Whether completed but unaccepted sub-divisional work items can be measured and claimed for progress payment: the quality-pass threshold to measurement and the negative rules barring valuation, exceptions for causes not attributable to the contractor and the measurement of rework quantities, the timing distinction between pre-concealment measurement and the final account, and the deduction rules when quality failures are found after measurement

Passing quality acceptance is a substantive threshold to measurement, not a formality: the object of measurement must be 'qualifying work the contractor has completed per the contract requirements and that is to be measured' (GB/T 50500-2024 cl. 7.1.1), and work not accepted under the quality acceptance standards, or failing acceptance, is withheld from measurement and valuation for payment by the project supervision office (TB 10402-2019 cl. 6.0.6 item 2) -- so it can be neither claimed for measurement nor enter progress payment; after rectification, rework and a passed re-inspection, measurement resumes for the same location. The only exception sits on the responsibility side: rework caused by a variation or by employer responsibility is measured per the rework items and quantities fixed in the rework confirmation sheet and the costs are compensated (cl. 7.6.1, 7.6.4); rework quantities caused by the contractor are not measured and the costs are borne by the contractor. Measurement results not checked in time may be deemed approved, but must not serve as evidence that the works have been delivered as accepted (cl. 7.1.5); where a quality failure is found after measurement, the employer may deduct repair and rework costs in the final account (cl. 10.3.13) and, within the defects liability period, deduct repair costs from the retention money (cl. 10.5.3).

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准 第7.1.1、7.1.2、7.1.5、7.1.8条
  • GB/T 50500-2024 第7.6.1、7.6.4条
  • GB/T 50500-2024 第8.11.10条
  • GB/T 50500-2024 第9.1.12、9.4.1、9.4.11条
  • GB/T 50500-2024 第10.1.4、10.3.13、10.3.14、10.5.3条
  • TB 10402-2019 铁路建设工程监理规范 第6.0.6条
  • DBJ41/T 208-2018 建设工程监理工作标准 第7.3.2条
  • GB/T 50522-2019 核电厂建设工程监理标准 第6.4.2条
  • GB/T 50319-2013 建设工程监理规范 第5.2.14条
  • 建设工程质量管理条例(国务院令第279号)第三十条

What This Card Covers

This card answers whether sub-divisional (divisional) works that are completed but not yet inspected, or that have failed inspection, can enter measurement of the works and progress payment; it also gives the exceptional measurement rules for causes not attributable to the contractor, the responsibility split for rework quantities, the timing distinction between measurement before concealment and taking-over, the sequence between progress payment and quality acceptance, and the deduction paths when quality failures are found after measurement in the same location.

Core Conclusions

1. Precondition of measurement: passing quality is a substantive threshold (a negative rule)

Under the BOQ valuation regime, Standard for Valuation of Construction Works by Bills of Quantities GB/T 50500-2024 cl. 7.1.1: 'Contract works shall be measured as work the contractor has completed per the contract requirements and that is to be measured. Quantities shall be calculated under the relevant national and industry quantity take-off standards agreed by the employer and the contractor, and any supplementary measurement rules.' The same clause, second paragraph: 'Re-measurement of contract works, measurement of variations and measurement of additional works shall be based on the qualifying work the contractor has completed per the contract and that is to be measured, and on the construction drawings and variation instructions issued by the employer, using the national and industry quantity take-off standards agreed in the contract and any supplementary measurement rules.' Cl. 7.1.2: 'The employer and the contractor shall measure the works at the time points, physical-target points or progress points agreed in the contract, per Sections 7.2 to 7.7 of this standard. Measurement for progress payment may follow Section 9.4 of this standard.' So the object of progress payment measurement is likewise confined to qualifying work.

The negative interception is enforced through the supervision codes:

  • Code for Supervision of Railway Construction Works TB 10402-2019 cl. 6.0.6: 'The project supervision office shall withhold measurement and valuation for payment for any of the following: 1 works whose commencement report is unapproved; 2 works not accepted under the quality acceptance standards, or failing acceptance; 3 works beyond the construction drawings or beyond the approved design changes; 4 works involving unlawful subcontracting or contract transfer; 5 other cases withheld from measurement and valuation for payment.'
  • Standard for Construction Supervision Services DBJ41/T 208-2018 cl. 7.3.2: measurement of the works must satisfy 'matching the payment items agreed in the construction contract', 'meeting the quality requirements agreed in the contract' and 'complete acceptance formalities'; 'quantities shall not be measured where inspection application documents are incomplete, where the work does not match the contract documents or design documents, where it is unaccepted or has failed acceptance, where rework was caused by the contractor, or where quantities exceed the measurement standards.'
  • Standard for Construction Supervision of Nuclear Power Plant Projects GB/T 50522-2019 cl. 6.4.2: 'Measurement of the works shall be based on quantities actually executed and confirmed by the professional supervising engineer under the measurement rules agreed in the contract; for parts of the works that fail acceptance or do not comply with the construction contract, the project supervision office shall not measure them.'

