7.6, clause set 8.4; Appendix G.2 tables and notes; A.2.1 (definitions), A.2.4; TB 10801-2024 clause 4.1.2; provincial guidance channels (Hubei, Hunan, Zhuhai pages - verify current numbers).

Keywords

  • 可调差材料范围
  • 可调价主要材料
  • 主要材料界定
  • 辅助材料调差
  • 施工耗材费用不调
  • 未列入调差清单
  • 附录G.2可调价主要材料表
  • equitable risk allocation