When bill and quota measurement units mismatch (m2 bill against m3 quota): no unit conversion - bill and quota quantities run on separate tracks, bridged by the all-in rate P = sum of item prices over Q
Bill units are locked - never rewrite a bill to m3 because the quota runs m3: GB/T 50500-2024 clauses 3.1.4 and 4.1.7 require units per the national and sector measurement standards, and GB 50861-2013 clause 4.2.6 (mandatory) "bill units shall follow the units in the appendix". The right handling is neither unit conversion nor a conversion factor on the quota rate, but: bill quantities on bill rules (keeping the appendix m2 unit), quota quantities converted on quota rules (m3), independent; then bridged per DBJ/T 15-145-2018 clause 6.1.4 - the all-in rate of a bill item equals the sum of the quota item prices under it divided by the bill item quantity.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准 第3.1.3、3.1.4、3.1.6、3.2.1、4.1.7条
- GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准 第4.2.5条及App. LTable L.7.1
- GB 50859-2013 矿山工程工程量计算规范 第4.2.6条
- GB 50860-2013 构筑物工程工程量计算规范 第3.0.3条
- GB 50861-2013 城市轨道交通工程工程量计算规范 第3.0.3、4.2.6条
- DBJ/T 15-145-2018 建设工程政府投资项目造价数据标准 第6.1.4、6.1.6条
- GB/T 51095-2015 建设工程造价咨询规范 第5.3.9条及App. C
- DB42/T 823-2021 建设工程造价咨询质量控制规范 第6.3.9条
- SJG 111.2-2022 城市地下综合管廊工程消耗量标准(Vol. 2 管廊建筑与装饰工程)第5.2.1条
Topic Positioning
How to handle bill-versus-quota unit mismatch (typically m2 bills against m3 quotas - steps, floor beds) when pricing bills through quotas, and how the all-in rate computes. The core: "quantities and prices split, two quantity tracks, bridged by the all-in rate" - never unit conversion.
Core Conclusions
1. Bill units are locked - never changed for the quota's
- GB/T 50500-2024 clause 3.1.4: bills compile per the item classes, units and rules of the national and sector measurement standards, from the drawings and technical standards, on the principles of clear items, clear boundaries, easy pricing and payment.
- Clause 4.1.7: unit-price or lump-sum alike, the codes, names, descriptions, units and work content of divisional BOQ items follow the national and sector standards and supplementary rules; preliminaries items likewise.
- GB 50861-2013 (rail transit measurement code) clause 4.2.6 (mandatory): "bill units shall follow the units in the appendix." The current building text GB/T 50854-2024 clause 4.2.5 the same: "bill units shall follow the units of annexes A to Q." -> A quota in m3 never justifies rewriting the bill unit to m3.
2. Where an appendix offers two or more units, pick one and stay consistent
- GB 50860-2013 clause 3.0.3: where the appendix has two or more units, fix one per the project; keep it consistent within one project (GB 50861-2013 clause 3.0.3 alike).
- GB 50859-2013 clause 4.2.6 (mandatory): units per the appendix; where two or more, fix one - and the same item keeps one unit across all unit works of one project (or section / contract section).
3. Two quantity tracks, bridged by the all-in rate
- The rate formula (a local data standard locks it) - DBJ/T 15-145-2018 (cost data standard for government-invested projects) clause 6.1.4: the all-in rate of a bill item computes P = sum of Tn / Q P the bill-item all-in rate, rounded to 2 decimals; Tn the price of each quota item under the bill item, at full precision (unrounded); Q the bill-item quantity, rounded to 3 decimals. The note: for items priced through quotas, the rate is the quota prices summed over the bill quantity - in substance "the quota price borne by one bill unit".
- The quota price - clause 6.1.6: Tn = Pn x Qn; Tn the quota price, full precision under bill pricing (rounded to 2 under quota pricing); Pn the quota rate (overheads and profit included), rounded to 2; Qn the quota quantity, rounded to 6 under bill pricing (3 under quota pricing). The clause notes the two modes differ in decimal handling - for consistent data exchange between software and for the two output regimes; and the day / material / machine-shift unit prices in the two modes differ - bill pricing takes compiling-period dynamic prices, quota pricing the quota base-period prices.
- Bill price build-up - GB/T 50500-2024 clause 3.2.1: unit-priced items price as quantity x all-in rate; lump-priced items price per item; divisional items preferably unit-priced, preliminaries preferably lump-priced.
- The rate's content - clause 3.1.6: rates and prices are tax-exclusive full prices of labour, materials, plant, overheads and profit, with the agreed or reasonable risk fees and indispensable auxiliary work; VAT sits in its own line - provisional prices for specialist works already carry it.
- Pricing and deliverables - GB/T 51095-2015 clause 5.3.9: item rates may derive from budget quotas and their companion on-cost quotas - labour, materials and plant from the quota's factor contents and the compiling-period market; overheads, profit, levies and tax from the companion on-cost quotas and the market; budgets carry all-in rate analysis sheets. (DB42/T 823-2021 clause 6.3.9 identical, noting it "fixes the rate build-up principle".)
4. Three operating steps
- Bill quantities: net quantities on the measurement standard's rules, unit locked to the appendix (steps on horizontal projection in m2) - untouched.
- Quota quantities: converted per the quota's own rules (monolithic finishes and beds by volume m3, from design area x design or converted thickness) - an independent second track; converted thickness needs drawing or quota-rule basis, never a loose factor.
- All-in rate: P = sum of quota item prices / bill quantity Q - the quota costs spread over one bill unit, the build-up shown in the rate analysis sheet with quantity and price sources.
Applicability Boundaries
- For bill pricing through budget (or consumption) quotas; not for items priced at market lump sums without quotas.
- Mismatch digests only at the rate-analysis level - never touch the item descriptions, codes or units; never rewrite quota units as bill units, never multiply quota rates by a blanket "conversion factor".
- What converts is the QUANTITY, on drawings plus quota rules - a different thing from consumption conversion inside an item (grades, mixes, thickness steps).
- Where an appendix offers two or more units, fix one per the code and stay consistent across the project (or section).
- DBJ/T 15-145-2018's decimals and precision are a local data standard - check the local counterpart before cross-province use; the factor-price bases of the two modes (compiling-period dynamic versus quota base-period) never mix.
- Route and arithmetic only; converted thicknesses and item routing follow the drawings and the local current quota.
Further Reading
- Units and bill basis: GB/T 50500-2024 clauses 3.1.3, 3.1.4, 3.1.6, 3.2.1, 4.1.7.
- Mandatory unit rules and multi-unit selection: GB 50861-2013 clauses 3.0.3, 4.2.6; GB 50860-2013 clause 3.0.3; GB 50859-2013 clause 4.2.6; GB/T 50854-2024 clause 4.2.5.
- Rate and price formulae, decimals: DBJ/T 15-145-2018 clauses 6.1.4, 6.1.6 (chapter 6).
- Build-up principle and analysis sheets: GB/T 51095-2015 clause 5.3.9 and annex C; DB42/T 823-2021 clause 6.3.9.
- Item-rule examples: steps per GB/T 50854-2024 Annex L table L.7.1 (011107); tunnel floors (beds, screeds and monolithic finishes on design-shown area; stairs and steps on horizontal projection) per SJG 111.2-2022 clause 5.2.1.
Keywords
- 清单计量单位
- 定额计量单位
- 单位不一致换算
- 清单量与定额量双轨
- 综合单价计算
- 定额子目合价
- 综合单价分析表
- 组价口径