Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-01

Whether lift-shaft walls need plastering: no code mandates it - the tests are "non-combustible + sturdy + dust-free", shaft clear-size tolerance, and the guide-bracket substrate - three hard constraints

No current code mandates plastering lift-shaft walls: GB 50310-2002 clause 4.2.5 item 2 requires only that the shaft walls "have the strength needed to mount lift parts, be built of non-combustible materials and not readily generate dust"; GB 50157-2013 clause 25.2.4 words it as built of "non-combustible, sturdy, dust-free materials". The design decides; unstated, deliver as struck. Cast-in-place concrete (shear wall) shafts usually go unplastered; masonry shafts follow the dust-free practice of thin cement-mortar sealing with the guide brackets anchored into concrete ring beams / constructional columns; the shaft wall below the landing sill must be smooth, hard metal sheeting - never plaster.

Applicable Codes

  • GB 50310-2002《电梯工程施工质量验收规范》第4.2.5条
  • GB 50310-2002《电梯工程施工质量验收规范》第4.4.3条
  • DB11/T 1832.20-2022《建筑工程施工工艺规程 第20部分:电梯系统工程》第4.3.8条
  • DB11/T 1832.20-2022 第5.3.1条、第5.4.3条、第8.4.6条、第10.3.6条
  • GB 50157-2013《地铁设计规范》第25.2.4条

Topic Positioning

The code basis and decision path for whether lift-shaft walls need plastering and how their finish is detailed. Finding: no code carries a mandatory "shaft walls must be plastered" clause - the decision returns to three hard constraints: material and surface (non-combustible, sturdy, dust-free), shaft clear-size tolerance, and whether the walls can anchor the guide brackets reliably.

Core Conclusions

1. No mandatory plastering - the codes bind the RESULT, not the process

  • GB 50310-2002 Code for Acceptance of Elevator Engineering Quality, clause 4.2.5 item 2: fully or partly enclosed shafts - their enclosure, walls, pit floor and roof shall have the strength needed to mount lift parts, be built of non-combustible materials and not readily generate dust.
  • GB 50157-2013 Code for Design of Metro, clause 25.2.4: shaft walls, floor and roof shall be built of non-combustible, sturdy, dust-free materials.
  • DB11/T 1832.20-2022 (construction technology code, Part 20: lift systems) clause 4.3.8 item 2 and 10.3.6 to the same effect (shafts fully enclosed by unperforated walls, floors and roofs; interiors clean, no seepage or leakage; works lighting at 36 V or below, each shaft separately fed with its own switch). "Not readily generate dust" binds the DELIVERED state (no dusting); plastering is one means, never the prescribed process.

2. Shaft clear-size tolerance (plaster eats clear space - never level a shaft with it) GB 50310-2002 clause 4.2.5 item 1: shaft size means the minimum clear dimensions of the shaft section projected along the travel, to match the construction layout drawings, tolerances: travel 30 m or less, 0 to +25 mm; over 30 m to 60 m, 0 to +35 mm; over 60 m to 90 m, 0 to +50 mm; over 90 m, per the layout drawings. DB11/T 1832.20-2022 clause 4.3.8 item 1 the same (worded 0 mm to +25 mm etc.). On completion the width, depth and plumb of the shaft walls shall meet the works requirements (DB11/T 1832.20-2022 clause 5.3.1).

3. Guide-bracket substrate - load bears on concrete, never on plaster

  • GB 50310-2002 clause 4.4.3: bracket fixing on shaft walls shall be reliable; inserts per the layout drawings; anchor bolts (expansion bolts etc.) shall fix into the CONCRETE members of the shaft wall, their connection strength and vibration capacity meeting the lift design, and the concrete compressive strength meeting the layout drawings.
  • DB11/T 1832.20-2022 clause 5.4.3: without reserved inserts, expansion bolts fix brackets directly to concrete shaft walls - NEVER to brickwork; expansion bolts not under M16, embedded not under 120 mm (absent maker's requirements); walls under 150 mm without inserts preferably avoid expansion bolts - drill through and fix a steel plate of 16 mm or more on pins over 16 mm; hollow and foam brick walls admit NO fixings. Bracket level tolerance 15/1000 or less.
  • DB11/T 1832.20-2022 clause 10.3.6 item 4: in non-shear-wall shafts, the ring-beam positions and heights carrying the brackets shall follow the design. That is: masonry shafts need added concrete ring beams / constructional columns / inserts to root the brackets - plaster contributes nothing to load.

