Quantity take-off of electrical conduit: GB/T 50856-2024 table D.12.1 (code 030412) measures by design-drawn length; the horizontal plus vertical segment method, attribution of reserved lengths, and listing rules for exposed versus concealed installation

Under GB/T 50856-2024, conduit and wiring form table D.12.1 with code 030412 (the 2013 edition's table D.11 / code 030411 is superseded; in the 2024 edition 030411 now designates overhead distribution lines of 10kV and below). Conduit is measured in m, calculated as length from the design drawings, without deducting the lengths occupied by junction boxes, luminaire boxes, switch boxes, socket boxes and wiring cabinets within the run. The quantity is L = sum of L_h,i + sum of L_v,j: horizontal segments follow the drawn path of the conduit centreline on the plan (not the straight-line distance between two points), and vertical segments are L_v = upper installation level minus lower installation level. This formula is a take-off decomposition method, not standard text; the reserved length for entering cabinets and panels belongs to the wiring (table D.17.3-8) and must not also be counted into the conduit itself, to avoid double counting.

Applicable Codes

  • GB/T 50856-2024 通用安装工程工程量计算标准 App. D Table D.12.1(配管、配线,code 030412)及问题说明第2、4、5、6、7条
  • GB/T 50856-2024 App. D Table D.11.1(10kV及以下架空配电线路,code 030411)
  • GB/T 50856-2024 App. D Table D.17.3-1~Table D.17.3-8(预留长度及附加长度)
  • GB/T 50856-2024 App. N(其他及附属工程)
  • GB 50856-2013 Table D.11(配管、配线,code 030411,已被2024版替代)
  • DB11/T 2382-2024 建设工程施工消耗量标准 第6.4.103~6.4.114条、Table 6.4.112
  • GB/T 50857-2024 市政工程工程量计算标准 H.8.10
  • SJG 181.7-2024 第6.2.1条;SJG 111.3-2022 第2.2.11条

Topic positioning

This card answers 'how is the quantity of electrical conduit (wire casing) calculated, how is the formula laid out, where do reserves count, and how is the BOQ code written': taking the measurement rules of table D.12.1 of appendix D to GB/T 50856-2024 (conduit and wiring, code 030412) as the baseline, it gives the horizontal / vertical segment method with variable definitions, and clarifies the code changes between the 2024 and 2013 editions, the attribution of reserved lengths, and the listing rules for exposed versus concealed installation.

Core conclusions

1. Correct the code first: in the 2024 edition, conduit and wiring are 030412

  • GB 50856-2013: table D.11, conduit and wiring, code 030411 (superseded).
  • GB/T 50856-2024: conduit and wiring are table D.12.1, code 030412; in the 2024 edition 030411 now designates table D.11.1, overhead distribution lines of 10kV and below.
  • Writing electrical conduit as 030411 under the 2024 edition mis-attaches conduit to overhead distribution lines - a listing error.

2. The standard text contains a single measurement rule

Table D.12.1 conduit item: unit of measurement m; the quantity rule is 'calculated as length from the dimensions shown on the design drawings'; item descriptions cover name, material, specification, installation arrangement, earthing requirements, catenary wire material and specification, and the drawing-in wire; work content includes laying of conduit runs, catenary erection (installation of tension devices), wire drawing-in and earthing.

Scope of installation arrangements (original text of note 2 to table D.12.1): 2 The names of conduit include JDG (set-screw) steel conduit, galvanised steel pipe, explosion-proof pipe, flexible metal conduit, plastic pipe, flexible metal hose, corrugated pipe, KBG press-fit steel conduit, etc.; the arrangement refers to exposed, concealed, above suspended ceilings, on steel-support racks, catenary-supported, buried, underwater, inside tanks and vessels, laid in masonry ducts, etc.

