Selecting quota items for metal decorative mouldings (stainless steel strips, aluminium alloy grooved strips): two measurement conventions - finished moulding installation by linear metres (centre-line length) versus site-fabricated structural steel framing by weight in tonnes - with item numbers and chapter positions in each system, separation of main-material and installation costs, the boundary against drip grooves, drip noses and plaster mouldings, and adjustment coefficients for curved mouldings

Metal decorative mouldings split into two conventions - 'finished moulding installation' and 'site-fabricated framing/steel members': moulding items whose work content is only setting out, lining, cutting to size, drilling (timber plugs), gluing, installing and fixing are measured by linear metres - bill basis GB/T 50854-2024 table Q.2.1 item code 011502001 'finished decorative mouldings', unit m, computed at the centre-line length of the design dimensions, work content 'installation' only; the railway TB/T 10831-2024 volume 10 items FY-1933 to FY-1948, unit 10 m. Framing items whose work content includes straightening and correcting sections, lofting, cutting, welding and anti-corrosion oil (railway FY-1470 to FY-1472 wall/column aluminium/steel/stainless framing, FY-1528 ceiling structural steel joists) are measured by weight in t. Drip grooves, drip noses and decorative beads formed on site in cement mortar run plastering items (railway FY-1352 plaster mouldings, FY-1969/FY-1970 cement mortar decorative beads; Tianjin table M.2 item 2-140 external elevation decorative-band general plastering) and must not be double priced against finished metal mouldings.

Applicable Codes

  • GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准 App. Q Table Q.2.1(编码 011502)
  • TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程 Ch. 2 装饰装修工程 第六节 三、(四)金属装饰线 FY-1933~FY-1948;(八)其他装饰线 FY-1969~FY-1974;第二节 七、骨架 FY-1470~FY-1472;第三节 二、(六)型钢龙骨 FY-1528
  • 天津市装饰装修工程工程量清单计价指引(2025)表Q.2 装饰线条(6-60~63、6-64~66)、表M.2 零星抹灰(011202,2-140 外檐装饰线一般抹灰)
  • 北京市《预算消耗量标准》(京建发〔2021〕201号)第十五章 其他装饰工程 15-21~15-26;现行版 DB11/T 2382-2024
  • 陕西省 2024 新编消耗量定额(征求意见稿)第十五章 其他装饰工程 说明三(弧形/天棚系数)
  • JGJ/T 235-2011 建筑外墙防水工程技术规程 第 2.0.3 条 滴水线

Subject positioning

Which quota item applies to metal decorative mouldings on walls and ceilings (mirror stainless steel strips, aluminium alloy grooved/corner/wrap-angle strips, waist-band mouldings, picture rails, titanium-plated strips), whether measurement is by linear metres or by weight, how finished-moulding main material and installation costs are separated, how the boundary runs against plastering-type mouldings (drip lines, drip noses, plaster beads), and whether curved mouldings carry adjustment coefficients. For pricing and auditing of building decoration and railway housing works.

Core conclusions

1. Fix the convention first: not by material, but by 'finished installation' versus 'site-fabricated framing'

The criterion is the item's work content and materials column, not 'contains steel, charge by the tonne':

Criterion Linear metres (finished moulding installation) Weight t (structural steel framing/steel members)
Work content Setting out, lining, cutting to size, drilling/timber plugs, gluing, installing, fixing Straightening and correcting sections, lofting, cutting, welding, anti-corrosion oil, installing
Materials column Finished mouldings enter the materials column per m (e.g. mirror stainless steel decorative strip 1.0300 m/m, including wastage) Structural steel per t (including fabrication material and wastage), unit t
Unit of measurement m (bill convention), 10 m (railway quota), m (Beijing) t
Fabrication included No fabrication (finished product, installation only) Fabrication + installation

The railway quota draws this line most clearly: metal decorative moulding items have work content of only setting out, lining, cutting, gluing, installing and fixing; wall/column framing and ceiling structural-steel joist items cover straightening and correcting sections, lofting, cutting, welding, anti-corrosion oil and installing, plus cleaning the base, setting out, lining, drilling, fixing expansion bolts and hangers, cutting, welding and assembling, anti-rust paint, hanging and installing with temporary supports, reserving holes, adjusting and correcting - all in t.

