Whether a supplier may seek a price adjustment when building material prices rise sharply during a fixed-price procurement (sales) contract: routing by contract type (procurement contracts via sales contract rules plus change of circumstances; construction contracts via Interpretation II Article 9; government pricing via Civil Code Article 513), a comparison of three adjustable exceptions and five unsupported scenarios, a legal basis list, and points on evidence, time limits and jurisdiction

As a rule, no. A supplier who has signed a fixed-price procurement contract cannot request an increase merely because building material prices have risen sharply: a fixed price is itself the allocation of price risk, and rises and falls are commercial risks the supplier should bear at the time of contracting. Only three exceptions allow an adjustment: (1) the contract provides otherwise for price adjustment / price fluctuation adjustment (including provisional prices, market-following pricing, or settlement at published price information), adjusted within the agreed band; (2) the subject matter is under government pricing or government guidance pricing and the government adjusts the price within the delivery period, in which case the price at the time of delivery applies (Civil Code Article 513); (3) the case satisfies change of circumstances under Civil Code Article 533 (unforeseeable at contracting, not a commercial risk, continued performance manifestly unfair, and renegotiation required first), and the subject matter is not a bulk commodity of active market attributes with large long-term price fluctuations -- steel, cement and other principal building materials fall squarely within the exclusion proviso of Article 32(1) of Fa Shi [2023] No. 13, so this route usually fails. Fixed prices in construction contracts are governed separately by Article 9 of Fa Shi [2026] No. 12, which leaves only two exits: contrary agreement or change of circumstances.

Applicable Codes

  • 中华人民共和国民法典第五百三十三条
  • 中华人民共和国民法典第五百一十三条
  • 中华人民共和国民法典第五百四十三条
  • 中华人民共和国民法典第一百八十八条
  • 中华人民共和国民事诉讼法(2023修正)第二十四条
  • 中华人民共和国仲裁法(2025修订)第九十条,2026年3月1日起施行
  • 最高人民法院关于适用《中华人民共和国民法典》合同编通则若干问题的解释(法释〔2023〕13号)第三十二条
  • 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)(法释〔2026〕12号)第九条、第二十三条,2026年6月30日起施行
  • GB/T 50500-2024 建设工程工程量清单计价标准 第8.7.2条、第8.7.3条
  • 地方造价主管部门建设工程材料价格风险管控/调差指导意见(政策口径参考):https://zjt.jiangxi.gov.cn/jxszfhcxjst/flfgg/pc/content/content_1765231085540274176.html
  • https://zjt.hainan.gov.cn/szjt/gfxwj/202506/73ac422f4d03411786b656e080796670.shtml
  • https://zjj.wulanchabu.gov.cn/zcfg/1488367.html
  • https://zjj.jiujiang.gov.cn/zmhd/hygq/zdhy/201912/t20191224_2633227.html

Positioning

For procurement (sales) contracts for building materials and equipment at a fixed price (fixed unit rate / fixed lump sum) already signed, whether the supplier can request a price adjustment when material prices rise sharply -- selecting the basis of the claim by contract type, comparing affirmative and negative scenarios, listing the legal bases, and practical procedural points. Intended for construction enterprise material procurement, supplier contract performance and settlement dispute assessment.

Core conclusion

Conclusion: as a rule, no. A fixed price is itself the parties' allocation of price risk; rises and falls are commercial risks the supplier should bear at the time of contracting, and the law does not allow a fixed price to be overturned merely because the rise is large. Only three exceptions support an adjustment: (1) the contract contains a price adjustment agreement (apply the agreement); (2) the subject matter is under government pricing or government guidance pricing (price at the time of delivery); (3) the case satisfies change of circumstances under Civil Code Article 533 and the subject matter is not a bulk commodity with large long-term price fluctuations.

1. First route by contract type to fix the basis of the claim (the step most often got wrong in practice)

Contract type Basis of the claim
Material / equipment procurement contract (supplier vs purchaser) Sales contract chapter of the Civil Code + Article 533 change of circumstances + Article 32 of Fa Shi [2023] No. 13; procurement is commercial sale, with no dedicated judicial interpretation on price fluctuation adjustment
Construction contract (contractor vs employer) Article 9 of Fa Shi [2026] No. 12 (dedicated rule, effective 30 June 2026)
Subject matter under government pricing / government guidance pricing Civil Code Article 513
Article 9 of Fa Shi [2026] No. 12 addresses the 'works price' and cannot be applied directly to the 'payment for goods' under a procurement contract; but its orientation -- a contractual fixed price means the price risk is borne as allocated, leaving only contrary agreement and change of circumstances as exits -- flows from the same adjudicative logic as sales contract cases and may serve as a persuasive reference.