The no-deduction position: the notes to table D.12.1 of the 2024 edition do not set out 'without deducting the lengths occupied by junction boxes, luminaire boxes, switch boxes, socket boxes and wiring cabinets' as a separate provision, but this follows from the calculation rule and consistent industry practice, and can be supported directly by quoting local or municipal standards - DB11/T 2382-2024 clause 6.4.103: 'the quantity shall be calculated as length from the dimensions shown on the design drawings, without deducting the lengths occupied by junction boxes, luminaire boxes, switch boxes, socket boxes and wiring cabinets within the run.' The municipal position is the same: GB/T 50857-2024 H.8.10, 'conduit installation does not deduct the lengths occupied by wiring cabinets (boxes), luminaire boxes and switch boxes within the run'.

3. Segment formula and variable definitions (conduit itself, unit m)

L = sum of L_h,i + sum of L_v,j (in summation form: L = Sigma L_h,i + Sigma L_v,j)

Variable Definition Measurement basis
L_h,i Length of horizontal segment i (m) Measured along the drawn path of the conduit centreline on the plan, converted by the drawing scale; runs along walls, at floor or slab level and above ceilings are segmented per the drawn path, not by the straight-line distance between two points; path increments for drawn detours and bends are included
L_v,j Length of vertical segment j (m) L_v = upper installation level minus lower installation level (absolute value), levels taken from the installation levels of boxes and equipment (drawing annotations or equipment data), not measured on site
L Quantity of one conduit run (m) Summarised separately by material, diameter and installation arrangement, each mapping to its BOQ item

This formula is a geometric decomposition method for drawing-based take-off (common industry practice), not a provision of the standard. The standard itself gives only the single sentence 'calculated as length from the dimensions shown on the design drawings'; in settlement checks and audit responses, 'standard text' and 'formula convention' must be distinguished.

4. Reserved lengths belong to wiring, not to the conduit itself

Note 7 to table D.12.1: 'the reserved length for wiring entering cabinets, panels and boards is given in table D.17.3-8.' Beijing DB11/T 2382-2024 clause 6.4.112 is to the same effect: 'the wiring quantity shall be calculated as single-line length from the dimensions shown on the design drawings (including reserved lengths)... the quantity added by the reserved length of wires connecting to equipment (external incoming and outgoing lines of boards, cabinets and panels) may follow table 6.4.112.' Table 6.4.112 values: all cabinets, panels, boards: 'height + width' (face dimensions); starters installed standalone (without cabinet or board), busbar trunking inlet and outlet boxes, etc.: 0.30m (from the centre of the installed object); from the pipe outlet at ground level to the power junction box: 1.00m (measured at the pipe mouth); connection of the supply to the in-pipe wiring (in-pipe wire to flexible or rigid busbars): 1.50m (measured at the pipe mouth); outgoing service line: 1.50m (measured at the pipe mouth). -> Conduit is measured to the pipe mouth at the cabinet or panel per the drawn length; adding the reserve for entering cabinets and panels into the conduit quantity would double-count against the wiring reserve. Tables D.17.3-1 to D.17.3-8 give the additional lengths for flexible busbars, rigid busbars, external incoming and outgoing lines of boards, cabinets and panels, conductor rails, cable laying, earthing busbars, downleads and air termination belts, overhead conductors, and the reserved length for wiring entering cabinets, panels and boards.

5. Exposed / concealed: affects itemisation and rate build-up, not the measurement rule

The installation arrangement is an item description of the conduit item, and items must be listed separately as exposed, concealed, above ceilings, buried, etc. (DB11/T 2382-2024 clause 6.4.103: 'conduit items shall be set according to the influencing factors of material, diameter and laying method, read with the relevant standards'); the measurement rule is the same for every arrangement - all calculated as length from the design drawings - and the differences appear in the quota line items and the work content (e.g. Beijing splits PVC flame-retardant plastic conduit into buried and exposed items). DB11/T 2382-2024 clause 6.4.104: welded steel pipe laying consumption shall include the work content of internal and external painting of the run, and buried steel pipe consumption shall include internal painting.

