Witnessed inspection items and sampling counts for seismic isolation bearings and dampers, ex-works inspection rates by fortification class, and the bearing and separate listing of testing costs
Isolation bearings and dampers must be witnessed-inspected - commissioned reports on samples drawn and submitted by the contractor or maker are void, and products judged non-conforming may not be used (JGJ 360-2015 clause 3.0.4). Witnessed inspection per clause 4.2.1 covers compression, shear (loading frequency not below 0.02Hz save special design) and ultimate lateral deformation: 2% of the same maker, type and specification and not fewer than 3 pieces, one in every 3 undergoing the large-deformation shear test, and bearings used for the ultimate-deformation test never enter the works. Ex-works sampling per GB/T 51408-2021 clause 5.2.2: special / key fortification classes 100% of every specification, standard class not less than 50% (100% on any failure), each project not fewer than 20 pieces and 4 per specification. The employer lists testing costs separately in the estimate (MoHURD Order No. 57 Article 17); failure to list separately or witness properly draws fines of RMB 30,000-100,000 (Article 47).
Applicable Codes
- JGJ 360-2015 建筑隔震工程施工及验收规范 第3.0.4条、第4.2.1条
- GB/T 51408-2021 建筑隔震设计标准 第5.2.2条
- GB 20688.3 橡胶支座 第3部分:建筑隔震橡胶支座
- JG 118 建筑隔震橡胶支座
- GB 50300 建筑工程施工质量验收统一标准
- 建设工程质量检测管理办法(住建部令第57号,2022)第十七条、第四十七条
Positioning
The sampling counts of site witnessed inspection and ex-works inspection for isolation bearings and dampers, who bears the testing cost, how it is listed in estimates, and the penalties.
Core conclusions
1. Witnessed inspection is mandatory; self-submission is void. JGJ 360-2015 clause 3.0.4: 'Bearings and dampers shall be witnessed-inspected; products judged non-conforming shall not be used.' Commentary: as products bearing on building safety and function, they require site witnessed inspection under GB 50300; commissioned reports on samples drawn or submitted by the contractor or maker are void. Despite certificates and ex-works reports, re-testing is required - sampling and submission witnessed by the trade supervising engineer (or the employer's technical lead), re-tested by a third-party laboratory; non-conforming products never enter the works.
2. Items and counts of witnessed inspection (clause 4.2.1). 'Bearings shall be witnessed-inspected; bearings used for ultimate-deformation testing shall not be used in the works. Results shall meet the design: 1 compression per GB 20688.3; 2 shear per GB 20688.3, loading frequency preferably the design frequency and, save special design, not below 0.02Hz; 3 ultimate lateral deformation per JG 118; bearings over 800mm diameter may be tested at the maximum rare-earthquake displacement.' Counts: same maker, type and specification - 2% of the total and not fewer than 3 for mechanical testing, one in every 3 of the inspected total for the large-deformation shear test. Method: check the reports. Commentary: the 0.02Hz floor makes the results practically meaningful - early drafts had no such condition or only 0.001Hz, far from the seismic working state; Japan requires not below 0.3Hz (isolation period not below 3s).
3. Ex-works rates by fortification class (GB/T 51408-2021 clause 5.2.2). 'Bearings of the isolation course shall be ex-works inspected before installation: 1 special and key fortification classes - 100% of every specification; 2 standard class - not less than 50% of the total, and 100% on any failure; 3 each project not fewer than 20 pieces and 4 per specification; fewer than 4 - test all.' Commentary: bearings are key to isolation safety; controlling ex-works counts is an effective quality lever. Schools, kindergartens and hospitals (not lower than key class) take 100%.
4. The cost interface and the listing channel.
- Employer side: Quality Testing Administration (MoHURD Order No. 57) Article 17 - 'The employer shall reasonably allow for testing costs in the estimate, list them separately and pay timely per the contract.'
- Contractor side: inspection and testing costs sit in overheads - ordinary verification and checking of the works, materials, members and installations (including own-laboratory consumables), excluding tests on new structures and materials, destructive member tests and other special examinations, and excluding tests commissioned by the employer; those run in the employer's other construction costs. Testing of materials with conformity certificates that fails is at the contractor's cost; passing, at the employer's; third-party material and acceptance testing commissioned by the employer per regulations is listed and paid by the employer.
- Hence the witnessed re-testing of bearings (third-party) is not the contractor's inspection cost - the employer lists it separately under other construction costs; ex-works inspection is normally inside the product price.
5. Penalties (Order No. 57 Article 47). 'Employer, contractor or supervision units committing any of the following: order to correct and a fine of RMB 30,000-100,000; harm caused - RMB 100,000-200,000; crime - criminal liability: (1) commissioning unqualified laboratories; (2) failing to list testing costs separately in the estimate; (3) failing to witness as required; (4) samples failing conformity, authenticity or representativeness; (5) directing or implying false reports; (6) altering or forging reports; (7) sampling, specimen making or submission breaching the rules or mandatory standards.'
Applicable boundaries
- Witnessed inspection addresses bearings and dampers; ex-works inspection addresses the bearings of the isolation course - different stages, different counts, neither replacing nor double-charging the other.
- Bearings used for ultimate-deformation testing never enter the works - count this loss in offers and procurement.
- Cost bearing follows the contract first; absent terms, the split above (ordinary checks to the contractor; third-party and special testing to the employer).
- The fortification class fixes the sampling rate - fix the class first (schools, kindergartens, hospitals and care homes not lower than key class), then compute the counts.
Further reading
- JGJ 360-2015 clauses 3.0.4, 4.2.1 and Table 1; GB/T 51408-2021 clause 5.2.2; Order No. 57 (2022) Articles 17 and 47; provincial fee norms, overheads - inspection and testing (e.g. Hubei 2024, Shaanxi 2025).
Keywords
- 隔震支座见证检验
- 出厂检验抽样数量
- 检测费单独列支
- 水平极限变形能力
- 压剪试验加载频率
- 建设工程质量检测管理办法
- 阻尼器复验