2. Comparison table of affirmative and negative scenarios

# Scenario Conclusion Basis
1 The contract sets an adjustment mechanism (base price, risk band, price information source and adjustment period all defined) Adjustable: no adjustment within the band; the excess is adjusted per the agreement Civil Code Article 543; GB/T 50500-2024 cl. 8.7.2 (where no band is agreed or the agreement is unclear and the market price fluctuation exceeds 5%, the contract price may be adjusted by one of the methods in Annex A)
2 Agreement on 'provisional price', 'market-following pricing' or 'settlement at published price information' Adjustable: settle per the agreed price formation mechanism Civil Code Articles 543 and 533 (agreement prevails)
3 Subject matter under government pricing or government guidance pricing, and the government adjusts the price within the delivery period agreed in the contract Adjustable: the price at the time of delivery applies; for late delivery, on a price rise the original price applies and on a fall the new price; for late collection or late payment, on a price rise the new price applies and on a fall the original price Civil Code Article 513
4 Due to policy adjustment or abnormal changes in market supply and demand, the price moves in a way unforeseeable at contracting, not constituting a commercial risk, with continued performance manifestly unfair, and the subject matter is not a bulk commodity May claim modification or termination (renegotiate first; if that fails, apply to the court / arbitration institution) Civil Code Article 533; Fa Shi [2023] No. 13 Article 32(1)
5 The subject matter is a bulk commodity with active market attributes and large long-term price fluctuations (steel, cement, sand and gravel, asphalt, non-ferrous metals, etc.) Generally not supported: expressly excluded from change of circumstances Fa Shi [2023] No. 13 Article 32(1) proviso
6 The rise sits within a normal market cycle, a seasonal range, or the contract-agreed or fallback risk band (5% as reference where no band is agreed) Not supported: the element 'not a commercial risk' fails Civil Code Article 533; GB/T 50500-2024 cl. 8.7.2
7 Other material price movements that are abnormal yet outside the agreed adjustable scope Negotiable: negotiate a risk band or cost-sharing ratio under equitable risk allocation, bearing the increase (decrease) or adjusting on actual costs GB/T 50500-2024 cl. 8.7.3
8 The contract excludes in advance the application of Civil Code Article 533 The exclusion agreement is void; change of circumstances may still be invoked Fa Shi [2023] No. 13 Article 32(4)

3. Text of the claim basis for change of circumstances (Civil Code Article 533) 'After a contract is formed, the fundamental conditions of the contract undergo a major change that the parties could not have foreseen at the time of contracting and that does not constitute a commercial risk, and continued performance is manifestly unfair to one party, the party adversely affected may renegotiate with the other party; if renegotiation fails within a reasonable period, the party may request the people's court or an arbitration institution to modify or terminate the contract. The people's court or arbitration institution shall modify or terminate the contract in light of the actual circumstances of the case and the principle of fairness.'

4. Table of legal bases

Instrument Provision Version and effective date
Civil Code of the PRC (Presidential Decree No. 45) Articles 533, 513, 543, 188 Effective 1 January 2021
Fa Shi [2023] No. 13, Interpretation on Several Issues Concerning the Application of the General Provisions of the Contracts Part of the Civil Code Article 32 (identifying price-type major changes; bulk commodities and risk-investment financial products excluded; modification preferred; exclusion agreements void) Effective 5 December 2023
Fa Shi [2026] No. 12, Interpretation (II) on Issues Concerning the Application of Law in the Trial of Construction Contract Dispute Cases Article 9 (fixed price in construction contracts not adjusted, save contrary agreement or change of circumstances), Article 23 (effectiveness and application cut-off) Adopted at the 1969th meeting of the SPC Adjudication Committee on 17 March 2026, effective 30 June 2026; applies to first-instance construction contract dispute cases newly accepted after it takes effect; first-instance cases accepted earlier remain governed in principle by the former interpretation; where this Interpretation conflicts with earlier interpretations, it prevails
GB/T 50500-2024, China national pricing standard for BOQ Cl. 8.7.2 (adjustment per Annex A when fluctuation exceeds 5%), cl. 8.7.3 (negotiated risk sharing for abnormal movements of other materials outside the agreed scope) 2024 edition
Civil Procedure Law of the PRC (2023 amendment) Article 24 (contract disputes under the jurisdiction of the court of the defendant's domicile or the place of contract performance) Effective 1 January 2024
Arbitration Law of the PRC (2025 revision) Article 90 (where the law provides limitation periods for arbitration, those provisions apply; absent provision, the rules on limitation of action apply) Effective 1 March 2026

5. Practice points (evidence + procedural time limits + risk traps)

  1. Evidence: the party seeking adjustment must prove the three elements 'unforeseeable at contracting, not a commercial risk, continued performance manifestly unfair' -- through the price level at contracting and the industry's historical fluctuation range, authoritative price indices or published cost information, policy adjustment documents, and 'rise in cost share / loss calculations'; and retain the written exchanges of the renegotiation (renegotiation is a pre-action step).
  2. Procedural time limits: change of circumstances requires renegotiation with the other party first; only where renegotiation fails within a reasonable period may the party request the court or arbitration institution to modify or terminate. The limitation period is three years, counted from the date the right holder knew or should have known of the harm to its right and of the obligor; rights harmed more than twenty years before are not protected (Civil Code Article 188); where the law sets no special arbitration limitation, the litigation limitation rules apply (Arbitration Law Article 90); jurisdiction lies with the defendant's domicile or the place of performance (Civil Procedure Law Article 24).
  3. Risk traps: (1) forcing a procurement contract into Article 9 of Fa Shi [2026] No. 12 (that clause governs only the works price); (2) assuming a 'huge rise' alone establishes change of circumstances and ignoring the bulk-commodity proviso; (3) demanding 'the full price difference' while seeking modification, which exceeds the scope of change-of-circumstances relief (the remedy is modification or termination of the contract, not automatic compensation of the difference); (4) an ill-drafted adjustment clause (missing base price, risk band or information source) that leaves adjustment available in principle but impossible to quantify.

Scope and limits

  • GB/T 50500-2024 applies to pricing between employers and contractors of construction works and does not apply directly to procurement contracts; its 5% band and adjustment methods may be adopted as an agreed or reference basis, but not as a statutory basis for adjusting price under a sales contract.
  • Civil Code Article 513 applies only where the subject matter is under government pricing or government guidance pricing; market-priced building materials are not covered.
  • The bulk-commodity proviso makes the most common scenario -- rises in steel, cement and other principal building materials -- nearly impossible to adjust through change of circumstances; the route runs back to the contract agreement.
  • Adjustment of the works price under a construction contract and adjustment of payment for goods under a procurement contract are two separate regimes and must not be mixed; the same price event may yield different conclusions under the two contracts.