6. Ancillary measurement details

  • Junction box and pull box placement (original text of note 4 to table D.12.1): a pull box shall be added where the run exceeds 40m with no bends; exceeds 30m with 1 bend; exceeds 20m with 2 bends; exceeds 10m with 3 bends. Where vertically laid conduit protection runs contain wires of 50mm2 cross-section or below, a pull box is added every 30m; 70mm2 to 95mm2, every 20m; 120mm2 to 240mm2, every 18m. In measuring conduit, junction and pull boxes are measured per the above rules where the design is silent.
  • Beijing differs: DB11/T 2382-2024 clause 6.4.110 uses 30m (no bend), 20m (1 bend), 15m (2 bends) and 8m (3 bends); vertical pull box intervals are as the national standard.
  • Switch boxes and socket boxes are listed under the junction box code of table D.12.1 (notes 5 and 8).
  • Chasing and cutting of grooves required for conduit installation are listed under the relevant items of appendix N, other and ancillary works (note 6).
  • Conduit without wires drawn in shall have a separate wire drawing-in item (clause 6.4.108); junction box installation is compiled per single-gang, with factors of 1.50 for two-gang, 2 for three-gang and 2.50 for four-gang (clause 6.4.109); wiring cabinets and boxes are counted as the quantities shown on the drawings.
  • Cable tray earthing method (wire jumper earthing, dedicated earthing clamp earthing) and wire connection method (connector jointing, wrapped and tin-dipped jointing) are item description content and must be described in the BOQ.

Applicable boundaries

  • L = sum of L_h,i + sum of L_v,j is a take-off decomposition method, not standard text; it must not be cited as 'the standard prescribes calculation by the segment formula'.
  • 'Without deducting the lengths occupied by junction boxes, luminaire boxes, switch boxes, socket boxes and wiring cabinets' is not separately listed in the notes to table D.12.1 of the 2024 edition; the provision-level basis is taken from local / municipal standards (DB11/T 2382-2024 clause 6.4.103, GB/T 50857-2024 H.8.10, SJG 181.7-2024, SJG 111.3-2022).
  • Junction box / pull box spacing must follow the pricing basis in force: national 40/30/20/10; Beijing 2024 consumption standard 30/20/15/8; the two must not be mixed.
  • Vertical segments take the absolute difference of the installation levels at the two ends; levels follow drawing annotations and equipment data - this is drawing-based take-off, not site measurement (over-design laying on site without a variation or site record is generally not counted).
  • Conduit above suspended ceilings in fire protection electrical circuits is treated as 'exposed installation' (fire protection required), opposite to the 'concealed' terminology of the water and drainage discipline; take care in listing and applying quota items.
  • This card covers building electrical conduit only; municipal street lighting, utility tunnels and urban underground pipe galleries have their own consumption standards (same calculation rules, different items and factors).

Further reading

  • GB/T 50856-2024 appendix D: table D.12.1 (conduit and wiring, code 030412) and notes 2, 4, 5, 6 and 7; table D.11.1 (overhead distribution lines of 10kV and below, code 030411); tables D.17.3-1 to D.17.3-8 (reserved and additional lengths, table D.17.3-8 being the reserved length for wiring entering cabinets, panels and boards); appendix N (other and ancillary works: chasing and groove cutting).
  • GB 50856-2013 table D.11 (conduit and wiring, code 030411, superseded by the 2024 edition; old codes must not be carried over).
  • DB11/T 2382-2024, Consumption Standard for Construction Works: clauses 6.4.103 to 6.4.114 and table 6.4.112 (reserved lengths for external incoming and outgoing lines of boards, cabinets and panels); chapter 11, conduit and wiring, of volume 4 (general installation works) of the Beijing 2021 budget consumption standard.
  • GB/T 50857-2024 H.8.10 (conduit measurement in street lighting works); SJG 181.7-2024 clause 6.2.1; SJG 111.3-2022 clause 2.2.11 (measurement rules for conduit, wireway, wiring cabinets and boxes).

Keywords

  • 电气配管
  • 配管、配线
  • 030412
  • GB/T 50856-2024
  • 水平段竖向段长度计算
  • 配线预留长度
  • 接线盒拉线盒
  • 明配暗配