2. Bill and item numbers by system (for card annotation)

  • National bill: GB/T 50854-2024 appendix Q, table Q.2.1 decorative mouldings (code 011502); item code 011502001 finished decorative mouldings, features being (1) base type, (2) moulding material type and specification, (3) protective/filling material type, unit m, quantity rule 'computed at the centre-line length of the design dimensions', work content 'installation'.
  • Tianjin (table Q.2 decorative mouldings, line-by-line identical to the national bill) combinable budget base-price items: 6-60 to 6-63 metal decorative strips, 6-64 to 6-66 mirror stainless steel decorative mouldings; the same table also lists 6-67 to 6-78 timber mouldings, 6-79 to 6-90 stone mouldings, 6-91 gypsum strip mouldings, 6-92 to 6-93 gypsum cornices, 6-94 to 6-95 gypsum relief, 6-96 mirror glass strips, 6-97 aluminium-plastic mouldings, 6-98 to 6-105 European-style mouldings; chapter: other decoration works, table Q.2.
  • Railway TB/T 10831-2024 volume 10 Housing Works, chapter 2 Decoration Works, section 6 Building Components Works, 3 Decorative mouldings, (4) metal mouldings: FY-1933 to FY-1948, unit 10 m - FY-1933 aluminium alloy strip; FY-1934/1935 mirror stainless steel strip (plate) width up to 30 / over 30; FY-1936/1937 mirror bronze strip (plate) up to 30 / over 30; FY-1938 to FY-1941 corner strips aluminium alloy/mirror stainless steel x up to 30/over 30; FY-1942 to FY-1945 wrap-angle strips aluminium alloy/mirror stainless steel x up to 30/over 30; FY-1946 metal picture rail; FY-1947 aluminium alloy waist-band moulding width over 60; FY-1948 stainless steel waist-band over 60.
  • Beijing Consumption Standard, chapter 15 Other Decoration Works: metal decorative strips 15-21 flat strips / 15-22 angle strips / 15-23 waist-band strips (unit m, work content 'setting out, lining, drilling, timber plugs, gluing, installing, fixing etc.', materials column: mirror stainless steel decorative strip, corner strip and waist-band strip all at 1.0300 m/m); timber mouldings 15-24 to 15-26.
  • Shaanxi 2024 new consumption quota (consultation draft), chapter 15 Other Decoration Works, 2 bead strips and decorative mouldings (convention reference only).

3. Quantity rules, original wording

  • National bill: finished decorative mouldings are 'computed at the centre-line length of the design dimensions', unit m.
  • Railway volume note 7(2) decorative mouldings: (1) flat strips, beads, angle strips and grooved strips are all measured by length of the design dimensions; (2) picture-frame and cabinet strips by length of the design dimensions; (3) European-style mouldings - external cornice boards and waist-band boards by length of the design dimensions, by specification; (4) other mouldings by length of the design dimensions. Decorative mouldings are thus uniformly 'by length', not by area or weight.
  • Scope of the railway moulding items: applicable to decorative mouldings designed on internal and external walls, columns, cabinets, ceilings and other positions.

4. Classify by material and form first, then choose the item

Mouldings are distinguished by material (railway volume note 3; Beijing note 3 to the same effect): (1) flat strip - both faces of the strip plane with no profile; (2) bead strip - back face plane, front face profiled; (3) angle strip - back face triangular, front face profiled internal/external corner moulding; (4) corner flower - right-angled triangular ornamental piece; (5) grooved strip - U-shaped strip for jointing; (6) European-style moulding - European-style decorative mouldings of all kinds. Beijing adds: mouldings are compiled by material and form and apply to internal and external walls, columns, cabinets, ceilings and positions where decorative mouldings are designed.

5. Separating main-material and fabrication/installation costs of finished mouldings

  1. Finished moulding items have work content of 'installation' only - the main material (finished moulding) enters the materials column per m with wastage (1.0300 m/m), the main-material unit price being replaced at compilation-period market prices; installation labour and auxiliary materials (adhesive, sealant, timber plugs, plywood bases, etc.) form the installation cost.
  2. The railway item base price splits into labour cost, material cost and machine cost; the moulding main material sits in material cost, installation labour in labour cost; metal decorative mouldings FY-1933 to FY-1948 all have zero machine cost - no machine cost may be added when pricing.
  3. Where the moulding itself is a structural steel member cut and welded on site (including anti-corrosive coating) - run the framing/steel member item by t (fabrication + installation included), and do not additionally apply the finished moulding item's installation cost.
  4. The Shaanxi notes state that bead strips and decorative mouldings are all considered as finished installation - site-fabricated ones need separate fabrication or a swapped item.

6. Boundary against plastering-type mouldings: drip lines, drip noses, grooved beads

Under JGJ/T 235-2011 clause 2.0.3, a drip line is a construction at the outer edge of parts projecting from or recessed into the external wall face that blocks water ingress in the horizontal direction; drip lines stop water running back onto the wall face; they are required at window sills and heads, canopies, balconies, parapet copings and projecting waist bands; the forms are the drip groove and the drip nose, usually formed in cement mortar but also as metal (stainless steel, aluminium alloy) prefabricated pieces. The boundary therefore follows the method (process), not the position or name:

