Cable laying in vertical shafts (electrical risers): choosing the quota line item, the labour factor adjustment, and pricing the shaft and horizontal sections separately (including where reserve lengths sit and the link to the BOQ code)
DB11/T 2382-2024 clause 6.4.59: cable laying in vertical shafts does not distinguish whether floors exist within the shaft - it follows the corresponding cable laying items, with labour consumption preferably multiplied by a factor of 1.30 (the 2021 edition said labour workdays multiplied by factor 1.3); the factor adjusts labour only and acts on the shaft section only, so one cable must be priced in a shaft section and a horizontal section under separate line items - multiplying the whole cable on the shaft basis does not hold; pre-fabricated branch cables are already comprehensively measured for shaft laying and take no factor; the cable laying length already includes reserve (additional) length, and no separate item is listed; on the BOQ side cable installation is Table D.9.1 code 030409, and shaft laying is a different item description from other laying methods.
Applicable Codes
- DB11/T 2382-2024 建设工程施工消耗量标准 第6.4.55条、第6.4.59条、第6.4.60~6.4.62条、App. G Table G.5.45
- 京建发〔2021〕201号 2021预算消耗量标准 通用安装第四册 电气设备安装工程 第八章 说明第十条、工程量计算规则第一条
- GB/T 50856-2024 通用安装工程工程量计算标准 App. D Table D.9.1(code 030409)、D.17.12 问题说明、Table D.17.3-5
- SJG 181.7-2024 市政工程消耗量标准 Vol. 7 第5.1.2条、第5.2.4条
What this card covers
This card fixes the pricing basis for 'cable laying in vertical shafts (electrical risers / cable shafts)': when a run counts as a vertical shaft, which line item applies, where the labour factor sits, how the shaft and horizontal sections are priced separately, how reserve (additional) lengths relate to the factor, and how the BOQ code links to the sectional quota pricing.
Core conclusions
1. Test and item selection (DB11/T 2382-2024 clause 6.4.59, verbatim)
Cable laying in vertical shafts shall, without distinguishing whether floors exist within the shaft, be priced under the corresponding cable laying items, with labour consumption preferably multiplied by a factor of 1.30.
Broken down: (1) the location = the vertical run laid inside a vertical shaft; (2) whether floors exist within the shaft (whether fire-stopped floor levels are provided) does not affect the item; (3) no dedicated 'vertical shaft' line item is set - the cable laying items of the same cross-section and laying method (on tray / trunking, on supports, in conduit, etc.) still apply; (4) the adjustment touches labour consumption only - materials and plant are not multiplied.
Beijing 2021 edition (Jing Jian Fa [2021] No. 201, General Installation Volume 4, Electrical Equipment Installation Works, Chapter 8, note 10), verbatim:
10 Where cables are laid in vertical shafts, the corresponding line items apply, with labour workdays multiplied by a factor of 1.3; pre-fabricated branch cable laying is already taken as laying in vertical shafts and labour workdays take no further factor.
The two editions differ: 2021 said rigidly 'labour workdays multiplied by factor 1.3'; 2024 says labour consumption 'should preferably be multiplied by a factor of 1.30'.
2. Pre-fabricated branch cables take no further factor
DB11/T 2382-2024 clause 6.4.61:
- 'The construction consumption for laying pre-fabricated branch cables shall be determined comprehensively as cable laying in vertical shafts, including the installation of the branch-cable suspension fittings';
- 'The construction consumption for laying pre-fabricated branch cables is determined for a branch cable length of up to 10 m per branch; where the actual length exceeds 10 m, the consumption for the excess is determined under this standard in light of actual conditions.' And clause 6.4.60: pre-branch cable laying does not distinguish the number of cores but sets items by the cross-section of the main cable, the quantity being the length per the design dimensions of the main cable.
3. Sectional pricing rules
- Factor-type systems (Beijing general installation volumes): the factor is a labour adjustment for 'the laying operation within the vertical shaft'; non-shaft runs (horizontal sections, other locations) stay on the ordinary quota items with no factor. Where one cable passes through a shaft and then runs horizontally, it must be split by location into a shaft section and a horizontal section, lengths collected separately and priced under the same-cross-section laying items - shaft labour x 1.30, horizontal section unmultiplied. Multiplying the whole cable by the factor would inflate the non-shaft section as well and does not hold (a semantic inference from the qualifier 'cable laying in vertical shafts' in clause 6.4.59; the wording does not state verbatim 'the whole cable may not be counted').
- Dedicated-item systems (graded by cross-section, no factor): DB11/T 2382-2024 Annex G Urban Rail Transit Works, Table G.5.45 'power cable laying' contains an item 'power cables laid along vertical shafts', graded by cable cross-section, unit m; example G5-8-70 (cable cross-section up to 300 mm2): work content - preparation, measuring, cable testing, transport, setting up drums, laying cable, cutting, fixing, binding, tagging, records; consumption - comprehensive labour class II 0.4390 workdays/m, cable 1.0100 m/m. In this system the shaft section takes the dedicated item directly, with no further shaft factor.
4. The threshold for 'vertical shaft' (systems differ, do not mix)
- Beijing general installation volumes: judged solely by 'whether laid within a vertical shaft', with no level-difference threshold.
- Shenzhen SJG 181.7-2024 clause 5.1.2: 'The general power cable laying items apply to direct burial, cable trenches, trays and conduit laying of cables, whether inside or outside the plant. Laying in vertical shafts applies to cables laid vertically with a level difference of no less than 20 m. The items of this chapter do not apply to cables laid in rivers and water areas, under water, in mine shafts and similar conditions.' -> an explicit threshold of no less than 20 m.