Conclusion: where a sub-divisional item is unaccepted or has failed acceptance, the supervisor's refusal to sign the inspection application leaves no measurement output, so no progress payment certificate can be issued -- the work can neither be claimed for measurement nor enter progress payment. After rectification, rework and a passed re-inspection, measurement resumes for 'the same location'; this is original quantity, not additional quantity.

2. Exceptions: divided by attribution of responsibility

  1. The measurement gate for rework and for written-off or scrapped materials (GB/T 50500-2024 cl. 7.6.1): 'Where a variation or an employer-responsibility event causes rework of part or all of the work the contractor has completed, or causes purchased or processed materials of the contractor to be written off or scrapped, the contractor shall request rework confirmation from the employer in writing within the time agreed in the contract and provide the supporting documents. If the contractor does not request rework confirmation within the agreed time, it shall be treated that the variation instruction or employer-responsibility event caused no rework of the works and no write-off or scrapping of purchased or processed materials; the rework quantities shall not be measured and the related costs shall not be compensated.' Second paragraph of the same clause: 'For rework of completed work or write-off or scrapping of purchased (processed) materials caused by a variation or employer responsibility, the rework quantities shall be calculated and the employer shall compensate the contractor for the related losses and (or) direct costs of executing the rework.'
  2. Split of cost bearing and measurement scope (cl. 7.6.4): 'For items involving rework, the responsibilities of the employer and the contractor shall be clarified per the contract, and the costs caused by the rework shall be borne by the responsible party. Where the cause is a variation or employer responsibility, the rework items and their quantities in the rework confirmation sheet, and the purchased and processed materials written off or scrapped and their quantities, shall be the measured quantities of that rework and the basis for pricing the rework under the contract price adjustment rules of Chapter 8 of this standard; where the cause is the contractor's responsibility, the related rework quantities shall not be measured.' It also states that where the contractor fails to perform as agreed in the contract, 'the rework confirmation sheet cannot be used to calculate rework compensation'.
  3. Claim basis for employer responsibility (cl. 8.11.10): where events caused by employer responsibility cause economic loss, added cost and (or) delay, then besides cost and time claims 'profit may also be claimed'; the listed events include 'the employer's late provision of construction drawings or the site', 'setting-out errors or rework of the contractor caused by the employer', 'delay, suspension of the works, or failure to resume on time after suspension caused by the employer', and 'the employer's occupation of the works before completion'; 'for events of economic loss and (or) delay caused by government authorities, the time shall be extended accordingly and the economic losses suffered by the employer and the contractor are borne by each party itself'.
  4. Where works are halted or slowed, or drawings and source data are delayed, for reasons not attributable to the contractor, locations already completed and passing inspection remain work 'completed per the contract requirements and to be measured': they are measured as usual and enter progress payment; rework, protection and standby losses are claimed separately per the rework confirmation sheet and the Chapter 8 basis.

3. Timing distinction: measurement before concealment versus taking-over

  • Before concealment is an in-process point: before concealing concealed works the contractor shall notify the employer and the construction quality supervision authority (Regulation on Quality Management of Construction Works, Article 30); the supervisor inspects the concealed works, inspection lots, sub-divisional works and divisional works submitted for inspection, signs off those that pass, and refuses to sign those that fail while requiring rectification within a time limit and re-submission; for work already agreed to be covered but of doubtful quality, or covered without consent, the supervisor may require drilling probes or stripping for re-testing -- where re-testing proves compliance with the contract, the employer bears the added costs and (or) delay and pays a reasonable profit; otherwise the contractor bears them (GB/T 50319-2013 cl. 5.2.14). The pre-concealment sign-off feeds the in-process measurement of the current period.
  • The final account is a different point: once the contract works as a whole pass taking-over, the employer and the contractor shall complete the final account within the settlement period agreed in the contract (GB/T 50500-2024 cl. 10.1.4). Passing in-process measurement does not mean passing handover.

4. Sequence between progress payment and quality acceptance

  • Cycle and milestones: the employer and the contractor shall, at the times or physical-progress points and by the procedures and methods agreed in the contract, measure and pay progress payment for completed work in each measurement period, and the measurement period shall match the payment cycle; where the contract is unclear, measurement and payment may proceed monthly in instalments (cl. 9.4.1).
  • Checking and payment: the employer shall check a progress payment application within a reasonable time after receipt, issue a progress payment certificate upon confirmation and pay on time; where the parties dispute the measurement or valuation of some BOQ items, the employer shall issue the certificate and pay progress payment on the undisputed parts (cl. 9.4.11).
  • Limits of the effect of measurement output (cl. 7.1.5): 'If the employer does not provide the checking result within the agreed time, the measurement output submitted by the contractor may be deemed accepted by the employer; unless the contract provides otherwise, that measurement output may serve as the basis for calculating the works payment, but shall not serve as the basis that the relevant works have been delivered as accepted.' -- This is the key sentence dividing 'completed / measured' from 'accepted'.
  • Use of measurement output (cl. 7.1.8): 'Measurement output of the works signed and confirmed by the employer and the contractor shall be the basis for contract price adjustment and construction payment settlement, except where the contract provides otherwise or the parties expressly limit it to a basis for progress payment or state that it is a rough estimate.'

