Charging basis and test quantity (duct developed area) calculation for duct light-leakage method testing (light-leakage test) and air leakage rate testing (air-leakage test)
Duct light-leakage method testing and air leakage rate testing are two different tests, usually carried as separate quota / BOQ items charged separately. Three current bases: (1) separate items by duct developed area (m2) - e.g. railway quota TB/T 10831-2024 FY-2820 light-leakage method testing and FY-2821 air leakage rate testing, unit 10 m2; (2) merged into the ventilation works testing and commissioning BOQ item, measured per system (GB/T 50856-2024 code 030704, a system being all air systems of the ventilation and air-conditioning works); (3) merged into the system adjustment charge at 7% of system labour cost (SJG 111.3-2022 Article 4.1.3, including light-leakage and air-leakage testing costs). Choose one, never stack. Where charged by area, the duct developed area applies (no deduction for inspection holes, measuring holes, supply / exhaust outlets; centre-line length including fittings, deducting components); sampling ratios such as 5% low-pressure, 20% medium-pressure and 100% high-pressure are only quality-acceptance checking quantities - neither the codes nor the quotas convert them into chargeable area.
Applicable Codes
- TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程
- DB11/T 638-2016 房屋修缮工程工程量计算规范 App. C Table C.8.4
- GB/T 50856-2024 通用安装工程工程量计算标准 App. G Table G.4.1、Table G.5.10
- SJG 111.3-2022 城市地下综合管廊工程消耗量标准(Vol. 3 附属设施安装工程)第4.1.3条
- GB 50243-2016 通风与空调工程施工质量验收规范 第6.2.9条
- GB/T 50299-2018 地下铁道工程施工质量验收标准 第17.3.4条
Scope of the question
Duct light-leakage method testing (the light-leakage test) and air leakage rate testing (the air-leakage test) are two different tests. This card sorts out their charging bases (separate quota item / merged BOQ item / coefficient charge) and how the test quantity (duct developed area) is calculated.
Core conclusions
The two tests are listed separately and may be charged separately, with different scopes. Light-leakage testing uses light to check the tightness of duct joints and seams; air leakage testing measures the leakage per unit area under a set pressure. Acceptance division: low-pressure systems mostly use light-leakage testing; medium-pressure systems should be sampled for air leakage after passing light-leakage testing; high-pressure systems should go straight to air leakage testing (GB 50243-2016 Article 6.2.9; GB/T 50299-2018 Article 17.3.4).
Three current charging bases exist; one per project, never stacked: Basis 1, separate quota / BOQ items by duct developed area (m2). The railway quota TB/T 10831-2024 Volume 10 Buildings, Chapter 3 Section 3 item (7) duct testing carries two items: FY-2820 duct testing, light-leakage method; FY-2821 duct testing, air leakage rate; both in 10 m2 (base prices are base-period, not market; the air-leakage base price is about 2.5x the light-leakage one). Work content: making blanking plates, setting up instruments, checking, testing, removing plates. Beijing DB11/T 638-2016 Table C.8.4 separately sets a ventilation works testing and commissioning BOQ item (code 930804), duct light / air leakage tests measured on developed area (m2). Basis 2, merged into the ventilation works testing and commissioning BOQ item, measured per system. GB/T 50856-2024 Appendix G Table G.4.1 lists ventilation works testing, commissioning and testing (code 030704), unit system, calculated on the ventilation and air-conditioning air systems shown on the drawings; the Table G.5.10 notes confirm that a system there means all air systems of the works (counted by number of systems, not by area). Basis 3, merged into the system adjustment charge by coefficient, not charged separately. SJG 111.3-2022 (Volume 3 ancillary installation works) Article 4.1.3: the system adjustment charge is 7% of the system labour cost, within which labour is 35% and materials 65%, including air leakage and light-leakage testing costs; the same article sets scaffolding erection and dismantling at 4% of item labour, likewise 35% labour / 65% materials.
Where charged by area, the area is the duct developed area (m2), same basis as duct fabrication and installation: no deduction for inspection holes, measuring holes, supply and exhaust outlets; length on the design centre line (main and branch divided at centre-line intersections), including elbows, tees, reducers, square-to-round transitions and other fittings, excluding (deducting) the lengths of valves and other components.
Sampling ratio does not equal chargeable area. The checking quantities in GB 50243-2016 Article 6.2.9 are acceptance sampling requirements: micro-pressure systems undergo full visual inspection per workmanship requirements; low-pressure systems sampling scheme II; medium-pressure systems scheme I; high-pressure systems full testing. GB/T 50299-2018 Article 17.3.4 details: low pressure sampled at 5% and not less than 1 system; medium pressure 20% and not less than 1 system; high pressure full; duct systems sampled at 10% and all passing. These govern how many tests are run; neither the codes nor the quotas convert sampling ratios into chargeable area; practice charges the test item on the full developed area of the duct system.
Applicability limits
- The three bases are mutually exclusive: choose one per the current local quota and the contract / BOQ pricing rules; where the local quota has no separate item and no inclusion rule, treat as a supplementary item or a third-party testing fee.
- The railway quota base prices are base-period; adjust to compilation-date prices - not market prices as they stand.
- The two tests apply to different systems: low pressure mainly light-leakage; medium pressure air leakage only after passing light-leakage; high pressure air leakage in full - do not merge the two into one charge.
- The area basis applies only to area-charged quota / BOQ bases; under per-system or coefficient bases there is no area conversion at all.
Further reading
- TB/T 10831-2024 Railway Works Budget Quota Manual, Volume 10 Buildings, Chapter 3 building services works, Section 3 ventilation and air-conditioning, item (7) duct testing, FY-2820 and FY-2821.
- Beijing DB11/T 638-2016 Measurement Code for Building Repair Works, Appendix C (normative), Table C.8.4 ventilation works testing and commissioning (code 930804).
- GB/T 50856-2024 Measurement Standard for General Installation Works, Appendix G Table G.4.1 ventilation works testing, commissioning and testing (code 030704), Table G.5.10 notes, Table G.2.1 duct developed area rules.
- SJG 111.3-2022 Consumption Standard for Urban Utility Tunnel Works, Volume 3 ancillary installation works, Article 4.1.3.
- GB 50243-2016 Code for Acceptance of Construction Quality of Ventilation and Air Conditioning Works, Article 6.2.9 and Appendix C (tightness testing).
- GB/T 50299-2018 Standard for Acceptance of Construction Quality of Underground Railway Works, Article 17.3.4.
Keywords
- 漏光法检测
- 漏风量测试
- 通风管道检测
- 风管严密性检验
- developed (unfolded) area
- 系统调整费
- FY-2820
- 030704