Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-25

Measurement boundaries and no-double-counting rules where several circuits share one cable tray and branch conduits run from the tray into the premises (GB/T 50856-2024 Annex D conduit and wiring 030412 + consumption-standard cross-check)

The tray itself is measured once along the design centre-line length (not multiplied by the number of circuits, no deduction for bends or tees); the wiring run inside the tray belongs to the tray alone; the outlet hole where it leaves the tray is the start point of the conduit and the outer edge of the box, cabinet or panel (the conduit mouth) is its end point, the reserve length into the box belonging to the cable or wire (tables D.17.3-8 / D.17.3-5); conduits are measured separately in metres per dedicated branch conduit, with no deduction for the lengths taken up by junction boxes, lamp boxes, switch boxes, socket boxes or connection cabinets. Codes must follow the 2024 edition: conduit 030412001, trunking 030412002 (table D.12.1, code 030412); the 2013 code 030411 (conduit and wiring) is withdrawn, and 030411 in the 2024 edition now denotes overhead power distribution lines of 10kV and below.

Applicable Codes

  • GB/T 50856-2024 通用安装工程工程量计算标准 App. D Table D.12.1(配管、配线,code 030412)及问题说明
  • GB/T 50856-2024 App. D Table D.9.1(电缆安装,code 030409)、Table D.11.1(10kV及以下架空配电线路,code 030411)、Table D.17.3-8、Table D.17.12
  • GB 50856-2013 通用安装工程工程量计算规范 App. D Table D.11(配管、配线,code 030411)
  • DB11/T 2382-2024 建设工程施工消耗量标准 第6.4.103、6.4.106、6.4.107、6.4.108、6.4.109、6.4.110、6.4.111、6.4.112、6.4.113条及Table 6.4.112

Positioning

Answers, for the common electrical riser and feeder scenario in which several circuits share one cable tray and then run in their own conduits into the premises after leaving the tray, how the measurement boundary between tray and conduit is drawn, how BOQ items are split, and which treatments count as double counting or omission. Based on GB/T 50856-2024 (general installation works measurement standard) Annex D (table D.12.1 conduit and wiring; table D.9.1 cable installation; table D.11.1 overhead distribution lines; table D.17.12 notes to table D.9.1) and the chapter notes of the local consumption standard.

Core conclusions

1. First correct the codes (edition-sensitive; citing the old number is always wrong)

  • GB/T 50856-2024: conduit and wiring form table D.12.1, code 030412; conduit 030412001, trunking 030412002, unit of measurement m, 'computed by length as shown on the design drawings'. Within table D.12.1 the 'cable tray' and 'wiring' items sit in later line items of the same table; their last-digit item numbers must be verified word for word against the continuation pages of the standard before being cited.
  • GB 50856-2013 (withdrawn): conduit and wiring formed table D.11, code 030411 (2013 edition: conduit 030411001, trunking 030411002, cable tray 030411003, wiring 030411004).
  • In the 2024 edition 030411 has moved to table D.11.1 'overhead power distribution lines of 10kV and below (code 030411)' and no longer means conduit and wiring; 2013 edition 030411 = conduit and wiring. Any BOQ that writes 'conduit' under 030411 carries a wrong code under the 2024 edition.
  • Cable installation: the 2024 edition has table D.9.1 (code 030409), under which power cables, control cables and cable protective conduits sit (corresponding to the 2013 series 030408).
  • Cable trays and trunking are expressly 'hung back' under the conduit and wiring section in the 2024 edition: table D.17.12 note 3 reads 'cable trays and cable trunking shall be coded and listed under the corresponding items of D.12 conduit and wiring of this standard'; note 1 of the same table: 'the laying method of a cable protective conduit means above ground or underground; the cable protective conduit for conduits entering the premises shall be coded and listed as connecting short conduit under D.12 conduit and wiring of this standard'.

2. Three hard boundary rules for the shared and dedicated segments

The national standard has no dedicated 'shared segment / dedicated segment' clause; the boundary is assembled from three existing rules:

