Conduit for electrical wiring (including rigid plastic conduit and trunking) crossing building movement joints requires a compensation device fixed at both ends: the code provisions, the two practices (flexible metal conduit / a junction box on each side), segmented measurement on both sides of the joint, and no deduction for the lengths boxes occupy
Where wiring conduits cross building movement joints (expansion, settlement or seismic joints) a compensation device fixed at both ends shall be installed (GB 50575-2010 Clause 3.0.6; GB 51348-2019 Clause 8.6.10; GB 50166-2019 Clause 3.2.3), with conductors fixed on both sides of the crossing and left with suitable slack. The detail may be a flexible metal conduit transition for surface-laid steel conduit (connected via a junction box or an adapter), or a junction box cast in on each side (the far box opened vertically in its base with a bore no smaller than twice the incoming conduit bore) plus a compensating bonding strap connected across. For measurement, the runs on the two sides are each taken to the face of that side's box and gathered as separate segments; the lengths the boxes occupy are not deducted, and the boxes are counted separately per the design drawings; whether the compensation device proper and the bonding strap are itemised separately is checked against the work content of the quota line items in the applicable consumption quota standard.
Applicable Codes
- GB 50575-2010 第3.0.6条及条文说明
- GB 51348-2019 第8.6.10条
- GB 50166-2019 第3.2.3条及条文说明
- T/CMEA 26-2022 第6.2.5条
- DB 51/T 5047-2007 第14.3.20、14.3.27条
- DB11/T 2382-2024 第6.4.103、6.4.113条(计量口径)
Scope of the topic
Compensation-device requirements where wiring conduits (electrical conduit, rigid plastic conduit and trunking) cross building movement joints (expansion, settlement and seismic joints), the two typical details, and, once junction boxes are placed on both sides, how quantities are gathered in segments and how the lengths boxes occupy and the compensation device proper are handled.
Core conclusions
1 Mandatory code requirement: a compensation device fixed at both ends at movement joints
- GB 50575-2010, Code for Construction and Acceptance of Wiring Works at 1kV and Below, Clause 3.0.6: 'Where circuits cross movement joints of buildings or structures, a compensation device fixed at both ends shall be installed.' Commentary: movement joints comprise expansion joints provided for temperature change and settlement joints provided for differential foundation settlement; the building masses on both sides may displace as anticipated, the magnitude being fixed by design calculation. Rigid wiring systems in wiring works -- conduits and the like of every kind -- should as a rule avoid crossing movement joints, so that building movement does not sever the circuit; where a crossing is unavoidable, the run turns from rigid to flexible at the crossing, the so-called compensation device, its two ends fixed to the rigid circuit ends; its expansion allowance and construction details should be taken from the construction design drawings or standard detail albums.
- GB 51348-2019, Standard for Electrical Design of Civil Buildings, Clause 8.6.10: 'Rigid plastic conduit (trunking) crossing a building movement joint shall be fitted with a compensation device.'
- GB 50166-2019, Standard for Construction and Acceptance of Automatic Fire Alarm Systems, Clause 3.2.3: 'Where conduit runs pass movement joints of a building -- settlement, expansion or seismic joints -- compensation measures shall be taken, and cables crossing a movement joint shall be fixed on both sides and left with suitable slack.' Commentary: conduit passing a movement joint (including settlement, expansion and seismic joints) requires compensation measures (adding junction boxes, for example); conductors crossing the joint are fixed on both sides with suitable slack, so that the circuit does not fracture and system reliability improves.
- T/CMEA 26-2022, Technical Regulation for Power Supply and Distribution Systems in Urban Utility Tunnels, Clause 6.2.5: 'Where metal conductor wiring passes a structural expansion joint, junction boxes shall be provided on both sides of the joint and connected by flexible conduit.'
2 Two typical details (workmanship regulations)
- Surface-laid steel conduit (flexible metal conduit transition): DB 51/T 5047-2007, Regulation for Workmanship of Building Electrical Works, Clause 14.3.20 -- surface steel conduit passing an expansion or settlement joint of a building shall carry a compensation device, connected at its middle by flexible metal conduit; the flexible conduit joins the steel conduit via a junction box or an adapter.
