GB/T 50500-2024 list of measurement and pricing risk allocation: Clause 3.3.2 seven employer-borne risks, Clause 3.3.3 eight items for the contractor's tender, and the Clause 6.1.8 tender link
Under GB/T 50500-2024, Clause 3.3.2 lists 7 employer-borne risks (errors and omissions in the BOQ of a re-measurable contract, errors in the employer's original data and datum, approved variations, directed acceleration/early completion/suspension or slowing of the works, changes in laws, regulations and policies, cost fluctuation beyond the agreed range, others), which the contractor's tender need not consider; Clause 3.3.3 lists 8 items the contractor shall consider in its tender (accuracy and completeness of the bill of preliminaries, errors and omissions in the BOQ of a lump-sum contract, the cost of completing all work per the contract drawings, specifications and measurement standards, changes to the contractor's own scheme, causes attributable to the contractor's own plant, technique or management, the contractor's own acceleration or suspension, cost fluctuation within the agreed band, others). The contractor bears its own technical and management risks (e.g. management fees) and a certain market risk, but not the risk of changes in laws, regulations and policies; the tender price shall include the risk costs within the agreed ranges (6.1.8), and where the tender documents are silent, bidders shall seek written clarification from the employer within the prescribed time.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准 第3.3.1~3.3.3条、第6.1.8条
- GB 50500-2013 建设工程工程量清单计价规范(旧版对照)
Topic Positioning
This card itemizes the measurement and pricing risk-allocation lists set out in Clauses 3.3.2/3.3.3 of GB/T 50500-2024, the China national pricing standard for BOQ (Standard for pricing on a bill of quantities basis for construction works) — employer-borne items versus items the contractor shall consider in its tender — and links Clause 6.1.8 on the treatment of risk costs at the tender stage, for quick reference when reviewing contract risk clauses, taking tender pricing decisions, and allocating risk in settlement disputes.
Core Conclusions
General principle (Clause 3.3.1): in construction contracting, the tender documents and the contract shall specify the contents and scope of measurement and pricing risk; wording such as "uncapped risk allocation to one party" or "all risks" shall not be used to agree risk contents and scope; pricing risk reflects the principle of equitable risk allocation — the employer shall state in the tender documents and contract the risk contents and their scope or risk band to be considered by the bidder or contractor.
Employer-borne (Clause 3.3.2): measurement and pricing risks arising from the following shall be borne by the employer and need not be considered in the contractor's tender; the employer shall adjust the contract price in good time under the relevant provisions of Chapter 8, and where the matter affects the programme and meets the contract's programme-adjustment conditions, the contract programme shall be adjusted: ① under a re-measurable (unit-rate) contract, errors and omissions in the BOQ provided by the employer other than the bill of preliminaries; ② errors in the original project data and datum provided by the employer; ③ variations approved by the employer; ④ acceleration, early completion, suspension or slowing of the works required by the employer; ⑤ changes in laws, regulations and policies; ⑥ cost fluctuation beyond the risk scope and band to be borne by the contractor as stipulated in the tender documents, and beyond the range and fluctuation band of changes in costs that shall be adjusted under Section 8.7 of the standard; ⑦ other matters for which the employer should bear responsibility. In addition: costs increased by adjustments to national product standards, technical standards and codes, construction acceptance codes, quality assessment standards and safety operating rules, as well as changes in costs that are adjustable under the contract or, where the contract is silent, adjustable under Section 8.7, are all borne by the employer.
Contractor-borne (Clause 3.3.3): measurement and pricing risks arising from the following shall be borne by the contractor and shall be considered in its tender; changes in the contract price and/or programme caused by them shall be deemed included in the contract sum and the contract programme and shall not be adjusted unless otherwise agreed in the contract: ① the accuracy and completeness of the bill of preliminaries; ② under a lump-sum contract, errors and omissions in the priced BOQ (other than items priced at a unit rate with provisional quantities), and the cost of completing all work required by the contract drawings and contract specifications and all work described in the work-content statements of the national and industry quantity take-off (measurement) standards; ③ under a re-measurable (unit-rate) contract, the cost of completing all work described by the BOQ and its item descriptions and all work described in the work-content statements of the national and industry quantity take-off (measurement) standards; ④ adjustments arising from changes to the contractor's own implementation scheme for reasons attributable to the contractor; ⑤ increases in construction cost caused by the contractor's own use of construction plant, application of construction techniques, and organisation and management level; ⑥ acceleration, suspension or slowing of the works caused by the contractor's own reasons; ⑦ changes in costs within the range and fluctuation band agreed in the tender documents and contract; ⑧ other matters for which the contractor should bear responsibility. The closing passage makes clear: bidders and contractors shall bear their own technical risks and management risks (e.g. management fees) and a certain market risk (changes in costs that are not adjustable under the contract or, where the contract is silent, are not adjustable under Section 8.7), but do not bear the risk of changes in laws, regulations and policies.
Tender link (Clause 6.1.8): the bidder's tender price shall include the risk costs falling within the scope and band to be borne by the contractor as stipulated in the tender documents; where the tender documents do not specify the relevant risk liabilities, the bidder shall, after receiving the tender documents, request the employer to clarify within the prescribed time, and the employer shall give a written reply within the prescribed time.
Applicable Boundaries
Applies to the allocation of measurement and pricing risk in construction contracting under the GB/T 50500-2024 BOQ-based pricing system. Allocation is governed by the tender documents and contract; Clauses 3.3.2/3.3.3 are the fallback allocation where the contract is silent or unclear; approved extensions of time and additions or reductions of cost arising from employer-caused delay follow Chapter 8. Details of adjustment for cost fluctuation are in Section 8.7 and Appendix A (where no band is agreed, the fallback adjustment applies once fluctuation exceeds 5%; the price difference carries value added tax (VAT) only, with no management fee or profit). Pitfalls: errors and omissions in the BOQ of a re-measurable contract go to the employer, those of a lump-sum contract go to the contractor, while errors and omissions in the bill of preliminaries go to the contractor under any contract form; the contractor's scope excludes the risk of changes in laws, regulations and policies. Not applicable to engineering, procurement and construction (EPC/Turnkey) pricing; GB/T 50500-2024 is a recommended national standard, effective 2025-09-01; earlier projects apply GB 50500-2013 (substantially the same conclusions).
Further Reading
See GB/T 50500-2024, the China national pricing standard for BOQ, Clauses 3.3.1–3.3.3 (risk allocation), Clause 6.1.8 (tender price to include risk costs; clarification procedure), Section 8.7 and Appendix A (adjustment for cost fluctuation), Appendix G, Table G.2.1 (adjustable materials and risk bands as a contract annex); for the old-new comparison, GB 50500-2013 Clauses 4.1.2 and 9.5.1. Related cards: determining the scope of pricing risk in the all-in unit rate (contract agreement primary, statutory fallback); risk-bearing for incomplete item descriptions (BOQ errors and omissions); quantity and price risk boundaries across fixed lump-sum, fixed unit-rate and cost-plus contracts; steel price adjustment (Appendix A.2).