The dual measurement boundary of composite slabs and composite beams: the precast soffit plank itemised as a precast concrete component for prefabricated construction (010504), the post-cast composite topping merged into post-cast concrete of composite beams and slabs, and the attribution of its rebar (010506) and formwork (010505)

Composite members must be measured on two sides: the precast soffit plank is measured in m3 as a precast concrete component for prefabricated construction (010504), with no deduction for grout sleeves, post-cast keyways or plank joints, and the joint grouting layer and bedding mortar layer are merged into the component volume; the post-cast concrete strips between precast planks are, per item 4 of GB/T 50854-2024 Annex E.7.7, 'measured within post-cast concrete of composite beams and slabs' and are not added to the plank volume; rebar of the post-cast layer goes to 010506 and formwork to 010505 (by contact area), and none of the three may duplicate the measurement of the precast plank.

Applicable Codes

  • GB/T 50854-2024 App. E Table E.4.1(装配式预制混凝土构件 010504)
  • GB/T 50854-2024 App. E Table E.2.1(现浇混凝土构件 010502)
  • GB/T 50854-2024 App. E Table E.5.1(混凝土模板 010505)
  • GB/T 50854-2024 App. E Table E.6.1(钢筋及螺栓、铁件 010506)
  • GB/T 50854-2024 App. E 说明 E.7.7 第1~4款
  • DB11/T 2382-2024 第4.6.4条、第4.6.8条
  • GB/T 51231-2016 装配式混凝土建筑技术标准 第10.3.8条(预制梁、叠合梁安装)

Topic positioning

The dual measurement boundary of composite members (composite slabs and composite beams) in the bill of quantities: which part is itemised as a precast concrete component for prefabricated construction, which part as cast-in-place (post-cast) concrete, and the resulting attribution of rebar and formwork, so that the same concrete volume is never measured twice.

Core conclusions

1. Two item sets run in parallel: fix attribution before taking off quantities

  • Table E.4.1 precast concrete components for prefabricated construction (code: 010504): the item set-up, the content of item descriptions, the units of measurement and the quantity take-off rules for precast concrete components shall follow Table E.4.1.
  • Table E.2.1 cast-in-place concrete components (code: 010502): cast-in-place concrete components ... shall follow Table E.2.1.
  • Attribution principle: the boundary is the component as shown on the design drawings - the part prefabricated in the plant and erected on site as a finished product goes to 010504; the concrete cast in formwork on site (composite topping, post-cast strips and joint zones included) goes to the cast-in-place concrete items. The two volumes must not overlap.

2. Precast soffit plank: measured as a precast component, joints and bedding merged

  • Precast concrete components are measured by volume at the component dimensions shown on the design, with no deduction for the volume of insulation layers, finishes, rebar, embedded iron parts, conduits, sleeves, junction boxes and holes of individual area no more than 0.30 m2 within the component, and the volume of exposed rebar is not added (DB11/T 2382-2024 clause 4.6.8 item 1).
  • Refinement in the provincial consumption standard (Jiangsu consumption quotas for building and decoration works): no deduction for the volume of rebar, embedded parts, reserved holes, grout sleeves, post-cast keyways and joints between precast components within the component; the volume of grouting layers at column and beam joints is merged into the component volume; for slabs the volume of component edge chamfers is not deducted; for walls the volume of the bedding mortar layer is merged into the component volume and door and window openings are deducted.
  • Scope of embedded parts: embedded steel plates, bolts, sleeves, nuts, junction boxes, electrical boxes, conduits, timber blocks and the like (GB/T 50854-2024 Annex E.7.7 item 3).

