Quantity demarcation and length measurement between risers and branch pipes in water supply and drainage (heating, gas) piping: risers accumulated segment by segment by design level difference (storey-height accumulation only as a check), the tee/cross intersection on the riser centreline as the demarcation point, branch pipes measured from that centre to the fixture inlet, vertical segments measured on isometric drawings and horizontal segments on plans, same-floor versus floor-through drainage branch differences, and parallel risers in one shaft listed pipe by pipe
Riser length is accumulated segment by segment along the pipeline centreline shown on the design as upper level minus lower level; storey-height accumulation is only a check value and never a measurement basis. The demarcation between riser and branch is the tee or cross intersection on the riser centreline; the branch runs from that centre point to the centre of the farthest fixture or equipment connection, and the length of the tee fitting itself is neither deducted nor added (fitting installation is already inside the piping item). Parallel risers sharing one shaft must be itemised pipe by pipe by material, connection form and specification, never merged into one measurement.
Applicable Codes
- GB/T 50856-2024 通用安装工程工程量计算标准 App. K Table K.1.1(code 031001)、K.9.6、K.9.8(Table K.3.1)
- DB11/T 2382-2024 建设工程施工消耗量标准 第6.10.24~6.10.32条
- TB/T 10832-2024 铁路工程预算定额 Vol. 11 给水排水工程 册说明 十二、工程量计算规则
- SJG 111.4-2022 城市地下综合管廊工程消耗量标准(Vol. 4 入廊管线安装工程) 1.2.1 给水排水工程
- GB 50015-2019 建筑给水排水设计标准 第2.1.63条
- CJJ 232-2016 建筑同层排水工程技术规程 第2.0.1条
Topic positioning
In take-off of water supply and drainage (including heating and gas) piping: the demarcation test between 'riser vs branch', the measurement basis of riser length (design level difference or storey-height accumulation), the measuring points where a branch starts and ends, the split of measuring vertical segments on the isometric (system) drawing and horizontal segments on the plan, and how same-floor vs floor-through drainage and parallel risers in one shaft affect itemisation and length. It applies to four yardsticks: BOQ measurement (GB/T 50856-2024 Appendix K), local consumption standards, the railway quota manual and utility tunnel consumption standards.
Core conclusions
I. Measurement basis (original code wording)
- GB/T 50856-2024 'Quantity take-off standard for installation works', Appendix K, Table K.1.1 'water supply, drainage, heating and gas piping (code 031001)', quantity take-off rule: computed by length along the pipeline centreline shown on the design, unit m. The table states that item setting, item description, measurement unit and quantity take-off rules for water supply, drainage, heating and gas piping shall follow Table K.1.1.
- Table K.1.1 notes on related issues, note 8, original text: 'In quantity take-off of piping, no deduction is made for the lengths occupied by fittings such as valves, pressure reducers, steam traps, water meters and expansion joints, or by chambers of any kind; square expansion loops enter the pipe installation quantities at their occupied length, and the all-in unit rate for pipe installation includes fabrication and installation of square expansion loops.'
- Note 9, original text: 'The work content of all piping items shall include pressure testing and purging and cleaning; pressure testing includes the hydrostatic, pneumatic, leakage, pipeline watertightness, ball-passing and vacuum tests required by the design, and purging and cleaning includes the water flushing and air blowing required by the design.'
- Note 6, original text: 'The work content of drainage piping shall include riser access openings and vent cowls.' Note 4, original text: 'The installation positions of all piping refer to indoor and outdoor piping alike.'
- DB11/T 2382-2024 Clause 6.10.32, original text: 'Pipe installation quantities shall be computed by length along the pipeline centreline shown on the design, without deducting the lengths occupied by fittings, valves and accessories. The consumption for pipe installation shall include the fitting of fittings; fitting material quantities may be computed per the quantities shown on the design drawings or per Table 6.10.32.'
- The express source for the branch start point - TB/T 10832-2024 'Railway Works Budget Quota Manual, Volume 11: Water Supply and Drainage Works', volume preamble, XII, quantity take-off rules (I), original text: 'Pipe length is computed as the centreline length shown on the design; branch length is computed from the centre of the main to the centre of the connection at the end of the branch.' (II), original text: 'Pipe quantities are computed in extended metres; the lengths occupied by fittings and valves are already allowed for in the construction wastage of piping, so they are not deducted when computing quantities.'