- A junction box cast in on each side (common for concealed conduit): Clause 14.3.27 of the same regulation -- cast one junction box into each side of the joint, fix one end of the conduit to its box, open a hole vertically in the base of the other side's box with a bore no smaller than twice the incoming conduit bore, and connect the compensating bonding strap across both sides.
3 Measurement calibre in segments
- Conduit length: the runs on the two sides of the joint break apart, each measured to the face of its own junction box; for runs with boxes, the lengths the boxes occupy are not deducted -- per 'quantities shall not deduct the lengths occupied by intermediate junction boxes, lighting fixture boxes, switch boxes, socket boxes and pulling boxes in the run, and shall be computed by length from the dimensions shown on the design' (DB11/T 2382-2024 Clause 6.4.103). The break is segment-wise gathering, not a deduction: the two short runs still sum to the length measured continuously along the drawn route.
- Boxes as such: counted per 'each' from the quantities shown on the design (DB11/T 2382-2024 Clause 6.4.113: junction boxes and boxes are measured by the quantities shown on the design), tracked separately from conduit length.
- The compensation device proper (flexible metal conduit, adapters, compensating bonding strap): whether it sits within the work content of the conduit or box quota line items, or is itemised separately, must be checked against the work content of the quota line items in the applicable consumption quota standard; a comparable boundary is the treatment 'laying of set-screw (crimp) type thin-walled steel conduit excludes the work content of the bonding conductor, which is computed separately if it occurs' (Beijing Jian Fa [2021] No. 201, General Installation Volume 4, Chapter 11, note 5) -- bonding-conductor content is normally not inside the conduit-laying quota line item.
- Conductor slack: GB 50166-2019 requires cables crossing a movement joint to be fixed on both sides with suitable slack; that slack is a laying allowance, and the wire-drawing (wiring) quota line items already absorb the reserved wire length (Beijing Jian Fa [2021] No. 201, General Installation Volume 4, Chapter 11, note 10: 'the wire-drawing line items already absorb the reserved wire length'), so no extra conduit length is measured for crossing a joint.
Applicable boundaries
- Scope: rigid wiring systems at movement joints (expansion, settlement, seismic) of buildings and structures -- electrical conduit (steel conduit, rigid plastic conduit), trunking and cable trays; the rigid runs flanking a flexible connection are still segmented as above.
- Not a substitute for design: the expansion allowance and the actual construction (whether a box sits on each side, the flexible conduit length) are fixed by design calculation and standard detail albums; the codes mandate only the functional requirement of 'a compensation device fixed at both ends plus conductors fixed on both sides with slack'.
- The detail is not unique: surface runs may transition directly through flexible metal conduit (joined via a junction box or an adapter), while concealed runs usually cast in a box on each side; 'a box is mandatory on each side' is therefore not a universally binding conclusion.
- Quota calibres are regional: consumption quota standards of different provinces and cities word differently whether compensation devices (flexible metal conduit, junction boxes) get their own quota line items and whether the bonding conductor sits within the conduit-laying item; check the local current standard and its quota line item work content before applying rates.
Further reading
- GB 50575-2010 Clause 3.0.6 and its commentary (the two joint types; the rigid-to-flexible and both-ends-fixed principle); GB 51348-2019 Clause 8.6.10; GB 50166-2019 Clause 3.2.3 and its commentary (adding junction boxes; fixing on both sides with slack); T/CMEA 26-2022 Clause 6.2.5 (junction boxes on both sides of a structural expansion joint, connected by flexible conduit); DB 51/T 5047-2007 Clause 14.3.20 (the flexible metal conduit compensation detail for surface steel conduit) and Clause 14.3.27 (the box-on-each-side detail with a hole no less than twice the conduit bore); measurement calibre per DB11/T 2382-2024 Clauses 6.4.103 and 6.4.113, and Beijing Jian Fa [2021] No. 201, General Installation Volume 4, Chapter 11, notes 5 and 10 and calculation rules 1 and 4.
Keywords
- 变形缝补偿装置
- 伸缩缝 沉降缝 配管
- 刚性塑料导管 槽盒 变形缝
- 接线箱 预埋 补偿
- 金属软管 过渡接头
- 导线跨越变形缝 预留余量