  1. Measure the physical object, do not scale by circuit count. Tray and trunking quantity = design centre-line length x 1, regardless of the number of circuits inside; conduit quantity = the sum of the lengths of the individual conduits (N dedicated branch conduits added one by one). Both fall under 'computed by length as shown on the design drawings'.
  2. One boundary point only; each of the three interfaces is attributed once:
    • the wiring run inside the tray -> charged as tray only (the cable or wire measured separately); conduit must not be charged again (that run has no conduit entity of its own);
    • the outlet hole in the tray side wall or base plate (including outlet sleeves and connecting short conduit) -> start point of the conduit (the conduit entity begins here);
    • the entry point (outer edge of the box, cabinet or panel, or the connecting conduit mouth, or the terminal box) -> end point of the conduit; the reserve length into the box belongs to the cable or wire, not to the conduit, and enters the cable or wire quantity under the wiring reserve (table D.17.3-8, unit m per unit) or the cable reserve and additional lengths (table D.17.3-5), never the conduit quantity.
    • vertical segments: Lv = top installation level - bottom installation level (measured from the tray bottom or top level to the box or cabinet bottom or top level).
  3. One conduit belongs to one BOQ item only; one cable is attributed segment by segment according to its carrier:
    • insulated wires in the conduit -> conduit (030412001) + wiring (wires drawn in the conduit, a line item of the same table D.12.1);
    • cables in the conduit -> the cable is measured per single length under table D.9.1 and its protective conduit is listed as cable protective conduit; the same conduit run must not be listed both as cable protective conduit and as conduit 030412001;
    • the protective conduit of a conduit entering the premises is listed as 'connecting short conduit' per table D.17.12 note 1; that note also states expressly that connecting short conduit applies to prefabricated buildings - in other buildings the connecting short conduit is deemed included in the work content of the related equipment - do not list connecting short conduit separately for non-prefabricated buildings.

3. Measurement formulas

  • Tray: L_tray = sum of the design centre-line lengths (including bends, tees and reducer sections, no deduction).
  • Conduit (circuit i): L_i = sum of horizontal centre-line lengths + sum of (top level - bottom level).
  • Wires in conduit: L_wire,i = L_i + reserve at box, cabinet or panel (table D.17.3-8, m per unit).
  • Cable: L_cable = total single laying route length (tray segment + drawn conduit segment) + reserve and additional lengths (table D.17.3-5).

4. Boxes not deducted, counted separately (verbatim basis)

Note 4 to table D.12.1: conduit runs must be provided with junction boxes and pull boxes where 'the conduit length exceeds 40m with no bend; exceeds 30m with one bend; exceeds 20m with two bends; exceeds 10m with three bends'; vertically run protective conduits must be provided with pull boxes for fixing the wires where 'the wire cross-section is 50mm2 and below and the length exceeds 30m; 70mm2~95mm2 and the length exceeds 20m; 120mm2~240mm2 and the length exceeds 18m'; and 'when measuring conduit, where the design makes no requirement, junction and pull boxes are measured per the above rules'. Notes 5 and 8: 'switch boxes and socket boxes are coded and listed as the junction boxes of this table'. When measuring length, no deduction is made for the lengths taken up by intermediate junction boxes, lamp boxes, switch boxes, socket boxes or connection cabinets (table D.12.1 rules + DB11/T 2382-2024 clause 6.4.103). Note 6 in addition: 'the chasing and cutting needed for conduit installation shall be coded and listed under the corresponding items of Annex N, other and ancillary works, of this standard'.

5. Verbatim chapter notes of the consumption standard (pricing basis, citable as is)

  • Clause 6.4.103: 'conduits shall be set up as items by the influences of material, diameter and laying method, together with the related codes. The quantity is computed by length as shown on the design drawings, without deducting the lengths taken up by intermediate junction boxes, lamp boxes, switch boxes, socket boxes or connection cabinets.'
  • Clause 6.4.106: 'trunking and tray quantities are computed by length as shown on the design drawings, without deducting the lengths taken up by bends or tees'; the same clause also provides that the installation consumption of trunking and trays already includes support installation (non-factory-made supports fabricated on site are priced under clause 6.4.135), that where the design thickness of the main structure of a steel tray exceeds 3mm labour and plant are preferably multiplied by 1.20, and that stainless steel trays are priced as steel trays x 1.10.
  • Clause 6.4.111: 'trunking and tray quantities are computed by length as shown on the design drawings, without deducting the lengths taken up by bends or tees.'
  • Clause 6.4.112: 'wiring quantities are computed by single-wire length as shown on the design drawings (including reserve lengths); where the design and the codes make no express provision, the quantity added by the reserve length of equipment-connecting wires (external in-and-out wiring of panels, boxes and cabinets) may follow table 6.4.112'; table 6.4.112: boxes, cabinets, panels and boards of all kinds per 'height + width (panel face size)'; starters installed alone (without box or panel) and busbar in-and-out boxes 0.30 m per unit; from the ground-level conduit outlet to the power connection box 1.00 m per unit; power supply connected to wires in the conduit 1.50 m per unit; outgoing building wires 1.50 m per unit (the last four measured at the conduit mouth) - 'measured at the conduit mouth' confirms the conduit mouth as the measurement datum on the entry side.