- Shenzhen SJG 181.7-2024 clause 5.2.4: 'Cable laying in vertical shafts shall be measured in metres by the length of the cable passing through the vertical shaft (including the horizontal run after passing through).' -> in that dedicated volume one item already contains the horizontal run beyond the shaft, so it must not be split into two charges on the Beijing pattern.
5. Reserve (additional) length and the factor
DB11/T 2382-2024 clause 6.4.55:
The quantity of cable laying shall be the length per the design dimensions (including reserve and additional lengths). Where design and codes set no clear rule on reserve and additional lengths, Table 6.4.55 may be applied.
Table 6.4.55, eleven reserve (additional) lengths: (1) slack, waviness and crossings of laid cable, 2.5% (on the full cable length); (2) cable entering a building, 2 m; (3) cable rising (dropping) into a trench or onto brackets, 1.50 m; (4) substation incoming and outgoing lines, 1.50 m; (5) power cable terminations, 1.50 m; (6) cable joint boxes, 2 m each end; (7) boxes, cabinets, boards and panels, height + width (per the face dimensions); (8) cable to a motor, 0.50 m (from the motor terminal box); (9) station service transformer, 3 m (from floor level); (10) added length where cable passes around beams and columns, per actual measurement; (11) lift cable to cable-support fixing points, 0.50 m each.
Conclusion: reserve and additional lengths are part of the laying length, already inside the item quantity measured by length; they must not be listed as separate items or added again; shaft-section x 1.30 only adjusts that section's labour consumption, changes neither the reserve length values nor compensates the reserved part. Clauses 6.4.57 and 6.4.58 further confirm that rigid mineral-insulated cables (BTTZ and the like) and flexible mineral-insulated cables (YTTW, BTLY and the like) take the same reserve and additional lengths under clause 6.4.55.
6. Link to the BOQ code (GB/T 50856-2024 Annex D)
- Cable installation sits in Table D.9.1, code 030409 (the citation of 030408 does not match the 2024 code table - check the current code before itemising).
- D.17.12 on Table D.9.1: note 5, 'the cable laying method means direct burial, in cable trenches (tunnels), in ducts, indoors, in shafts and the like'; note 2, 'reserve and additional lengths for cable laying, see Table D.17.3-5'; note 1, the laying method of cable protection pipe means above ground or underground, and the protection pipe for cables entering buildings is itemised as a 'connection spool' under Annex D.12; note 3, cable trays and trunking are coded under the corresponding items of Annex D.12; note 4, cable branch boxes are coded under 'terminal boxes' in Annex D.5.
- The link: shaft laying versus indoor, tray, direct burial and so on are different laying methods - a substantive difference of item description. On the BOQ side the work is itemised under 030409 measured in m (or itemised by laying method and priced separately), while on the quota side the sections choose items or add the labour factor by location - a two-track fit of 'one BOQ code + multi-section quota pricing'.
Applicable boundaries
- The 1.30 factor touches labour consumption only; materials and plant stand. Where it stacks with the core / material factors of clause 6.4.56 (five-core power cable x1.15, single-core power cable x0.67, aluminium or aluminium-alloy cable x0.67, all compiled on three-core copper cable, including three-core-with-earth, as the basis), whether the factors multiply together must follow the local quota interpretation and compilation notes - they must not be stacked on one's own authority.
- Three systems - the Beijing general installation volumes (factor type), the Shenzhen SJG 181.7-2024 municipal power-duct volume (threshold of no less than 20 m), and the Beijing rail Annex G (dedicated items by cross-section) - differ in threshold and item setting; items and factors must not be applied across systems or mixed.
- Cable run vertically surface-mounted on walls or columns without a shaft enclosure does not constitute a 'vertical shaft' and has no basis for the factor (semantic inference).
- Pre-fabricated branch cables already absorb shaft laying (including suspension fitting installation) and take no further 1.30.
- Versions: the Beijing 2021 consumption standard has been superseded by DB11/T 2382-2024; the 2021 basis applies only where an existing contract stipulates its continued use.
- Support fabrication and installation and fire stopping within vertical shafts are not in the cable laying items and are handled under the corresponding items.
Further reading
- DB11/T 2382-2024 (Consumption Standard for Construction Works) Chapter 6 General Installation Works, 6.4 Electrical Equipment Installation Works, 'IX Cables', clauses 6.4.54 to 6.4.67, and Table 6.4.55 reserve and additional lengths for cable laying.
- DB11/T 2382-2024 Annex G Urban Rail Transit Works, Table G.5.45 Power cable laying ('power cables laid along vertical shafts' graded by cable cross-section, example item G5-8-70).
- Jing Jian Fa [2021] No. 201, 2021 Budget Consumption Standards, General Installation Volume 4, Electrical Equipment Installation Works (Part 1), Chapter 8 Cables: note 10 and measurement rule 1 (laying measured by length per the design dimensions, including reserve and additional lengths, per attached Table 2).
- GB/T 50856-2024 (Standard for Calculation of Quantities of General Installation Works) Annex D, Table D.9.1 Cable installation (code 030409), D.17.12 notes, Table D.17.3-5.
- SJG 181.7-2024 (Consumption Standard for Municipal Works, Volume 7: Power Ducts, Communication Ducts and Lighting) clause 5.1.2 (threshold of no less than 20 m), clause 5.2.4 (measured by shaft transit length, including the horizontal run beyond).
Keywords
- 竖直通道电缆敷设
- 电气竖井电缆
- 人工消耗量乘以系数1.30
- 预制分支电缆
- 电缆敷设预留长度
- 030409 电缆安装
- 分段套用子目
- 竖直通道高差20m