Calculation rules and values of reserved (additional) lengths in cable laying quantities

Cable quantity = the single-cable laying length shown on the design + various reserved (additional) lengths; where the design stipulates, follow the design, otherwise take the standard values: slack/bending/crossing add 2.5% (on the base of the drawn length plus the sum of reservations); terminations 0.5 m, joints 0.5 m, entry to distribution panels 1 m, power distribution boards 1.5 m, control panels 2 m, plant transformers 3 m, main transformers 5 m, etc. (GB 50217-2018 Appendix G); directly buried cables entering buildings may take 5% of the route length.

Applicable Codes

  • DB11/T 2382-2024 建设工程施工消耗量标准 第6.4.55~6.4.67条及Table 6.4.55
  • GB/T 50856-2024 通用安装工程工程量计算标准 Table D.9.1(030409)、Table D.17.3-5
  • GB 50217-2018 电力工程电缆设计标准 第5.1.17条、App. G
  • 京建发〔2021〕201号 2021预算消耗量标准 通用安装第四册 电气设备安装工程 第八章 说明第三条及附表2
  • SJG 181.7-2024 市政工程消耗量标准 Vol. 7 第5.2.3条及Table 5.2.3
  • SJG 111.3-2022 城市地下综合管廊工程消耗量标准(Vol. 3)Table 2.2.9
  • https://zjw.beijing.gov.cn/bjjs/gczj14/xhlbz/ys20/cjwd33/743942418/index.shtml
  • https://zjw.beijing.gov.cn/bjjs/gczj14/xhlbz/ys20/cjwd33/743942391/index.shtml

Topic Positioning

The calculation rules and values of reserved (additional) lengths in cable laying quantities (BOQ/budget), solving the general question of "cable quantity = drawn length + how much reservation", covering building M&E installation and municipal calibers.

Core Conclusions

Cable quantity = the single-cable laying length shown on the design (horizontal + vertical routes) + various reserved (additional) lengths; where the design stipulates, follow the design, otherwise take the standard values:

  1. BOQ rule: GB/T 50856-2024 Appendix D Table D.9.1 (code 030409) — power cables/control cables computed in m by single-cable length plus reserved length, with reservations counted into the quantity rather than as loss.
  2. Additional base: slack, bending, and crossing add 2.5%, on the base of "drawn horizontal + vertical lengths + the sum of reserved lengths" — first add the fixed reservations, then multiply by 1.025, without duplicating the fixed reservations.
  3. Fixed reservations (GB 50217-2018 Appendix G, 35 kV and below): termination fabrication 0.5 m, joints 0.5 m, from grade to distribution panel 1 m, workshop power boards 1.5 m, control/protection panels 2 m, plant auxiliary transformers 3 m, main transformers 5 m, motors 0.5~1 m; cable entry into buildings 2 m, entry into trenches/racks or risers up (down) 1.5 m (local consumption-standard caliber).
  4. Special cases: for directly buried cables from the plant area into buildings, the reservations needed for terrain burial, trench/tunnel/rack riser connections, terminations and joints may take 5% of the drawn route length; where the design does not stipulate intermediate joints, the standard is one per 400 m of single cable, one more per additional 400 m (each joint end reserves a 0.5 m stripping section); for above 35 kV the increase from snaked-lay bending is counted into the additional length.

Applicable Boundaries

Applies to quantity calculation of cable laying at 35 kV and below; municipal street lighting/utility tunnels follow GB/T 50857-2024 Appendix H Table H.8.15-3 and SJG 111.3-2022 Table 2.2.9 respectively, with slightly different values; the BOQ and quota calibers must be consistent — where the quota already includes waviness allowances, the BOQ quantity must not multiply the coefficient again; spare lengths near terminations and joints are recommended for maintenance (GB 50168-2018 Clause 6.1.5); the expansion of high-voltage cables is considered in the designed product structure.

Further Reading

See GB/T 50856-2024 Appendix D Table D.9.1; GB 50217-2018 Clause 5.1.17 and Appendix G (the directly buried 5% caliber inherited from the notes of the former Appendix E of GB 50217-2007); SJG 181.7-2024 Clause 5.2.3 Table 5.2.3; SJG 111.3-2022 Clause 2.2.9 Table 2.2.9 (the 400 m intermediate-joint rule); GB/T 50857-2024 Appendix H Table H.8.15-3.

Keywords

  • 电缆敷设
  • 预留长度
  • 附加长度
  • 弛度2.5%
  • 单根长度加预留长度
  • 电缆头按个计量
  • 箱柜高加宽
  • 表6.4.55