Selecting quota items for drip lines and drip grooves: the two routes of mortar beads / pressed grooves versus proprietary drip strips, the application and unit of moulded-render (decorative-line) items (extended metres or area), and avoiding double pricing against the element's finish plaster
No edition of the building and decoration consumption (budget) quotas carries an item named 'drip line / drip groove': for mortar-bead or pressed-groove drips, where the local quota has a 'moulded render (decorative line)' item, apply that item by extended metres (10m / 100m); without it, merge into the element's plaster by area with no extra charge. Proprietary metal / PVC drip strips take the proprietary decorative-line items with main-material conversion, by the metre. Where window-sill lines, string courses, eaves projections, parapet cappings, sun-shade edges etc. have already been priced as moulded render, the drip formation is deemed included - no further extended-metre drip line may be added.
Applicable Codes
- TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程(册说明第十一条、Ch. 2第二节墙柱面工程说明,子目 FY-1346~FY-1358)
- GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准 App. M Table M.1.1(011201)、Table M.2.1(011202)
- GB 50210-2018 建筑装饰装修工程质量验收标准 第4.2.9条
- JGJ/T 220-2010 抹灰砂浆技术规程 第6.2.6条
- DB11/T 2382-2024 建设工程施工消耗量标准 第4.13节
- 湖南2025版 房屋建筑与装饰工程消耗量标准 第十二章 墙柱面
- 陕西2024 新编消耗量定额 第十二章 墙、柱面装饰与隔断、幕墙工程
- 江苏2026版 江苏省建筑与装饰工程消耗量 墙柱面抹灰
Positioning
Fixing 'which quota item a drip line takes, whether it is inside the plaster item, and whether it measures by extended metres or area' - for drip details at eaves, window sills (heads), canopies, balconies, cappings, string courses and projecting decorative bands - across the railway and local building decoration consumption quotas, the measurement standards and the plastering acceptance rules.
Core conclusions
1. No item named 'drip line / drip groove' exists. Checked one by one - railway TB/T 10831-2024 Volume 10, Beijing DB11/T 2382-2024, Hunan 2025, Shaanxi 2024 draft, Jiangsu 2026 - none sets such an item. What to apply depends on the drip detail and on whether a 'moulded render' item exists locally.
2. Two routes by detail:
- Route 1: mortar-formed drip beads or pressed grooves - where a moulded-render item exists, apply it by extended metres; otherwise merge into the element's plaster by area, no extra charge.
- Route 2: proprietary drip strips (PVC / aluminium / stainless) - the proprietary decorative-line items (groove or flat line classes), main material converted, by the metre.
3. Two accounts against the element's finish - guard against duplication. Sill lines, string courses, eaves projections, cappings, sun-shade edges and door / window architraves are themselves the objects of moulded render (listed expressly in every edition's notes). Once priced on the line items, the drip forming is deemed included in the item's trades - never add another extended-metre drip line: the commonest double-pricing error in practice.
4. Local moulded-render evidence (deciding 'metres or not'):
- Railway TB/T 10831-2024 Volume 10, volume note 11, IV.1: 'the decorative-line rendering item of ordinary plastering applies to architraves, eaves projections, string courses, cappings, sun-shade edges, notice-board frames and vertical / horizontal lines projecting from walls with developed width up to 300; width over 300 up to 400 x 1.33; over 400 up to 500 x 1.67.' Items FY-1352 'decorative-line rendering' per 10m; FY-1355 'sundry plastering' per 10m2.
- Hunan 2025 chapter 12: 'plaster lines apply to architraves, eaves, string courses, cappings, sun-shades, stair edges, notice-board frames, and vertical / horizontal lines projecting up to 500mm single-face width; beyond 500mm follow the floor, wall / column and ceiling plaster items'; rules: 'lines by extended metres banded by single-face width', 'sundry items by developed area'.
- Shaanxi 2024 note V.4: the same scope with the 500mm cap; 'line plastering by length; sundry items by developed area'.
- Jiangsu 2026: no by-length basis - eaves fillets, gutters, string courses, handrails, isolated architraves, sill lines and cappings 'all compute on structural developed area', i.e. always m2 inside the plaster.
- Beijing DB11/T 2382-2024: no line-by-length clause; 4.13.23 'sundry plastering computes by area'; 4.13.13 canopy and eaves upstand up to 500mm takes sundry decoration, over 500mm external-wall decoration. Only proprietary decorative lines (cornice classes) go by the metre.
5. BOQ basis: GB/T 50854-2024 Appendix M - wall and column plastering per Table M.1.1 (011201), sundry plastering per Table M.2.1 (011202).
6. Construction and acceptance basis (the premise of any detail): JGJ/T 220-2010 clause 6.2.6 - plastering of eaves, sills, window heads, balconies, canopies, cappings, string courses and decorative bands shall have drainage falls with drip lines (grooves) beneath and no reverse falls; window openings' plaster enters the frame joint and is packed tight; drip lines are formed face first, then top, then soffit, with the fall direction right; balconies, sills and cappings use M20+ cement mortar in layers. GB 50210-2018 clause 4.2.9: 'positions needing drainage shall carry drip lines (grooves), neat and straight, the drip line high inside and low outside; groove width and depth per design and never under 10mm.'
Applicable boundaries
- This card is a cross-regional method; factors, item numbers and units follow the current local chapter / volume notes and rules - no cross-regional factor borrowing (railway's 1.15/1.33/1.67 differ from local factors; Beijing round-column plaster labour x 1.15 material x 1.03; Shaanxi arc / zigzag labour and plant x 1.15 material x 1.05; Hunan arc / zigzag labour x 1.25).
- Extended metres apply only where the local quota expressly sets moulded render by length; elsewhere always by area inside the plaster - applying 'extended metres' there is a wrong item.
- Where the element is already priced on a line item, no separate drip project; where the drip sits on the edge of a large face (ceiling, floor) outside the line item's listed parts, it follows that finish - no separate project either.
- Proprietary strip main material enters at compilation-period market or published prices; the item carries consumption only.
- Editions change (TB/T 10831-2024 replaced the old building volume) - check the current edition.
Further reading
- Railway TB/T 10831-2024 Volume 10, volume note 11 rules, chapter 2 section 2 notes (1)-(9), items FY-1346~FY-1358, esp. FY-1352 / FY-1355.
- Hunan 2025 chapter 12 notes 1-2 and rules I; Shaanxi 2024 chapter 12 note V.4 and rule I.6; Jiangsu 2026 wall / column plaster area notes; Beijing DB11/T 2382-2024 clauses 4.13.13 / 4.13.21 / 4.13.23 / 4.13.24.
- JGJ/T 220-2010 clause 6.2.6; GB 50210-2018 clause 4.2.9; GB/T 50854-2024 Tables M.1.1 (011201), M.2.1 (011202).