Whether threshold stones (door-sill stones) and tile border stones (edgings) list separately, and their measurement and pricing: different materials take separate items, the opening-merger rule, and the applicable item types
A threshold stone of material different from the adjoining tiles must list and price separately (different kinds and materials on one laid face execute their own quota items); tile finishes compute on the laid face area with door openings and voids merging in - once the threshold lists apart, its area never merges into the surrounding tile area. Ordinary building works take the stone floor items (m2); scattered floor areas of 0.5 m2 or less may list as sundry decoration (code 011108); finished metal trim strips take the trim-strip installation items (m); heritage / traditional stone work measures by volume (m3) (code 920204 sill-cushion, threshold and centre-dividing stones). Border stones merge when of the same material and size as the field, list apart when not.
Applicable Codes
- GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准 App. L Table L.2.1、Table L.8.1
- DB11/T 638-2016 房屋修缮工程工程量计算规范 App. A Table A.13.4、App. B Table B.2.4
- DB11/T 2382-2024 建设工程施工消耗量标准 第5.3.7条
- DB11 512-2017 建筑装饰工程石材应用技术规程 第5.3.3条
- 湖南2025房屋建筑与装饰工程消耗量标准(楼地面装饰工程计算规则)
- 陕西2024消耗量定额(楼地面装饰工程工程量计算规则)
Topic Positioning
How threshold stones (sill stones) and tile border stones (edgings) list and price in floor decoration bills and quotas: whether separate, how the quantities tie into the main field, which items apply when separate, and the relation between edging and thresholds. For building decoration measurement, pricing and review.
Core Conclusions
1. Whether to list apart. The general basis: different kinds and materials on one laid face execute their own items. DB11/T 638-2016 Annex A table A.13.4 note: "stone decorative mouldings of the same material as the wall need not list apart; of different material they may list separately under A.13.6 other-face tiling." Threshold stones are mostly natural stone (granite, marble), differing from the adjoining floor tiles - hence normally listed and priced separately; where the opening continues the field's stone of the same type and size, it merges into the field without separate listing.
2. Quantity tie-in: can openings still "merge"? Tile finishes compute on the laid face area, the openings of doors, voids, radiator pockets and niches merging into the corresponding quantities - GB/T 50854-2024 Annex L table L.2.1 (stone and tile finishes, code 011102); local quotas agree (Hunan 2024 (2025 edition in the source data) and Shaanxi 2024 floor rules alike). Hence: an opening continuing the same tile merges into the floor tiles, no separate listing; an opening carrying a threshold (different material) - the threshold measures on its laid area, the adjoining rooms' tiles run to the threshold edge, and the threshold's area never merges into the surrounding tiles (against double counting).
3. Which items when listed apart.
- General decoration (ordinary building works): stone floor items, unit m2 - e.g. Beijing 2024 A.11.2 "A-11-45 stone floor, piece area within 0.64 m2" and "A-11-46 within 1 m2".
- Very small scattered floors: floor areas of 0.5 m2 or less may list as sundry decoration, on laid area m2 - GB/T 50854-2024 Annex L table L.8.1 (sundry decoration items, code 011108); Beijing 2024 A.11.8 "A-11-124 stone, not patterned".
- Finished metal trim strips: floor divider / trim-strip installation items, unit m (Beijing 2024 A.11.2 "A-11-65 floor divider line, install trim strip").
- Heritage / traditional stone work: dedicated stone items by volume. DB11/T 2382-2024 clause 5.3.7 item 5: "sill-cushion, threshold and centre-dividing stones compute by volume at design-shown dimensions"; DB11/T 638-2016 Annex B table B.2.4 sets "sill-cushion, threshold and centre-dividing stones (code 920204)", noting that "sill-cushion with a stone sub-sill means the two made together; ordinary sill-cushion lists under the corresponding items". Some local heritage standards add "threshold stone" and "sill-cushion" items.
4. Border stones (edgings) and thresholds are two different details. DB11 512-2017 (technical regulation for stone in decoration) clause 5.3.3: "where floor stone finishes design an edging ... keep equal-width borders at wall corners, the block lines running point-to-corner ... where the edging meets a doorway and the design has no threshold stone, widen the edging to the sill or under the leaf" - with a threshold, the edging stops at it; without, the edging doubles as the threshold. Border stones of the same type and size as the field merge into the laid area, generally unlisted; of different material or size they list apart under the matching tile items.
Applicability Boundaries
- For floor decoration listing and pricing (building system); apply with the local quota chapter notes and rules - codes and bases differ by region.
- Listing apart turns on material / size difference from the field: same type and size merges; different material or size lists apart.
- Opening "merger" applies only where the opening carries the same tile; once a threshold is measured separately, its area never merges again - else double counting.
- Heritage stone-by-volume rules serve the heritage system only, not ordinary building decoration.
Further Reading
- GB/T 50854-2024, Annex L table L.2.1 (011102) and table L.8.1 (011108).
- DB11/T 638-2016, Annex A table A.13.4 note; Annex B table B.2.4 (920204).
- DB11/T 2382-2024, section 5.3 stone works (5.3.7, 5.3.8).
- DB11 512-2017, clause 5.3.3 (edging design requirements).
- Local quotas: Hunan 2024 (2025 edition in the source data) and Shaanxi 2024 floor rules; Beijing 2024 Annex A A.11.
Keywords
- 过门石
- 门槛石
- 收边石
- 圈边
- tile and stone finishes
- 单独套项
- 零星装饰项目
- 门洞开口并入