- SJG 111.4-2022 'Consumption standard for urban utility tunnel works (Volume 4: installation of in-tunnel pipelines)', Volume 4, 1.2.1 water supply and drainage works, original text: 'Pipes of all kinds are installed and itemised separately by material, connection form and specification. Among them, water supply, reclaimed water (grey water) and other pressure-flow pipe installation quantities are computed in metres along the design pipe centreline, the branch length running from the centre of the main to the centre of the end connection of the branch, with no deduction for the lengths occupied by valves, fittings and pipe attachments including fixture assemblies, their lengths being comprehensively allowed for in the construction wastage of piping; where gravity drainage pipes with inspection chambers are designed, the installation quantity is computed in metres along the centreline from chamber centre to chamber centre less the clear inner length of the chambers.'
II. Riser length basis: accumulated segment by segment by design level difference; storey-height accumulation only as a check (measurement rule + derivation)
Basic formula of segment-by-segment level differences:
Lriser = sum(i = 1...n)(Htop_i - Hbottom_i) + sum(j)(Loffset_j)
| Variable | Definition |
|---|---|
| Htop_i | Design level of the pipe centre at the top of riser segment i (m) |
| Hbottom_i | Design level of the pipe centre at the bottom of riser segment i (m) |
| n | Number of segments. Mandatory control points: size-change points, riser offset (transfer) points, the centre of the branch tee at each storey, the bottom take-off point, the roof penetration |
| Loffset_j | Length of the offset segment (horizontal plus inclined) where the riser does not run on one plumb line; it cannot enter the level-difference formula and must be listed separately and added in |
Check formula on storey-height accumulation (quick cross-check only, never a measurement basis):
Lriser ~ sum(k = 1...N) h_k + Dbottom + Dtop
h_k is the storey height of storey k, taken consistently with the level datum of the drawings (+/-0.000 or finished floor level); Dbottom and Dtop are the adjustments for the buried segment at the bottom (basement) and the segment through the roof. Storey-height accumulation leaves out size changes, offset transfers, and over-length buried or roof runs, so it serves only as a deviation check - where the two differ markedly, return to the isometric drawing and check the segment levels.
III. Demarcation between riser and branch (measurement rule + practical determination)
- The demarcation point = the tee or cross intersection on the riser centreline (where the riser throws off a branch). The branch runs from that centre point to the centre of the inlet of the farthest fixture or item of equipment: water supply to the angle valve or connection centre; drainage to the trap or the fixture drain connection.
- The tee or cross body carries no separate length: fitting installation and materials are already inside the pipe installation items (DB11/T 2382-2024 Clause 6.10.32 'the consumption for pipe installation shall include the fitting of fittings'; GB/T 50856-2024 Table K.1.1 note 8, no deduction for lengths occupied by fittings). So the fitting at the demarcation is 'neither deducted nor added'; the intersection centre is the boundary, and neither side's length shifts for the fitting's footprint.
- Fixture-side accessory boundary - GB/T 50856-2024 Table K.3.1 note 1, original text: 'The work content of all sanitary fixtures shall include the water supply attachments such as taps, flexible metal hoses, valves, flush pipes and spray heads, the drainage accessories such as traps, drain plugs and waste outlets, and the connecting pipes furnished with the fixture.' Hence the branch stops at the fixture connection, and the connecting pipes furnished with the fixture count as no further pipe length.
- On the riser side, control points must be set storey by storey and segment by segment vertically (each storey's branch tee, size changes, offsets, bottom take-off, roof penetration), each segment measured by level difference - never replaced by one product of 'number of storeys x storey height'.
IV. Split measurement: isometric (system) drawing vs plan (practical method)
- Plans carry horizontal segments: branch mains, buried or below-slab horizontal runs, and horizontal transfer segments in shafts and trenches, measured along the plan projection centrelines.
- Isometric (system) drawings carry vertical segments: riser segments, roof vent stacks, short vertical fixture drains, and the buried bottom riser segments, measured by the level annotations.
- Closure of the two: the two drawings cross-check at the centreline intersections (tees / crosses, bend corners); one centreline segment is counted once only - where a plan corner and an isometric level change denote the same piece of pipe, no double entry. The sum of horizontal segments should agree with the branch level lines of each storey on the isometric; the sum of vertical segments should agree with the storey heights and the total height.
- This split is a matter of practice (the codes say only 'computed by length along the pipeline centreline shown on the design'); the codes set no measuring tool or order.
V. Effect of same-floor and floor-through drainage on branch measurement (term wording + derivation)
- GB 50015-2019 Clause 2.1.63, term wording: 'same-floor drainage: a drainage arrangement in which the horizontal branch drains are laid within the storey and the fixture drains do not penetrate the floor.'