5. Clawback rules when quality problems emerge after measurement

  1. Deduction at the final account stage (cl. 10.3.13): 'Where work quality fails due to the contractor, the employer may require the contractor to rectify to acceptance; if the contractor fails to rectify after rectification or does not rectify, the employer may, per the contract, require the contractor to bear repair, rework and similar costs and deduct them in the final account of the works. Where the employer suffers loss from this, it may claim against the contractor under cl. 8.11.18 of this standard. The employer may deduct from the total final account the price of quality defects that the contractor still cannot rectify after rectification and that are unrepairable; repairable quality defects are repaired by the contractor, and the costs incurred are borne by the contractor. Where the employer and the contractor dispute a quality defect, both shall jointly engage a specialist quality appraisal body, determine the treatment per its findings, and the cost of the appraisal body may be borne by the responsible party.'
  2. Handling quality objections alongside the final account (cl. 10.3.14): for works that have passed taking-over, or are complete but unaccepted yet put to premature use by the employer, quality disputes are handled under the works warranty contract or the warranty clauses of the contract, and the final account proceeds per the contract; for works complete but unaccepted and not in use, and for suspended or halted works, the disputed part may be tested by an agency with testing and appraisal capability, and the final account is completed after the solution is fixed by the test results or after the decision of the construction quality supervision authority is implemented; the final account for parts without quality objections proceeds per the contract.
  3. Repair deductions within the defects liability period (cl. 10.5.3): if the contractor refuses to repair or fails to repair within a reasonable time and still does not repair after the employer's written notice, the employer may repair itself or engage a third party; the contractor bears the repair cost, and the employer may deduct it from the retention money or the warranty bond; where the cost exceeds the security amount, the employer may claim under cl. 8.11.18.
  4. Self-correction of progress payment (cl. 9.1.12): where a progress payment contains omissions, duplications or errors, either the employer or the contractor may apply for correction; per the method of cl. 9.1.6 for accounting the cumulative value of work completed, the amount is paid or deducted in the next progress payment.

Applicability Boundaries

  • The card applies to measurement of the works, progress payment and settlement payment under construction contracting contracts; GB/T 50500-2024 is a recommended national standard whose rules become contractual obligations only through contractual agreement (or incorporation via tender documents or the contract); where the contract provides otherwise on non-measurable cases, the agreement prevails.
  • Railway works follow TB 10402-2019 (the measurement-and-valuation-for-payment regime of railway practice); nuclear power works follow GB/T 50522-2019; local supervision standards (such as DBJ41/T 208-2018) are valid only within their own administrative regions -- cross-sector or cross-region citations must be checked for scope and should not be interchanged.
  • Deemed approval of measurement output on lapse of time (cl. 7.1.5) resolves only the 'basis for calculating payment'; it expressly 'shall not serve as the basis that the relevant works have been delivered as accepted', and cannot excuse rectification, rework or acceptance obligations.
  • If the contractor fails to request rework confirmation within the contract time, it loses the right to measurement of rework quantities and cost compensation; rework quantities caused by the contractor's responsibility are never measured, and the rework confirmation sheet cannot be used to compute rework compensation.
  • For causes attributable to government authorities (not a breach by either party), time is extended but each party bears its own economic loss; the employer-responsibility cost-plus-profit claim basis does not apply.
  • The settlement basis for payment for completed work and material cancellation losses upon termination of the contract for force majeure has its own clause (cl. 10.4.2) and is outside this card's 'no measurement without acceptance' scope; the judicial payment consequences of non-conforming work (acceptance after repair, deemed approval from premature use of the works without taking-over, etc.) are covered by cards on contract payment and acceptance responsibility.

Further Reading

  • GB/T 50500-2024 Standard for Valuation of Construction Works by Bills of Quantities: cl. 7.1.1, 7.1.2, 7.1.5, 7.1.8 (object of measurement and effect of measurement output); cl. 7.6.1, 7.6.4 (rework measurement and responsibility); cl. 8.11.10 (employer-responsibility claims including profit); cl. 9.1.12, 9.4.1, 9.4.11 (progress payment correction and payment); cl. 10.1.4, 10.3.13, 10.3.14, 10.5.3 (final account and quality deductions).
  • TB 10402-2019 Code for Supervision of Railway Construction Works: cl. 6.0.1 to 6.0.8 (cost control, measurement and payment sign-off procedures, the five cases withheld from measurement and valuation for payment, final account review).
  • DBJ41/T 208-2018 Standard for Construction Supervision Services: cl. 7.3.2 (measurement requirements and non-measurable cases).
  • GB/T 50522-2019 Standard for Construction Supervision of Nuclear Power Plant Projects: cl. 6.4.2 (measurement based on actually executed and confirmed quantities).
  • GB/T 50319-2013 Code for Construction Project Supervision: cl. 5.2.14 (acceptance of concealed works, inspection lots, sub-divisional and divisional works, and cost allocation for re-testing).
  • Regulation on Quality Management of Construction Works (State Council Decree No. 279), Article 30 (pre-concealment notice to the employer and the quality supervision authority).