  • Drip grooves, drip noses and decorative beads (round or straight) formed on site in cement mortar - run plastering items: railway FY-1352 general plastering of walls/columns, plaster mouldings (unit 10 m, work content: cleaning the base, patching holes, wetting, carting, sweeping, levelling by layered plastering, trowelling the finish), FY-1969 cement mortar decorative beads, round / FY-1970 straight (work content: cleaning and patching the base, mixing mortar, lining out, plastering, finishing and trowelling, unit 10 m); Tianjin table M.2 sundry plastering (011202) combinable item 2-140 external elevation decorative-band general plastering. Sundry plastering is billed by developed area in m2, while decorative mouldings are billed by centre-line length - two different conventions.
  • Prefabricated metal drip strips, nose strips and bead strips installed as finished pieces - run finished metal decorative moulding items (011502001 / Tianjin 6-60 to 6-63, 6-64 to 6-66 / railway FY-1933 to FY-1948 / Beijing 15-21 to 15-26) measured by centre-line length.
  • Only one of the two per position: the plastering item already contains the labour and materials to form the bead, the finished moulding item already contains installation - no double pricing; painting or coating over the plaster finish follows the painting chapter rules.
  • The same railway chapter also has non-metal finished moulding items FY-1971 titanium-plated mouldings (up to 30 / over 30), FY-1973 mirror glass decorative strips, FY-1974 imitation magnesium-aluminium strip mouldings, unit 10 m - metal-look finished mouldings do not all fall under the metal decorative mouldings subsection; match by material.

7. Adjustment coefficients for curved mouldings

The Shaanxi 2024 consumption quota (consultation draft) chapter 15 note 3 gives explicit rules (items compiled on the base of finished installation and decorative mouldings installed straight on walls):

  • Curved decorative mouldings on walls/columns: labour x1.2, materials x1.1;
  • Straight decorative mouldings on ceilings: labour x1.34;
  • Curved decorative mouldings on ceilings: labour x1.6, materials x1.1. So going onto the ceiling is itself a surcharge convention (labour x1.34), and curvature stacks on top; ceiling plus curved combines to labour x1.6, materials x1.1. No equivalent express coefficient clauses were seen in the other systems (Tianjin, Beijing, railway); each quota or consumption standard's chapter notes must be checked - out-of-region coefficients must not be applied across systems.

Applicability boundaries

  • Moulding items only cover 'finished moulding installation' or 'structural steel framing fabrication and installation' per se; they exclude large-area base levelling and plastering and framing installation (apply the wall/column and ceiling chapters); Tianjin table Q.2 lists only combinable base-price items - framing items are not in the table and must be combined or supplemented per the design.
  • The quota units (10 m or 100 m) of Tianjin 6-60 to 6-63 and 6-64 to 6-66 must be verified against the Tianjin Decoration Works Budget Base Price volume text; do not multiply the bill-unit m price directly.
  • Railway metal moulding items are in 10 m against bill m - convert by 0.1; items are already split by material, width (up to 30 / over 30) and form (strip/corner/wrap-angle/waist-band/picture rail) - apply without conversion or merging.
  • The Shaanxi 2024 quota is a consultation draft: its curved/ceiling coefficients and item numbers are convention references only and must not be used directly as a settlement basis.
  • Beijing's 2021 Consumption Standard (Jing Jian Fa [2021] No. 201) item numbers are the 15-x system; Beijing's consumption standard has since changed generation (DB11/T 2382-2024) - verify item numbers, units and work content against the current edition before pricing.
  • Item units, contents and base prices belong to each system; item numbers and coefficients must not be mixed across systems (Tianjin/Beijing/railway/Shaanxi).
  • The curved and ceiling coefficients presuppose 'finished moulding installation'; where the moulding is formed by site plastering, handle under the plastering item's thickness increase/decrease and developed-area rules, not these coefficients.

Further reading

  • TB/T 10831-2024 Railway Engineering Budget Quota, Volume 10 Housing Works: volume notes 3 (material classes of mouldings) and 7(2) (quantity rules); chapter 2 section 6, 3 decorative mouldings, (4) metal mouldings FY-1933 to FY-1948, (8) other mouldings FY-1969 to FY-1974; section 2, 1(1) FY-1352 plaster mouldings; section 2, 7(2) FY-1470 to FY-1472; section 3, 2(6) FY-1528.
  • GB/T 50854-2024 Measurement Standard for Building and Decoration Works, appendix Q, table Q.2.1 decorative mouldings (code 011502).
  • Tianjin Decoration Works Bill Pricing Guide (2025): table Q.2 decorative mouldings (011502), table M.2 sundry plastering (011202); verify units and consumption against the 2020 Tianjin Decoration Works Budget Base Price.
  • Beijing Consumption Standard (Jing Jian Fa [2021] No. 201), Housing Building and Decoration Works (volume 2), chapter 15 notes 3 and 4 and items 15-21 to 15-26; check the current edition per DB11/T 2382-2024.
  • Shaanxi 2024 new consumption quota (consultation draft), chapter 15 notes 2 and 3 (bead strips and mouldings as finished installation; curved/ceiling coefficients).
  • JGJ/T 235-2011 Technical Specification for Waterproofing of Building External Walls, clause 2.0.3 (drip line terminology and construction).

Keywords

  • 金属装饰线条
  • 成品装饰线条
  • 011502
  • 延长米
  • 中心线长度
  • 型钢骨架按重量
  • 弧形线条系数
  • 滴水线鹰嘴压槽
  • FY-1933