Quantity take-off of cable tray and wireway body length: the segmented formula L = Sum(L_h) + Sum(L_v) for horizontal segments (L_h) and vertical segments (L_v), measurement against the dimensions shown on the design drawings, and the rule of no deduction for bends and tees (Beijing 2021 Consumption Standard, Volume 4, Chapter 11)

Cable trays and wireways are measured by length (extended metres, unit m) against the dimensions shown on the design drawings, without deducting the length occupied by bends and tees. Practice applies the segmented summation formula L = Sum(L_h) + Sum(L_v): horizontal segments are measured along the tray centreline path shown on the plan, vertical segments follow the level difference of the two ends L_v = |H_top - H_bottom| (both ends taken from the same datum); different materials or sizes are accumulated separately, and path increments caused by MEP coordination detours do not adjust the quantity.

Applicable Codes

  • 京建发〔2021〕201号《北京市建设工程预算消耗量标准》通用安装工程第四册 电气设备安装工程(下册)第十一章 配管、配线——说明七、工程量计算规则二
  • DB11/T 2382-2024 · Standard for Construction Consumption of Construction Works (Beijing) 第6.4.106条、第6.4.111条
  • GB/T 50856-2024 · Standard for measurement of general mechanical, electrical, plumbing and fire services (电气设备安装工程附录,桥架/线槽按长度计量口径对照)

Topic positioning

The quantity take-off method for the body length of cable trays (including wireways): the original text of the measurement rule, the segmented measurement formula and variable definitions for horizontal and vertical segments, the treatment of differences between drawing dimensions and the actual routed path after coordinated layout, and the relevant chapter notes of Chapter 11 of Volume 4, Electrical Equipment Installation (lower volume), of the Beijing 2021 budget consumption standard for general installation works. Applicable to electrical installation quantity take-off, settlement checking and measurement before applying quota items.

Core conclusion

1. Original text of the measurement rule (Beijing 2021 Consumption Standard, General Installation Volume 4, Electrical Equipment Installation (lower volume), Chapter 11 'Conduit and Wiring', quantity take-off rules, clause 2)

'2 Wireways and trays are measured by length against the dimensions shown on the design drawings, without deducting the length occupied by bends and tees.'

DB11/T 2382-2024 'Consumption Standard for Construction Works' clause 6.4.106 is to the same effect: 'The quantity of wireways and trays shall be calculated by length against the dimensions shown on the design drawings, without deducting the length occupied by bends and tees.' Clause 6.4.111 restates it. That is: the lengths occupied by bends, tees, crosses and reducers are not deducted, nor are they billed separately as 'pieces' (their installation consumption is already included in the working content of the tray installation line items).

2. Segmented formula and variable definitions (the practical algorithm merging the plan with the schematic/section information)

Total length (extended metres, m):

L = Sum(L_h) + Sum(L_v)

  • L: the measured length of trays of one material and one size band (banded by 'width + height'), in m, in extended metres rather than developed area, consistent with the unit of measurement of the quota line item;
  • L_h,i: the length of the i-th horizontal segment, measured along the path shown on the plan (tray centreline) - straight segments take the drawn length between axes or the annotated dimension; horizontal turns, wall runs, beam runs and detours are measured segment by segment along the drawn polyline and summed;
  • L_v,j: the length of the j-th vertical segment, calculated from the level difference of the two ends: L_v = |H_top - H_bottom|. H is the tray level annotated on the schematic/section/design notes (for example 'tray underside 2.5 m above floor', 'tray top 0.3 m below beam soffit'), and both ends must use the same datum (both underside, both top, or both centreline; never one end underside and the other top);
  • Segmented billing principle: trays of different materials (steel/stainless steel/GRP/aluminium/mesh), different width + height, or different installation positions (horizontal/vertical, indoor/outdoor) are billed and accumulated separately, never merged across sizes;
  • Starting point and crossings: where a vertical segment passes through floors or walls it is measured along the continuous drawn path (including the slab or wall thickness), not just the clear height; the starting datum (tray underside/centreline/top) must be uniform within one item.

