Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-25

BOQ rules for measuring cable trays and raceways by the metre, and the pricing boundary of fittings such as elbows and tees (no separate BOQ itemisation, the installation cost of fittings included in the tray installation quota line item, fire stopping measured separately)

Cable trays and raceways are invariably measured in length 'm' as shown on the design drawings, not by 'piece/unit'; the lengths occupied by elbows, tees, crosses and reducers are not deducted (DB11/T 2382-2024 Clauses 6.4.106 and 6.4.111); at BOQ level they are not itemised separately, and at quota level the installation cost of the fittings is already included in the work content of the tray installation line item (e.g. Beijing line item C4-11-253, whose work content includes 'elbows, tees or crosses... support and hanger installation, earthing'), so no separate installation line item may be applied 'per piece'; fire stopping of holes where trays pass through fire compartment walls is measured separately under fire barrier board and similar items (Beijing C4-8-497, in m2) and is not included in tray installation.

Applicable Codes

  • GB/T 50856-2024 App. D Table D.12.1 配管、配线(code 030412)
  • GB 50856-2013 Table D.11 配管、配线(code 030411)
  • DB11/T 2382-2024 第6.4.103~6.4.114条(Ⅻ 配管、配线)
  • DB11/T 2382-2024 App. C 子目C4-11-253、C4-8-497
  • GB 50168-2018 第8.0.2条

Positioning

This card clarifies the unit of measurement for cable trays (trough-type, ladder-type, tray-type and mesh-type) and raceways, the pricing boundary of 'fittings' - elbows, tees, crosses, reducers - at both the BOQ measurement level and the quota pricing level, and when fire stopping at fire compartment penetrations is measured separately. The BOQ basis is GB/T 50856-2024 Annex D Table D.12.1 (code 030412; formerly Table D.11 of GB 50856-2013, code 030411); the quota basis is Beijing Consumption Standard for Construction Works DB11/T 2382-2024 Clauses 6.4.103~6.4.114 (XII conduits and wiring) and the line items of Annex C by way of example.

Core conclusions

  1. The unit of measurement is 'm', not 'piece'. In Table D.12.1 (the same as Table D.11 of the 2013 edition), in the conduits and wiring section, raceway and tray items are all measured by length as shown on the design drawings, and the item description includes name, model, specification, material, type, earthing arrangement and so on.

  2. The lengths occupied by elbows and tees are not deducted. DB11/T 2382-2024 Clause 6.4.106 and Clause 6.4.111 (the same wording repeated for emphasis): 'The quantities of raceways and trays shall not deduct the lengths occupied by elbows and tees, and shall be calculated by length as shown on the design drawings.' That is, the quantity = the length of the straight sections + the developed length of the fittings along the tray centreline, all counted into the extended metres; fittings are neither deducted, nor given additional length, nor itemised separately.

  3. The installation cost of the fittings is already within the tray installation line item, and no 'per piece' installation line item may be applied additionally. Beijing 2024 consumption standard line item C4-11-253 'steel trough-type tray (width + height) (mm) up to 1200', unit m, work content: 'assembly, installation, fixing, elbows, tees or crosses, covers, partition plates, accessories and support and hanger installation, earthing, etc.' - the installation processes of elbows, tees or crosses are already within the line item; applying a 'per piece' installation line item again is double counting.

  4. Supports: installation included, fabrication measured separately. Clause 6.4.106 provides that the consumption for raceway and tray installation shall include the work content of support installation; where non-fabricated (made-to-measure) supports are used, their fabrication is governed by Clause 6.4.135 (fabrication measured separately).

  5. Coefficient adjustments by tray type (Clause 6.4.106): where the main structure of a steel tray is designed thicker than 3mm, the corresponding steel tray installation item applies, with the labour and plant consumption preferably multiplied by 1.20; stainless steel trays follow the corresponding steel tray installation items, with the labour and plant consumption preferably multiplied by 1.10; for mesh trays, the earthing bolts should be taken as supplied with the tray, and the earthing conductor may use BV insulated wires.

  6. Positioning of the earthing arrangement: GB/T 50856-2024 Table D.12.1 note 9 states that 'the tray earthing arrangement refers to conductor-bonded earthing or dedicated earthing clips', which belongs to the item description; the work content of the tray installation line item already includes 'earthing', so conductor bonding itself is not itemised separately, but different earthing arrangements should be clearly described in the item description.

  7. Fire stopping is measured separately. GB 50168-2018 Clause 8.0.2 requires dense fire stopping with fire-sealing materials at the following holes: 1) holes where cables pass through walls and floors; 2) holes where cables enter panels, cabinets, boxes and enclosures; 3) openings where cables enter or leave cable shafts; 4) holes where cable trays pass through walls and floors; 5) ports where cable conduits enter cable trays, cable shafts, cable trenches and cable tunnels. The Beijing consumption standard sets a separate line item C4-8-497 'fire barrier board', unit m2, work content: 'cleaning, installing fire barrier boards, clearing up, etc.' - stopping and barrier boards are not within the work content of the tray installation line item and shall be itemised and measured separately as hole stopping / fire barrier board items.

  8. Code change: 030411 (GB 50856-2013 Table D.11) -> 030412 (GB/T 50856-2024 Table D.12.1); the itemised content and the length measurement basis are the same, only the coding system is updated - do not mix them in citation.

Boundaries of application

  • The BOQ measurement rule 'measured by length' does not itself mention deduction of fittings; the explicit 'no deduction of the lengths of elbows and tees' is a provision at the consumption standard (quota) level, and the two must be read together; in pricing disputes, cite both the BOQ rule and the local quota explanations.
  • Material cost of the fittings: Beijing line item C4-11-253 lists only 'cable tray 1.0050m' as material and has no separate material line for elbows or tees; the material cost of fabricated fitting assemblies is usually carried into the all-in unit rate with the tray item as unpriced material - this is common pricing practice rather than an express line item provision, and must be checked against the quota explanations applicable at the project location before deciding.
  • The line item numbers (C4-11-253, C4-8-497) and the coefficient values are the Beijing DB11/T 2382-2024 basis, given only to locate the quota line items; other provinces and cities may divide line items differently, include or exclude supports, and set different coefficients - always price under the current standard of the project location. Trays (carrying cables) and raceways (laying insulated conductors) differ in construction and application, and although both are measured in 'm', their pricing line items differ and must not be interchanged.
  • The developed length of a fitting follows the centreline arc length marked in the product catalogue; where the design drawings show only straight runs and corners, confirm with the designer or take catalogue values - do not simply measure the straight lengths.

Further reading

GB/T 50856-2024 Annex D Table D.12.1 conduits and wiring (code 030412) and notes 4 and 9 to that table (pull boxes, tray earthing arrangement); GB 50856-2013 Table D.11 conduits and wiring (code 030411); DB11/T 2382-2024 Clauses 6.4.103~6.4.114 (XII conduits and wiring), in particular Clause 6.4.106 (tray and raceway items, support installation included, 1.20 coefficient for thickness >3mm, 1.10 for stainless steel, earthing of mesh trays), Clause 6.4.111 (no deduction for elbows and tees) and Clause 6.4.135 (fabrication of non-fabricated supports); Annex C general installation works line items C4-11-253 (steel trough-type tray) and C4-8-497 (fire barrier board); GB 50168-2018 Clause 8.0.2 (holes to be sealed by the fire-stopping measures of cable installations).

Keywords

  • 电缆桥架
  • 桥架工程量
  • 弯头三通计价
  • 线槽
  • 不扣除弯头三通
  • C4-11-253
  • 防火封堵
  • 030412

Cited By