Construction Interpretation II, Article 9: where the contract stipulates settlement of the project price at fixed prices, a request to adjust the price on the ground of material changes in labour costs or the prices of key building materials within the construction period is not supported, leaving only two exits: 'the parties have otherwise agreed' and 'change of circumstances under Article 533 of the Civil Code'
In principle, not supported. Under Fa Shi [2026] No. 12 Article 9, where a construction contract stipulates settlement of the project price at fixed prices and a party requests adjustment on the ground of material changes in labour costs or the prices of key building materials within the agreed construction period, the people's court shall not support the request, unless the parties have otherwise agreed or the case satisfies Article 533 of the Civil Code on change of circumstances. Three points of distinction: (1) the rule negates 'adjustment requests premised on material price changes'; it does not invalidate the fixed-price clause; (2) 'the parties have otherwise agreed' is the most-used channel - where the contract lists adjustable materials, agrees a base price and a risk band, an adjustment formula or a source of published price information, adjustment follows the agreement and is not blocked by this Article; (3) only one judicial channel remains, change of circumstances, with a high threshold (unforeseeable at contract formation, a material change outside commercial risk, and manifest unfairness on continued performance) and prior negotiation required.
Applicable Codes
- 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》法释〔2026〕12号 第九条(2026年6月30日施行)、第二十三条
- 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》法释〔2020〕25号 第十九条
- 《中华人民共和国民法典》第五百三十三条
- GB/T 50500-2024 建设工程工程量清单计价标准 第3.3节、第8.7节及App. A、App. G
- GB/T 50875-2013 第3.3.6~3.3.8条
Scope
In fixed-price (fixed lump sum / fixed unit rate) contracts, when labour costs or the prices of key building materials such as steel and cement move sharply during performance, can the contractor break through the fixed price and claim an adjustment? This card gives the negative rule of the judicial interpretation, the two exception channels, and how it connects with contractual price-adjustment clauses and the change-of-circumstances doctrine.
Core conclusions
1. The rule (Fa Shi [2026] No. 12, Article 9, original text): 'Where a construction contract stipulates settlement of the project price at fixed prices, and a party requests adjustment of the project price on the ground that labour costs or the prices of key building materials changed materially within the agreed construction period, the people's court shall not support the request, unless the parties have otherwise agreed or Article 533 of the Civil Code on change of circumstances is satisfied.'
2. Three readings
- Nature of the rule: what is negated is the adjustment request premised on 'material change in labour costs or key building material prices within the period', not the validity of the fixed-price clause - price fluctuation risk rests with the contractor by agreement, the judicial working-out of the quantity-and-price lump-sum essence of fixed-price contracts. Where the contract stipulates settlement at fixed prices, the settlement price is in principle not moved by price changes.
- Exception 1: the parties have otherwise agreed (the most-used channel). Where the contract has agreed an adjustable scope (labour costs and key materials listed as adjustable), a base price, a risk band, an adjustment formula or a source of published price information, that is an 'other agreement': adjustment follows the agreement and is not blocked by this Article; where the band is not clearly agreed, the fallback in the industry pricing standards that 'fluctuation beyond 5% is adjustable' may be referenced, but entry is still through the adjustment mechanism agreed in the contract.
- Exception 2: change of circumstances (Article 533 of the Civil Code). Its elements must be satisfied (unforeseeable at the time of contract formation, a material change outside commercial risk, and manifest unfairness to one party on continued performance); procedurally the party must first negotiate with the other side, and failing agreement request the people's court or the arbitral institution to vary or terminate the contract; the claiming party bears the burden of proof. Ordinary market rises and falls are usually commercial risk and cannot be forced into the change-of-circumstances mould.
3. Distinction from 'switching the settlement to audit by supplementary agreement': this Article deals with whether the amount may be adjusted (price adjustment); audit clauses deal with which figure governs the settlement (the pricing basis) - different questions that do not substitute for each other. A fixed-price contract can neither use audit to re-price around this Article, nor use this Article to resist review of validity for departing materially from the substantive content of the bid-awarded contract.
4. Boundary between the old and new rules: Fa Shi [2026] No. 12 takes effect on 30 June 2026; first-instance construction contract disputes newly accepted by the people's courts after that date apply this interpretation, and SPC interpretations issued earlier that are inconsistent with it yield to it (Article 23).
Boundaries of application
- Applies only to contracts stipulating settlement at fixed prices. Where an adjustable price, cost-plus or a built-in adjustment mechanism applies, the contract and the relevant pricing standards govern, and the negative conclusion of this Article does not apply.
- The adjustable scope is limited to the 'labour costs and key building materials' expressly listed; plant costs, overheads and profit are outside it and cannot be stretched in through this Article.
- The time is limited to price changes 'within the agreed construction period'; the attribution of price fluctuation caused by delay or acceleration must be judged separately under the rules on responsibility for delay and cannot directly borrow this Article's 'within the construction period' limit.
- Procedurally it must be raised as a claim or defence in litigation or arbitration, with the burden of proof carried (the contract agreement, the source of price information and the size of the swing, unforeseeability and manifest unfairness).
- This Article is not an absolute 'prices never adjust' rule: where the contract contains a price-adjustment clause, the agreement governs; the commonest practical error is to negate, under this Article, a contract that already contains an adjustment clause.
Further reading
- SPC Interpretation (II) on Application of Law in Construction Contract Disputes (Fa Shi [2026] No. 12) Article 9; Article 23 of the same interpretation (effective date and the boundary for newly accepted cases).
- Article 533 of the Civil Code (change of circumstances); Construction Interpretation (I) (Fa Shi [2020] No. 25) Article 19 (settlement per the agreed pricing standard or method).
- GB/T 50500-2024 (China national pricing standard for BOQ) Section 3.3 (contract types and the quantity and price risk boundary), Section 8.7 and Annexes A and G (the four elements of material price adjustment, the formulas and the contract annex tables).
- GB/T 50875-2013 Clauses 3.3.6 to 3.3.8 on the division of quantity and price risk between lump-sum and unit-rate contracts.