The index-based adjustment method (GB/T 50500-2024 Appendix A.1): the adjustment formula, fixing the fixed weight A and variable weights Bi, and the sources and timing of price indices (factors)

The index method computes dP = P0 x [A + sum Bi x (Fti/F0i) - 1]: P0 the net-of-VAT contract price of the measurement period; A the fixed weight and Bi the weights of adjustable factors on the net-of-VAT contract price, with A + sum Bi = 1; weights and base indices are ranged by the employer and fixed in the tenderer's price-index and weight schedule of the tender-letter appendix, absent which the tender price ceiling's weights may be used (A.1.4); base indices at the contract base date (28 days before the tender deadline for tendered works), current indices per period, the previous period's usable provisionally (A.1.2/A.1.5/A.1.6); the index source is contractual (2024 no longer mandates authority indices first); adjustments carry VAT only, never overheads or profit.

Applicable Codes

  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works App. A.1.1~A.1.6
  • GB/T 50500-2024 第3.3.5条
  • GB/T 50500-2024 第8.7.1~8.7.6条
  • GB/T 50500-2024 App. G Table G.2.1-1、Table G.2.1-2
  • GB 50500-2013 App. A.1.1(已废止,仅作版本对照)

Positioning

The complete fixing rules of GB/T 50500-2024 Appendix A.1, index-based adjustment: the formula, who fixes the fixed weight A and variable weights Bi and how, the timing and sources of base / current indices (the "factors"), and the fallbacks for missing agreement or changed circumstances.

Core conclusions

1. The formula (A.1.1)

Where labour, material or plant prices fluctuate, per the employer's Appendix G Table G.2.1-2 (adjustable key materials) and the data agreed in the tenderer's index-and-weight schedule:

dP = P0 x [A + B1 x (Ft1/F01) + B2 x (Ft2/F02) + ... + Bn x (Ftn/F0n) - 1]

  • dP - the price difference to adjust;
  • P0 - the agreed net-of-VAT contract price payable for the period, excluding price adjustments, retention held or paid, advance payments made or recovered, and variations already priced at current rates - but including BOQ errors and variations priced at award rates;
  • A - the fixed weight (the non-adjusted share);
  • B1...Bn - the variable weights of the adjustable factors on the net-of-VAT contract price;
  • Ft1...Ftn - current price indices;
  • F01...F0n - base price indices at the contract base date; where the contract allows a fluctuation band, the base indices incorporate that band factor.

A + sum Bi = 1 at contract level - the fixed plus variable shares make the whole.

2. Weights: scope and fixing

  1. Adjustable factors: labour, key materials and the fuel/power within plant costs only; per clauses 3.3.5 items 1/3 and 8.7.6 - consumables, small tools, preliminaries, other plant, non-agreed materials, overheads and profit, and contractor-cause costs never adjust.
  2. Bi base: the factor's net-of-VAT amount / net-of-VAT contract price (not the VAT-inclusive bid total); A = 1 - sum Bi.
  3. Who fixes, where: the employer ranges the factors, weights and base indices from the works' conditions; the tenderer agrees them in the tender-letter appendix; objections are raised to the employer before tendering (A.1.1 closing).
  4. Fallback: variable weights not agreed - use the tender price ceiling's corresponding weights (A.1.4).
  5. Variations distorting weights: adjust by negotiation (A.1.3).
  6. Carrier: Appendix G Table G.2.1-2, a contract annex; "name, specification" and "base index" by the tenderer-inviter; labour adjusted by index likewise entered in "name" (3.3.5 item 2, Appendix G).
  7. No empirical values for A / Bi are given - "15% / 20% fixed share" is trade habit, not the standard; the lawful sources are this contract's build-up plus the appendix schedule, or the ceiling's weights.

3. Indices: sources and values

  1. Source by contract: A.1.1 closing - "the index source or determination method is agreed in the contract"; 3.3.5 item 1 likewise. The 2024 edition drops the 2013 rule that authority indices come first (GB 50500-2013 A.1.1, now superseded); in practice contracts still mostly adopt the provincial / municipal authorities' labour and material indices with the base period named - the safest evidentiary choice.
  2. Base index timing: tendered works - the index 28 days before the tender deadline (stated in the tender documents); non-tendered - 28 days before contract signature (A.1.6).
  3. Current indices: several within a period - arithmetic mean over the period, quantity-weighted mean, or the index of the main-consumption period; the parties agree the method or its priority (A.1.5).
  4. No current index yet: adjust provisionally using the previous period's index, truing up later (A.1.2).
  5. Fluctuation bands: allowed bands enter the base index (A.1.1); absent agreement, labour, key materials and fuel/power adjust once swings exceed 5% (8.7.2).
  6. Charging: differences in labour, materials and fuel/power inside the all-in unit rate carry VAT only, never overheads or profit - those risks sit in the bid (3.3.5 item 4).

Applicable boundaries

  • For works contracted on Appendix A.1 index adjustment of labour, key material and fuel/power differences; the price-information method (A.2) computes dP = sum((Ci - C0(1+-r)) x Q) instead - the two never mix on one factor.
  • Not for the eight non-adjustable classes of clause 8.7.6; adjustments during delay periods follow chapter 8 by responsibility.
  • Weights and indices follow the contract; this card gives the standard-level rules, not any project's values; sector or local rules prevail.
  • Versus 2013: "P0 = the amount of the payment certificate", "Ft = the index 42 days before the certificate's final day", "authority indices first" are gone - contracts signed under the old version follow it.

Further reading

GB/T 50500-2024 A.1.1~A.1.6; clauses 3.3.5, 8.7.1~8.7.6; Appendix G Tables G.2.1-1/-2; superseded: GB 50500-2013 A.1.1 and Table-22.