Charging rules for pipeline pressure testing, flushing, disinfection, and water-quality testing costs (included in BOQ items vs. separately billed under quota norms vs. borne by the employer)
BOQ basis: GB/T 50856-2024 Table K.1.1 note 9 — the work content of all pipeline items includes pressure testing and purging/cleaning, so pressure testing/flushing are not billed separately; municipal quota norms (e.g., SJG 181.4-2024) exclude functional testing and disinfection flushing from pipeline laying, so dedicated quota line items must be applied; the water-quality testing fee is a statutory delivery inspection borne by the employer and is not within installation quota norms.
Applicable Codes
- GB/T 50856-2024 通用安装工程工程量计算标准
- SJG 181.4-2024 市政工程消耗量标准 Vol. 4 给水排水管网工程
- DB62/T 3029-2018 建筑给水排水及供暖工程施工工艺规程
- DB11/T 1835-2021 给水排水管道工程施工技术规程
- GB 50268-2008 给水排水管道工程施工及验收规范
- GB 5749 生活饮用水卫生标准
Topic Positioning
The charging rules for four cost types in pipeline installation works — pressure testing, purging/flushing, disinfection, and water-quality testing: which are included in pipeline installation items, which require separate quota line items, and who bears the testing fee.
Core Conclusions
- BOQ basis: GB/T 50856-2024 Table K.1.1 (code 031001) note 9 — the work content of all pipeline items shall include pressure tests (hydrostatic, pneumatic, leakage, watertightness, ball-passing, vacuum tests, etc.) and purging and cleaning (water flushing, air purging, etc.) — building interior water supply/drainage, heating, and gas pipeline BOQs do not bill these separately; the costs are included in the all-in unit rate for pipeline installation.
- Quota norms fall into two types: for building interior installation quota norms, pressure testing, water-flow testing, and flushing are mostly already included in the pipeline installation line items — check the notes to the selected quota-norm volume before applying; municipal water and sewer network quota norms generally exclude functional testing from pipeline-laying line items, so dedicated line items must be applied by length: "pipeline watertightness test", "pipeline pressure test (pneumatic/hydraulic)", "pipeline disinfection and flushing" (e.g., SJG 181.4-2024 Section 1.3.8).
- Disinfection: before handover of domestic water supply systems, flushing and disinfection are mandatory — soak for 24 h with clean water containing effective chlorine not below 20 mg/L, and flush a second time until samples pass testing (DB11/T 1835-2021); the cost is charged with the municipal "disinfection flushing" line item or with the content already included in the installation line items.
- Water-quality testing fee: before handover, domestic water supply must be sampled and tested by the relevant authorities for compliance with GB 5749, with a test report provided (DB62/T 3029-2018); this fee is a statutory delivery inspection — it is not covered by installation quota norms and is not part of the inspection-and-testing fee within overheads (company and site) (which covers the general appraisal of materials and components); it is borne by the employer, charged under the contract or by site instruction / variation record, or listed under project costs other than the works (land, consents, supervision, etc.).
Applicable Boundaries
Applies to building interior water supply/drainage, heating, and gas pipelines and municipal water supply networks; for industrial pipelines (GB 50235 system), pressure testing and purging/cleaning are included and there is no disinfection step. The "included or not" treatment differs between quota-norm volumes — check the volume notes before compiling a budget to prevent omission or double-counting. Attribution of the testing fee follows the contract; the cost of preparing testing/flushing schemes belongs to overheads (company and site) and is not charged separately.
Further Reading
BOQ basis: GB/T 50856-2024 Appendix K Table K.1.1 note 9; municipal quota-norm line items: SJG 181.4-2024 Volume 4 Section 1.3.8; test parameters and delivery inspection: DB62/T 3029-2018 Clause 4.3.6; disinfection practice: DB11/T 1835-2021 Clause 8.12.9; mandatory requirements: GB 50268-2008 Clause 9.1.10 (pressure test passed, flushed and disinfected, and water quality up to standard before connection to the network for operation).