Brick permanent formwork (brick mold / brick side form): quantity calculation and pricing calibers — by volume, priced under brick-foundation items, plastering separate, with regional measure-item differences
Brick formwork quantities are computed by design-shown volume (m3): centerline length around the wrapped member x masonry height x design thickness, with brick-foundation rules (no deduction of spread-footing T-joint overlaps or single holes <= 0.30 m2). The mainstream pricing applies the "brick foundation" item — expressly in railway TB/T 10831-2024, Shenzhen SJG 111.2-2022, and Shaanxi's new draft; inner-face plastering prices separately under interior general plaster (Shenzhen: labor x 0.90); positions with brick formwork take no concrete side formwork. Regional difference: Shenzhen's building system lists brick formwork and its plastering under measures — concrete/reinforced formwork (SJG 77-2020, 5.5.3).
Applicable Codes
- DB11/T 2382-2024《建设工程施工消耗量标准》第4.5节、附录A表A.4.1
- TB/T 10831-2024《铁路工程预算定额 第十册 房屋工程》册说明第三节
- SJG 111.2-2022《城市地下综合管廊工程消耗量标准(第二册 管廊建筑与装饰工程)》
- SJG 77-2020《房屋建筑工程造价文件分部分项和措施项目划分标准》第5.5.3条
- GB/T 50854-2024《房屋建筑与装饰工程工程量计算标准》附录D表D.1.1
- 陕西省新编消耗量定额(征求意见稿)砌筑工程章
- https://zjt.jiangxi.gov.cn/jxszfhcxjst/wjtz/pc/content/content_1765341789538676736.html
- https://zjt.jiangxi.gov.cn/jxszfhcxjst/wjtz/pc/content/content_1765341564921114624.html
- https://zjt.jiangxi.gov.cn/jxszfhcxjst/wjtz/pc/content/content_1765347917509095424.html
- https://zjt.jiangxi.gov.cn/jxszfhcxjst/wjtz/pc/content/content_1765347419364192256.html
- https://zjt.jiangxi.gov.cn/jxszfhcxjst/wjtz/pc/content/content_1765346893465579520.html
- https://zjt.jiangxi.gov.cn/jxszfhcxjst/wjtz/pc/content/content_1934453988580843520.html
- https://zjt.jiangxi.gov.cn/jxszfhcxjst/wjtz/pc/content/content_1930526198311608320.html
- http://jsj.jinhua.gov.cn/col/col1229168694/art/2026/art_702c92a217ea4d0ea9c62f4a7c382e2b.html
Topic Positioning
Quantity rules and pricing calibers for brick permanent formwork (brick mold / side form — masonry built at the side-form position of underground concrete members). Compiles railway, Shenzhen, Beijing, and Shaanxi standards into a complete "takeoff — pricing — plastering — anti-duplication — regional difference" chain.
Core Conclusions
1. Takeoff: by volume (m3), brick-foundation caliber V = sum(centerline length x masonry height x design thickness), taken around pile caps, grade beams, raft drop panels, sumps, etc., from bedding top to the member design level; thickness per design (commonly 120/180/240mm). Detail rules follow brick foundations (Beijing DB11/T 2382-2024, 4.5.6): "Foundation quantities by design-shown volume, including attached-pier widening, deducting grade beams (ring beams) and constructional columns; not deducting spread-footing T-joint overlaps, embedded rebar/iron/pipes, damp courses, or single holes <= 0.30 m2; no addition for heating-trench cornices... external walls by centerline, internal by net length." Railway TB/T 10831-2024 agrees; GB/T 50854-2024 Table D.1.1 (010401) likewise by volume.
2. Pricing: "brick foundation" items (express in several regions)
- Railway TB/T 10831-2024 volume notes: "Brick foundations execute one item per brick type/spec regardless of width or spread foot. Brick molds for underground concrete members and masonry retaining walls use brick-foundation items."
- Shenzhen SJG 111.2-2022: "Brick molds for underground concrete members and masonry retaining walls use brick-foundation items." "...one item per brick type/spec regardless of width or footings." "Quantities by design-shown volume in m3."
- Shaanxi new draft: "Brick molds under raft drop panels, masonry retaining walls, and brick bore-pile liners use brick-foundation items."
- Beijing DB11/T 2382-2024 Table A.4.1 items A-4-1~A-4-4 (m3; work: base cleaning, mortar mixing, laying, jointing) — the same mainstream caliber though the text sets no "brick mold" clause.
3. Plastering: separate item Shenzhen SJG 111.2-2022: "Brick-formwork plastering executes interior general plaster with labor x 0.90, else unchanged." (Inner-face plaster often doubles as a waterproof base.)
4. Anti-duplication: no concrete side formwork where brick formwork is used Brick formwork is itself the side-form scheme — do not also price concrete side forms (one of the two).
5. Regional system difference (important) Shenzhen building system, SJG 77-2020, 5.5.3: "Basement masonry includes brick/block/stone walls, partitions, and all foundation bedding except concrete bedding; excludes masonry reinforcement and brick permanent formwork. Basement masonry reinforcement goes to basement rebar; brick permanent formwork and its plastering go to basement measures — concrete/reinforced formwork." I.e., that system lists it under measures, while railway and tunnel systems treat it as divisional masonry (brick-foundation items).
Applicable Boundaries
- Compiles railway TB/T 10831-2024, Shenzhen SJG 111.2-2022/SJG 77-2020, Beijing DB11/T 2382-2024, and the Shaanxi draft; pricing follows the contract and the local current basis/interpretations.
- Volume computation presumes the design fixes thickness, height, and position; curved masonry etc. per norm conversion rules.
- Brick formwork and concrete side forms are mutually exclusive — fix the brick-formwork scope in the method statement before pricing.
Further Reading
- DB11/T 2382-2024 Section 4.5 (4.5.6; Table A.4.1 items A-4-1~A-4-4).
- TB/T 10831-2024 Vol. 10 volume notes, masonry section (brick molds; labor x 1.3 above 3.60m).
- SJG 111.2-2022 masonry section (brick molds; plaster x 0.90).
- SJG 77-2020, 5.5.3 (brick formwork under measures formwork).
- GB/T 50854-2024 Annex D Table D.1.1 (010401).
- Local pricing pages (for verification): Jiangxi https://zjt.jiangxi.gov.cn/jxszfhcxjst/wjtz/pc/content/content_1765341789538676736.html and related; Jinhua http://jsj.jinhua.gov.cn/col/col1229168694/art/2026/art_702c92a217ea4d0ea9c62f4a7c382e2b.html
Keywords
- 砖胎膜
- 砖膜
- 砖侧模
- 砖基础子目
- 砖胎膜抹灰
- 砖基础工程量计算
- 地下混凝土构件砖模