4. Details plaster may never replace The shaft wall below the landing sill (DB11/T 1832.20-2022 clause 8.4.6): it shall form a vertical face tied directly to the sill, height not under half the unlocking zone plus 50 mm, width not under the clear entrance plus 25 mm each side; the surface continuous, of smooth hard metal sheeting or the like, taking a 300 N static force spread over a 50 mm2 circle or square at any point, permanent set not over 1 mm and elastic deflection not over 15 mm; projections not over 5 mm, those over 2 mm chamfered at 75 degrees or more to the horizontal; the wall ties to the next landing head, or extends down a hard smooth ramp (60 degrees or more, horizontal depth not under 20 mm).

5. The decision path (three steps)

  1. Check the design: do the finish schedules or lift layout drawings list "shaft wall plaster"? Unstated - deliver as struck (a shaft is no "occupied room"; ordinary plaster and full-fit-out acceptance exclude shafts).
  2. Check the substrate: cast-in-place concrete (shear wall) shafts usually go unplastered - just strip laitance, grind nibs and seal tie-bolt holes and honeycombing; masonry infill / masonry shafts take thin cement-mortar sealing against dusting, with concrete ring beams / constructional columns added to root the brackets.
  3. Check installation details: below-sill shaft walls follow the metal-sheet detail, never plaster; shared shafts follow the separator rules (GB 50310-2002 clause 4.2.5 item 6: separators start no higher than 0.3 m above the pit floor, rise at least 2.5 m above the lowest landing floor, gaps to the walls not over 150 mm; where car-top edges run under 0.5 m from the moving parts of adjacent lifts, the separator runs the full height, not narrower than the protected parts plus 0.1 m a side).

Applicability Boundaries

  • This card decides the DETAIL, not the quota application or pricing of shaft plaster.
  • Shaft-size tolerances benchmark the MINIMUM clear size against the layout drawings; plaster eats the clear space - never level a shaft with plaster under 0 to +25 mm positive-only tolerances.
  • Thin mortar sealing of masonry shafts is the dust-free works practice, not a written "must plaster"; design requirements prevail.
  • Anchor feasibility on concrete rests on the strength meeting the layout drawings; expansion bolts banned on brick and fixings banned in hollow / foam brickwork are prohibitions.
  • Clauses per current editions; GB 50310-2002 is the acceptance code, local technology codes (DB11/T 1832.20-2022) run finer - on conflict follow the project's local standards and design documents.

Further Reading

  • GB 50310-2002, clause 4.2.5 (shaft rules - size tolerance, materials and surface, pit access, dedicated shaft, permanent lighting 50 lx or more, separators, pit waterproofing, floor benchmarks) and clause 4.4.3 (bracket fixing).
  • DB11/T 1832.20-2022, clauses 4.3.8 (shaft rules and lighting table), 5.3.1 (wall completion), 5.4.3 (brackets, inserts, bolts and through-pins), 8.4.6 (below-sill wall protection), 10.3.6 (enclosure, low-voltage lighting, non-shear-wall ring beams).
  • GB 50157-2013, clause 25.2.4 (station lift shaft materials).

Keywords

  • 电梯井道抹灰
  • 井道内壁装修判定
  • 井道壁不燃不易产生灰尘
  • 井道尺寸允许偏差
  • 导轨支架固定
  • GB 50310-2002
  • DB11/T 1832.20-2022
  • 层门地坎下井道壁防护