Deduction and unfolded-merger rules for the three layers of basement base slabs (waterproofing / screed / fine-aggregate concrete protection): waterproofing under Appendix J (waterproofing chapter), screeds and protection under GB/T 50854-2024 clause J.6.11 re-listed in Appendix L floors, and unfolded merger of pile-cap sides and tops belonging to the waterproofing only
Three layers, three sources, three bases: the waterproof layer (Appendix J / waterproofing quota chapter) does not deduct the plan areas of pile caps and like projections above the slab, merging their sides and tops by unfolded area into the plane quantity, with sump and lift pits likewise merged unfolded; the screed and the fine-aggregate protection re-list per GB/T 50854-2024 clause J.6.11 under Appendix L floor items - screeds face two local bases ('no deduction clause, by shown dimensions' versus 'deduct structures and equipment foundations projecting from the floor'), while the protection has only 'by design dimensions as area' and no side or top merger clause - so the protection cannot copy the waterproofing's cap-side unfolded quantity and only follows it in physical laying extent.
Applicable Codes
- GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准 App. J Table J.5.1(基础防水及止水带 010905)、第J.6.11条
- GB/T 50854-2024 App. L Table L.1.1(整体面层及找平层 011101)
- GB/T 50854-2024 App. E Table E.1.1(基础及楼地面垫层 010501)
- DB11/T 2382-2024 建设工程施工消耗量标准 第4.10节(4.10.9、4.10.16、4.10.20、4.10.24~4.10.28)、第4.12节(4.12.1、4.12.9~4.12.11)
- 京建发〔2021〕201号 2021预算消耗量标准 房屋建筑与装饰工程 第九章 屋面及防水工程、第十一章 楼地面装饰工程
- 江苏省2026版 江苏省建筑与装饰工程消耗量 防水工程计算规则、楼地面计算规则
- 湖南2025版 房屋建筑与装饰工程消耗量标准 防水工程计算规则、楼地面计算规则
- 陕西省新编消耗量定额(2024征求意见稿)防水工程计算规则、楼地面计算规则
- SJG 111.2-2022 城市地下综合管廊工程消耗量标准(Vol. 2 管廊建筑与装饰工程)第7.2.1条
Positioning
The basement slab usually lists three layers side by side: waterproofing (membrane or coating), screed, fine-aggregate protection. They sit in different appendices at BOQ level and different chapters at quota level, with different deduction and unfolded-merger rules. This card gives the rule sources, the pile-cap and pit measurement, the projection / slope test, and the screed-versus-bedding anti-duplication boundary.
Core conclusions
1. Three layers, three sources - the root of every difference
GB/T 50854-2024 clause J.6.11 (Appendix J, roofing and waterproofing): wall waterproofing screeds list under Appendix M's'vertical mortar screed'; floor and foundation waterproofing screeds and the fine-aggregate protection list under Appendix L floor items ('fine-aggregate concrete floors'). So: waterproofing runs Appendix J; screeds and protection re-list under Appendix L floors at BOQ level. 'The protection follows the waterproofing' holds only in physical laying extent (same plan projection), never in measurement - the waterproofing's side-and-top merger clause does not transfer. Codes: Appendix J Table J.5.1 'foundation waterproofing and water-stops (010905)'; Appendix L Table L.1.1 'monolithic finishes and screeds (011101)'; bedding Appendix E Table E.1.1 (010501).
2. Deduction bases compared (pile caps projecting above the slab)
| Layer | Rule (source) | Cap plan projection | Sump / lift pits |
|---|---|---|---|
| Waterproofing | Beijing DB11/T 2382-2024 clause 4.10.26: 'foundation waterproofing by design area; upturned beams merge by unfolded area'; Jiangsu 2026 rule II.4: 'foundation waterproof / damp-proof by design area, pile heads and holes up to 0.3m2 not deducted; other foundations, lift pits and sumps connected to rafts and waterproof slabs merge by unfolded area, all counted into the plane quantity' | Not deducted (laid full over the slab); cap / upturned-beam sides and tops merge by unfolded area | Merged unfolded, expressly 'into the plane quantity' - plane items, not wall items |
| Screed | Beijing 4.12.9: 'by design area' (no deduction clause); Jiangsu / Hunan / Shaanxi: 'deduct structures, equipment foundations and trenches projecting from the floor; not dwarf walls, piers, flues or holes up to 0.3m2; door openings not added' | Two local bases: Beijing school - no clause, neither deduct nor add, one pass on the slab plan; Jiangsu-Hunan-Shaanxi school - caps are 'projecting structures', their footprint deducted, the cap top screeded separately if designed | No merger clause - pit sides only where the drawings show |
| Protection | Beijing 4.10.27 / Hunan note 7: 'by design area'; listing per J.6.11 (Appendix L fine-aggregate floors) | Shown area only, no side or top merger clause - never copy the waterproofing's cap-side quantity; upstands counted only where drawn | Shown area only, pit sides only where drawn |
3. Sumps and lift pits in sum
- Waterproofing: pit walls and bases merge unfolded into the plane waterproofing (Jiangsu expressly 'into the plane quantity'); Beijing's 4.10.9 puts additional layers at corners, post-cast strips, sumps and lift pits inside consumption, never re-measured.