3. Measurement basis: differences between drawing dimensions and the actual routed path after coordinated layout

Case Measurement treatment Nature of basis
Path shown on construction plans/sections Measured from the drawn dimensions, as the settlement quantity Main measurement rule ('calculated against the dimensions shown on the design drawings')
Path increments from MEP coordination avoidance, detours, re-bends and minor level adjustments Quantity not adjusted (the contractor's responsibility for organizing and coordinating its own works; the rule opens no adjustment) Drawings-based measurement principle
Design changes, agreed variations, drawing revisions (levels, routing, added vertical segments) Re-measured against the revised drawn dimensions, supported by change orders or site instruction records Exception
Site measurement differs from the drawings, or installation exceeds the design dimensions without change support The excess is generally not measured Drawings-based measurement principle

4. Chapter 11 'Notes' clause 7, wireway and tray installation (key points of the original text, directly relevant to tray pricing)

'1. The working content already includes the installation of supports; the fabrication of the non-proprietary metal supports used is priced under the corresponding line items for metal support fabrication in the ancillary works of Chapter 13. 2. Where the design thickness of the main structure of steel trays exceeds 3 mm, the labour workdays and machine-shifts are multiplied by coefficient 1.2. 3. Stainless steel trays are priced under the corresponding steel tray installation line items, with labour workdays and machine-shifts multiplied by coefficient 1.1. 4. The earthing conductor of mesh trays is based on BV insulated wire; earthing bolts are taken as supplied with the tray.'

DB11/T 2382-2024 clause 6.4.106 corresponds: 'The construction consumption of wireway and tray installation shall include the working content of support installation; where non-proprietary supports are used, support fabrication shall follow clause 6.4.135 of this standard; where the design thickness of the main structure of steel trays exceeds 3 mm ... the labour and plant consumption may be multiplied by coefficient 1.20; stainless steel trays shall follow the corresponding steel tray installation items, with labour and plant consumption multiplied by coefficient 1.10; the earthing bolts of mesh trays may be taken as supplied with the tray, and the earthing conductor may use BV insulated wire.'

Worked example (illustrative values, not project data): horizontal segments 18.6 + 7.2 + 12.4 = 38.2 m; vertical segments 8.1-4.5, 4.5-1.2, 1.2-0.3 totalling 7.8 m; L = 38.2 + 7.8 = 46.0 m.

Applicability boundaries

  • The rule governs the quantity of body installation of trays/wireways; earthing jumpers, fire stopping and (proprietary) supports and hangers are governed elsewhere or already included, and must not be re-billed on this clause.
  • 'No deduction for bends and tees' refers only to their occupied length; it does not mean bends and tees are not installed; their installation consumption is already included in the working content of the tray installation line items.
  • The drawings basis means the construction drawings (plans, schematics, sections, levels annotated in the design notes); where the contract expressly provides 'measurement as executed', that agreement prevails, otherwise drawn dimensions apply by default.
  • Tray body length excludes the cable/wire length itself (wiring is measured separately by single-wire length under the conduit and wiring rules); wiring in or through trays must not be mixed into the tray length.
  • Material and size banding must match the item banding of the consumption standard being applied; the coefficients for steel trays thicker than 3 mm and for stainless steel trays apply only under the corresponding conditions, and whether they stack with other coefficients requires checking the chapter notes.
  • The segmented formula above is a practical measurement algorithm, not a formula stated in the standard; the standard gives only the single rule 'measured by length against the dimensions shown on the design drawings'.

Further reading

  • Jing Jian Fa [2021] No. 201, 'Beijing Budget Consumption Standard for Construction Works', General Installation Works, Volume 4, Electrical Equipment Installation (in two parts; Chapter 11 is in the lower volume) -> Chapter 11 'Conduit and Wiring' -> Notes clause 7 (wireway and tray installation) and quantity take-off rules clauses 1 to 4; the tray installation items banded by 'width + height (mm)' sit in Chapter 11 section 3, selected by material (steel trough/ladder, GRP, aluminium, mesh) and size band.
  • DB11/T 2382-2024 'Consumption Standard for Construction Works', Chapter 6 General Installation Works, 6.4 Electrical Equipment Installation: clauses 6.4.103-6.4.114 (conduit, wiring, wireways and trays, junction boxes, reservation table 6.4.112).
  • BOQ measurement may be cross-checked against the tray and wireway items in the electrical equipment appendix of GB/T 50856-2024.
  • Note: the chapter-notes pages of Chapter 11 are scanned OCR text with table misalignment; the clause wording above follows the restored reading, and formal citation should be checked against the paper/PDF original.