Rules for determining retest items and retest frequency (lotting and sampling counts) for materials delivered to site
Retest items are fixed by the "general provisions" of each chapter of the discipline acceptance codes; at least one sample group is taken per manufacturer/variety/type of material on site, and test reports are checked per GB 55016-2021 Clause 5.4.1 (radioactivity, formaldehyde, VOC, benzene, etc.); retest frequency follows delivery batches and product sampling plans (bagged cement 200 t, bulk 500 t, rebar 60 t, mortar 250 m³/500 m³/50 t); certified products or three consecutive first-pass lots may double the lot size once only; retests use witnessed sampling and materials may be used only after passing and supervisor confirmation.
Applicable Codes
- GB 50210-2018 建筑装饰装修工程质量验收标准
- GB 55016-2021 建筑环境通用规范
- GB 50204-2015 混凝土结构工程施工质量验收规范
- GB 50550-2010 建筑结构加固工程施工质量验收规范
- DB22/T 5040-2020 建设工程见证取样检测标准
- DB11/T 695-2017 建筑工程资料管理规程
- DB37/T 5164-2020 建筑施工现场管理标准
Topic Positioning
The complete determination logic for on-site material retesting: what items to retest, how retest frequency (lotting and sampling counts) is fixed, when lots may be enlarged, and how special cases are handled — for material delivery acceptance and documentation.
Core Conclusions
Retest items: fixed by the "general provisions" of each chapter of the applicable acceptance code (e.g., granite radioactivity for stone facing panels, formaldehyde release of wood-based panels, water absorption of exterior ceramic panels and frost resistance in severe-cold regions); the general bottom line is at least one sample group per manufacturer per variety per type delivered, with stricter contract requirements prevailing; simultaneously check test reports per GB 55016-2021 Clause 5.4.1 — radioactivity for inorganic non-metallic materials, free formaldehyde for wood-based panels, VOC/benzene-series content for coatings and adhesives; items for common materials can be found in the "material delivery inspection item list" appendices of local documentation rules. Retest frequency: lot per delivery batch and product sampling plan — bagged cement 200 t and bulk cement 500 t per lot (≥1 test per lot); hot/cold-rolled rebar of the same brand, furnace/heat number, size, and delivery condition 60 t per lot; wet-mix mortar 250 m³, dry-mix masonry/plastering/floor/waterproof mortar 500 m³, dry-mix polymer waterproof and ceramic-tile adhesive mortar 50 t per lot; floor-screed cubes ≥1 group per floor (inspection lot), plus one group per additional 1000 m². Lot enlargement: certified products, or three consecutive lots from the same manufacturer and variety all passing on first test, may have the lot capacity doubled once only; any failure after enlargement reverts to the original capacity and no further enlargement is allowed. System requirements: retests use witnessed sampling and testing; materials may be used only after passing retest and supervisor confirmation; where codes specify check quantities, those govern — product standards are no substitute.
Applicable Boundaries
Applies to the general rules of material delivery retesting for building, municipal, and industrial installation works. The lotting figures exemplified come from local witnessed-sampling standards — cross-province use must be checked against the current local standard; the specific retest item lists follow each chapter of the applicable acceptance code; this card does not contain lotting figures for all materials.
Further Reading
See GB 50210-2018, Standard for Quality Acceptance of Decoration Works, Clauses 3.2.5, 9.1.3, 14.1.3; GB 55016-2021, General Code for Building Environment, Clause 5.4.1; GB 50204-2015, Clause 5.2.1 (note: superseded by GB 55008-2021 — rebar delivery inspection follows the general code); GB 50550-2010, Appendix D (special sampling); witnessed-sampling standards (e.g., DB22/T 5040-2020) and the material inspection item lists in local documentation-rule appendices.