- CJJ 232-2016 Clause 2.0.1, term wording: 'same-floor drainage: a drainage arrangement in a building drainage system in which the fixture drains and horizontal branch drains do not pass through the structural floor of the storey into the space below, and are laid on the same storey as the sanitary fixtures and connect into the drainage riser.'
- Measurement impact (derivation): the drainage riser is still measured full height, segment by segment, whatever the arrangement; with floor-through drainage each fixture drain penetrating the slab forms a short vertical piece, measured on the isometric and counted in the drainage pipe quantities; with same-floor drainage that penetrating piece disappears, replaced by longer horizontal branch runs within the storey floor (dropped slab or wall chase) and the horizontal connection near the riser, measured on the plan. The test follows the drawn laying position (whether the structural floor of the storey is penetrated), never the system name or the product model.
VI. Parallel risers in one shaft: listed pipe by pipe, never merged (negative conclusion)
- Conclusion: multiple risers within one shaft must be listed and measured riser by riser, separately by material, connection form and specification, never merged into one or measured as a total length. Basis: the item description elements prescribed by Table K.1.1 (material, specification, connection form) are exactly the separation elements; SJG 111.4-2022 'pipes of all kinds are installed and itemised separately by material, connection form and specification'. This conclusion is a determination inferred from 'separate itemisation + item description elements'; the codes carry no express 'no merging' clause.
- A shared shaft, shared supports or shared sleeves does not alter riser-by-riser itemisation; support fabrication, installation and painting are already inside the pipe installation items, so sharing adds no length and calls for no apportionment.
Applicable boundaries
- Do not mix the levels of yardstick: BOQ level GB/T 50856-2024 Appendix K (code 031001); Beijing consumption DB11/T 2382-2024 Chapter 6.10; railway quota TB/T 10832-2024 Volume 11; utility tunnel consumption SJG 111.4-2022 Volume 4. All four agree on 'centreline length, no deduction for fittings and valves', but their cost and consumption rules stand independently.
- The express wording 'branch length is computed from the centre of the main' sits in the railway quota volume preamble (outdoor water supply and drainage) and the in-tunnel pipeline chapter of the tunnel standard; the indoor piping standards (GB/T 50856-2024 Appendix K, DB11/T 2382-2024 Clause 6.10.32) give only 'computed by length along the pipeline centreline shown on the design'. The two are equivalent on the drawings - the centreline intersection at the tee is the start point, and practice follows that.
- Not applicable: for industrial piping (Appendix H), fittings, valves and flanges are separately itemised and counted by count / piece; directly buried prefabricated insulated pipes are itemised under the corresponding items of Appendix H industrial piping works (Table K.1.1 note 10); pipe protective casings are itemised under the corresponding material items (note 11); gravity drainage pipes with designed inspection chambers follow chamber-centre-to-chamber-centre less the chamber clear length under the municipal / tunnel yardsticks.
- Where one riser changes material or connection form across storeys (steel-to-plastic conversion at a transfer storey, electrofusion to butt fusion), itemise by segment; belonging to one riser is no reason to merge.
- This card covers the measurement method only, not price or consumption adjustments (disinfection flushing, labour factor adjustments for ball-passing tests, indoor rainwater factors etc. - see the respective consumption standards).
Further reading
- GB/T 50856-2024 'Quantity take-off standard for installation works', Appendix K, Table K.1.1 (code 031001) and items 4, 6, 8, 9, 10 and 11 of its notes on related issues (see K.9.6); sanitary fixtures Table K.3.1 note 1 (see K.9.8).
- DB11/T 2382-2024 'Consumption standard for construction works', Chapter 6.10, Part III indoor piping, Clauses 6.10.24 to 6.10.32 (including 6.10.26 cooling tower piping above DN400 and multi-split copper pipes as industrial piping, 6.10.27 indoor rainwater pipes at indoor water supply x 0.90, 6.10.28 electrofusion as butt fusion, 6.10.30 labour / material / plant factor adjustments for disinfection flushing and ball-passing tests).
- TB/T 10832-2024 'Railway Works Budget Quota Manual, Volume 11: Water Supply and Drainage Works', volume preamble XII, quantity take-off rules (I) (II) (III).
- SJG 111.4-2022 'Consumption standard for urban utility tunnel works (Volume 4: installation of in-tunnel pipelines)', 1.2.1 water supply and drainage works (the inside-outside tunnel boundary set at the outer edge of the tunnel structure).
- GB 50015-2019 'Design standard for building water supply and drainage', Clause 2.1.63 (same-floor drainage term); CJJ 232-2016 'Technical specification for same-floor drainage of buildings', Clause 2.0.1.