- Screed and protection: no merger clauses - shown area; pit sides only where drawn.
- Upstand split (waterproofing): Beijing 4.10.16 - upstands within 300mm run on floor items, above 300mm on wall items; 4.10.25 - upstands within 300mm merge into the floor quantity.
4. Projection or slope
- Roof waterproofing (Beijing 4.10.20): sloped roofs by slope area, flat (including falls) by horizontal projection; parapet, movement-joint and roof-light upstands merge; gutters, eaves and canopies merge by unfolded area; chimneys, vents and the like neither deducted nor added.
- Basement slabs (Hunan): 'plan projection area of the bedding x slope factor, deducting post-cast strips and drainage channels; perimeter upstands merge at width (slab thickness + 250mm) x the inner length of the permanent protection wall' - projection x slope factor, not the actual laid area; Beijing and Jiangsu say only 'by design area', falls already inside the drawn dimensions.
- Test: with an express 'slope factor / slope area' clause, convert; with only 'by design area', take the drawn area (flat roofs by projection - falls add nothing).
5. Screed versus bedding under caps - no duplication
- Different appendices and units: bedding Appendix E (010501) in m3; screed Appendix L (011101) in m2 - neither offsets nor replaces the other.
- Beijing 4.12.1: floor, stair, ramp and apron items exclude bedding (earth and concrete bedding under their own clauses); Jiangsu: bedding on net area x thickness in m3, deducting projecting structures, equipment foundations, piping and trenches.
- The anti-duplication line is trade attribution: the same element, same pass is never both bedding and screed; where caps already carry foundation bedding, no equal-thickness screed repeats; a cap-top screed prices separately by screed rules.
6. Frequent errors
- Checking the protection with the waterproofing's cap-side unfolded quantity - wrong, no merger clause.
- Copying the waterproofing's 'no deduction' onto screeds - wrong: Beijing has no clause (neither deduct nor add); Jiangsu / Hunan / Shaanxi deduct projecting structures.
- Listing pit-wall unfolded areas as wall waterproofing - Jiangsu expressly counts them into the plane quantity, plane items.
- Measuring additional layers - Beijing 4.10.9 already holds them in consumption (Shaanxi's draft prices membrane additional layers by laid area - a local difference; follow the standard in force).
Applicable boundaries
- This card compares the BOQ (GB/T 50854-2024) with local quota rules - two tracks, never interchangeable.
- Whether caps are 'projecting structures' follows the local wording: Jiangsu / Hunan / Shaanxi deduct their floor footprint; Beijing, having no clause, takes one pass by drawn area.
- 'Protection and screed follow waterproofing' holds only in drawn laying extent - never in measurement or merger.
- The 300mm upstand split is an item-attribution test, not a deduction rule.
- Chapter numbers follow the edition in force (Beijing 4.10 / 4.12; Jing Jian Fa [2021] No. 201 chapters 9 and 11).
Further reading
GB/T 50854-2024 Appendices J (J.5.1, 010905; clause J.6.11), L (L.1.1, 011101), E (E.1.1, 010501); Beijing DB11/T 2382-2024 clauses 4.10.9 / 4.10.16 / 4.10.20 / 4.10.24~28 and 4.12.1 / 4.12.9~11; Jing Jian Fa [2021] No. 201 chapters 9 and 11; Jiangsu 2026 waterproofing rules 2, 4, 5 and flooring rules 1-3; Hunan 2025 waterproofing notes 4-7 and flooring rules 1-2; Shaanxi draft waterproofing rules 3-7 and flooring rules 1-3; SJG 111.2-2022 clause 7.2.1 as a third-party parallel (pile-head waterproofing outward 300mm, trenches unfolded, all into the plane quantity).