6. Two differences between the BOQ basis and the quota basis (do not mix)

  1. Junction and pull box spacing: BOQ measurement follows note 4 to table D.12.1 of GB/T 50856-2024 at 40/30/20/10 m; applying the consumption standard and checking consumption follows DB11/T 2382-2024 clause 6.4.110 verbatim, '1) conduit length exceeding 30m, no bend; 2) exceeding 20m, one bend; 3) exceeding 15m, two bends; 4) exceeding 8m, three bends'; the vertical-segment figures of the two agree (30/20/18 m). The two sets of figures must not be cited against each other.
  2. Pull-through wires: under the BOQ basis the work content of the conduit item already includes 'pull-through wires' (in the 2013 edition the work content of this item was 'reserving chases'), so nothing is listed separately at BOQ level; DB11/T 2382-2024 clause 6.4.108, however, reads 'works in which the conduit carries no wires shall have a separate pull-through wire item' - at pricing level, where 'the conduit carries no wires', a separate pull-through wire line item must be applied.

7. Double-count and omission self-check (six items)

  1. The run inside the tray also charged as conduit -> double count (two carrier BOQ items on one route).
  2. The tray measured to the centre of the box and the conduit also starting from the centre of the box -> double count; the tray is measured to the outer edge of the entry point only, and the conduit starts at the tray outlet, with a single 'connecting short conduit / outlet sleeve' between them.
  3. Deducting the lengths taken up by intermediate junction boxes, lamp boxes, switch boxes and socket boxes -> under-measurement.
  4. Tray bends and tees listed per 'piece', or their lengths deducted -> wrong (no deduction for bends or tees; the quota work content already includes them).
  5. Pull-through wires for conduits listed again under the BOQ basis -> double count; chasing and cutting go to Annex N.
  6. Tray supports and earthing charged separately -> Beijing 2024 clause 6.4.106 already includes support installation (fabrication of non-factory-made supports under 6.4.135); table D.12.1 note 9: 'the tray earthing method means wire-bond earthing or dedicated earthing-clip earthing' - the earthing method serves only as an item description.

Application boundaries

  • Applies to electrical conduit, wiring and cable installation works of general installation projects measured under GB/T 50856-2024, and to the conversion check of legacy BOQs compiled under GB 50856-2013; the three combined rules 'measure the physical object, one boundary point, reserves belong to the cable' are the prevailing practice but are not express clauses of the national standard - the contract agreement prevails.
  • Confirm the edition of the measurement standard in use before citing: 2024 edition 030411 = overhead distribution lines and 030408 = trolley-wire installation; 2013 edition 030411 = conduit and wiring and 030408 = cable installation.
  • The last digits of the 'tray' and 'wiring' line items and the cable protective conduit item number must be re-verified against the continuation pages of the standard before citing; 'connecting short conduit applies only to prefabricated buildings' is an express restriction of table D.17.12 - do not list it separately for other buildings.
  • The quota and consumption basis is a local standard (DB11/T 2382-2024, Beijing); other regions must apply their own consumption standard for pricing, with spacing figures and work content per the local text.

Further reading

  • GB/T 50856-2024 Annex D: table D.12.1 (conduit and wiring, code 030412) and its notes 1~10 (note 1 connecting short conduit; note 2 conduit names and configurations; note 3 wiring names and forms; note 4 junction and pull boxes; notes 5 and 8 switch and socket boxes listed as junction boxes; note 6 chasing and cutting to Annex N; note 7 wiring reserve into boxes per table D.17.3-8; note 9 tray earthing method; note 10 wire connection methods); table D.9.1 (cable installation, 030409); table D.11.1 (overhead power distribution lines of 10kV and below, 030411); the table D.17.3 series of reserve-length tables (D.17.3-3 in-and-out wiring of panels, boxes and cabinets; D.17.3-5 cable laying; D.17.3-8 wiring into boxes, cabinets and panels, unit m per unit); table D.17.12 (notes to table D.9.1, notes 1 and 3).
  • GB 50856-2013 Annex D table D.11 (conduit and wiring, code 030411) - for legacy BOQ conversion.
  • DB11/T 2382-2024 'Construction works consumption standard', clauses 6.4.103, 6.4.106, 6.4.107, 6.4.108, 6.4.109, 6.4.110, 6.4.111, 6.4.112 and 6.4.113 and table 6.4.112 (reserve lengths for external in-and-out wiring of panels, boxes and cabinets).

Keywords

  • 配管配线
  • 030412
  • 030411
  • 桥架计量边界
  • 出桥架配管起算点
  • 不重复计量
  • GB/T 50856-2024
  • DB11/T 2382-2024