Cost attribution of opening reservations and sleeves in installation works: BOQ listing rules for new construction vs renovation/expansion (GB/T 50856-2024)
In new works, chasing (cutting) chases and hole drilling (opening reservations) are already included in the work content of pipeline installation/conduit items, not listed or charged separately; only renovation/expansion and variations are listed separately under Appendix N (code 031301). Sleeves (steel/plastic) are always listed by count under 031301003 and borne by the installation specialty, with work content covering fabrication and installation, stuffing and sealing, and hole plugging; the quota already includes "coordinating with civil works to reserve holes".
Applicable Codes
- GB/T 50856-2024 通用安装工程工程量计算标准 第3.0.7条、第3.0.10条
- GB/T 50856-2024 App. D Table D.12.1 配管、配线(code 030412)问题说明第6条
- GB/T 50856-2024 App. N Table N.1.1(code 031301)及第N.2.1条
Topic Positioning
The cost attribution and BOQ listing rules for opening reservations, chasing (pressing, cutting) chases, hole drilling, and wall/floor sleeves in installation works, focusing on the charging difference between new works and renovation/expansion/variation works.
Core Conclusions
- New works: chasing chases and hole drilling are already included in the work content of pipeline installation, conduits, and related items, not listed or charged separately (GB/T 50856-2024 Appendix N Clause N.2.1).
- Renovation/expansion and variations: listed separately per Appendix N Table N.1.1 (code 031301) — chasing (pressing, cutting) chases in m, hole drilling by count, with work content including the cutting/drilling and restoration; the cost is borne by the installation specialty (Shenzhen SJG 77-2020 Clause 6.1.9, same caliber: installation-works earthwork, chases and restoration, fire stopping, and sleeve installation are included in the respective specialties).
- Sleeves: steel sleeves (plastic sleeves) through beams/walls/floors are listed under Appendix N 031301003 sleeves, by count, with work content covering fabrication, installation, derusting and painting, stuffing with sealing materials, and hole plugging (Clause 3.0.7); the quota item work content already includes "coordinating with civil works to reserve holes" — reservation coordination is not charged again; sleeve main material + labor + packing + plugging mortar are all borne by the installation specialty.
- Construction cooperation obligation: pipelines through walls/floors shall coordinate with civil works to reserve holes (DB62/T 3029-2018, DB11/T 364-2023, CJJ 127-2009); on-site improvised chiseling is not allowed (GB/T 50905-2014 Clause 10.1.4); chiseling after the fact due to civil-works omissions falls under rework/variation, borne by the responsible party per vouchers.
Applicable Boundaries
Applies to installation BOQ pricing calibers (GB/T 50856-2024); the civil-installation interface should also be checked against local pricing rules and the contract agreement. Normal reservations in new works are not charged separately, but after-the-fact chiseling and special design requirements are exceptions.
Further Reading
GB/T 50856-2024 Clauses 3.0.7, 3.0.10, Appendix N Table N.1.1 and Clause N.2.1; SJG 77-2020 Clause 6.1.9; GB/T 50905-2014 Clause 10.1.4; for construction cooperation see DB62/T 3029-2018 Clause 4.1.6, DB11/T 364-2023 Clause 4.1.2, CJJ 127-2009 Clause 5.1.2.