3. Post-cast composite topping: not merged into the precast plank, itemised separately

  • Key provision (GB/T 50854-2024 Annex E.7.7 item 4): 'Post-cast concrete strips between the precast planks of composite slabs shall be measured within post-cast concrete of composite beams and slabs.' - the post-cast strips are neither added to the plank volume nor itemised separately as 'flat slabs'; they fall under the post-cast concrete of composite beams and slabs item.
  • Consistent provincial wording (Jiangsu consumption quotas for building and decoration works): 'post-cast concrete strips between the precast planks of composite slabs are measured within post-cast concrete of composite beams and slabs'; post-cast concrete for prefabricated construction is measured by volume at the design dimensions, without deducting the volume of rebar, embedded parts and reserved holes within the component, and without adding the edge chamfer parts of precast components and the post-cast keyway parts.
  • Quota wording (Shaanxi new consumption quota, draft for comment): the placing of post-cast concrete for prefabricated components is measured as solid volume at the design dimensions, without deducting the volume of rebar, embedded iron parts and holes of individual area no more than 0.3 m2 within the concrete, applying the corresponding concrete quota line items of the chapter.

4. Rebar and formwork of the post-cast layer each form their own items

  • Rebar: rebar beyond that built into the prefabricated component is itemised under the applicable codes of Annex E.6 rebar, bolts and iron parts (010506) (E.7.7 item 1); the post-cast concrete rebar quantity is calculated as the length and number of bars shown on the design multiplied by the unit theoretical mass of rebar, applying the corresponding rebar quota line items.
  • Formwork: the precast part carries no formwork; the post-cast layer formwork is measured separately in m2 of formwork contact area under concrete formwork (010505). Shaanxi wording: the formwork area of parts extending into the post-cast concrete and wrapping around precast components is not added; holes of individual area no more than 0.3 m2 in post-cast concrete walls and slabs are not deducted and their side-wall formwork is not added; holes of individual area no less than 0.3 m2 shall be deducted, with the hole side-wall formwork area merged into the formwork take-off of the corresponding walls and slabs.

5. Exceptional attribution of integrally precast components Balconies and air-conditioning slabs precast integrally with external wall panels follow the applicable external wall panel items, and those not precast integrally follow their own items (DB11/T 2382-2024 clause 4.6.4); 'integrally precast balconies, bay (bow) windows and air-conditioning slabs shall be merged into the external wall panel quantity' (clause 4.6.8 item 4). The test is whether the product is precast as a whole or as separate pieces, not where it sits.

Applicability boundaries

  • 'Post-cast concrete of composite beams and slabs' and the preliminary-type 'post-cast strips' (construction-joint post-cast strips and the extra cost of propping to post-cast strips) are not the same item and must not be mixed.
  • The division between the precast plank and the post-cast layer follows the design dimensions (slab thickness, topping thickness); portions cast thicker on site are not measured unless supported by a variation or a site instruction record.
  • Where the local consumption standard provides otherwise for the post-cast layer, such as 'apply the cast-in-place slab quota items' or a separately listed 'post-cast concrete' line item, the current pricing basis at the project location prevails; the provincial rules cited here are wording examples only.
  • Erection of prefabricated components itself includes erecting and removing temporary propping (E.7.7 item 2); no separate propping preliminaries may be measured unless the item description describes a special process.

Further reading

  • GB/T 50854-2024 Standard for quantity take-off of building and decoration works, Annex E: Table E.4.1 (precast concrete components, 010504), Table E.2.1 (cast-in-place concrete components, 010502), Table E.6.1 (rebar, bolts and iron parts, 010506), Table E.5.1 (concrete formwork, 010505), and note E.7.7 (prefabricated components) items 1~4.
  • DB11/T 2382-2024 Consumption standard for construction works, clause 4.6.4 (attribution of integrally precast components) and clause 4.6.8 (measurement of prefabricated components; sleeve grouting and joint cleaning and sealing paid by quantity).
  • Jiangsu consumption quotas for building and decoration works (2026 edition), measurement rules for precast concrete components (merging of post-cast strips, treatment of keyways and chamfers).
  • Shaanxi new consumption quota (draft for comment), chapter 5 'Erection of precast concrete components and placing of post-cast concrete' (post-cast concrete, rebar and formwork each applying its own quota items).