GB/T 50854-2024 removes "beam-and-slab": beams and slabs are coded and listed separately (combined application for solid slabs)
GB/T 50854-2024 has removed the "beam-and-slab" BOQ item (the 2013 edition's 010505001, by the sum of beam and slab volumes, repealed); beams list under "cast-in-place concrete beams" and ordinary floor slabs under "solid slabs", coded separately; at beam-slab intersections the slab counts to the beam's side face and the beam at full depth — the total is unchanged but the BOQ structure is split.
Applicable Codes
- GB/T 50854-2024 App. E.7.4
- GB 50854-2013 Table E.5(已废止)
Topic Positioning
Reading the beam and slab listing rules and combined application after GB/T 50854-2024 "Standard for measurement of building and decoration works" removed the "beam-and-slab" BOQ item.
Core Conclusions
The 2013 edition (repealed), Table E.5, had "beam-and-slab 010505001" by the sum of beam and slab volumes; the 2024 edition, Appendix E.7.4, removed it — beams and slabs are coded and listed separately: beams under the corresponding "cast-in-place concrete beam" items, ordinary floor slabs under "solid slab". Slab categories list only solid slab, hollow slab, sloped roof slab, and other slabs. At beam-slab intersections the slab counts to the faces of walls and beams, the beam at full depth — the concrete total is unchanged but the BOQ structure is split; following the old "beam-slab merged" habit causes omissions or duplication. Itemization rules: roof slabs with slope < 20% under "solid slab", >= 20% under "sloped roof slab" with the slope described (beams with slope >= 20% likewise); concrete cast on steel plate under "solid slab", deducting the steel plate volume and counting profiled-plate corrugation volume changes; hollow floor systems (embedded tubes/boxes) under "hollow slab" deducting their volumes; canopies, gutters, canopy slabs, protruding bay-window top (bottom) slabs, bay-window side panels, drop panels, balustrade panels, and sculptural panels list separately under "other slabs".
Applicable Boundaries
Applies to BOQ compilation for building and decoration works per GB/T 50854-2024 (Appendix E, concrete and reinforced concrete works). The 2013 edition is repealed — the "beam-and-slab by volume sum" caliber must not be used; prefabricated construction, municipal works, and other specialties follow their own standards.
Further Reading
See GB/T 50854-2024, Appendix E.7.4 "cast-in-place reinforced concrete beams and slabs, notes" and E.7.2 "cast-in-place reinforced concrete foundations, notes"; old-new comparison per GB 50854-2013, Table E.5 (repealed).
Keywords
- 有梁板
- 实心楼板
- 坡屋面板
- 现浇混凝土梁
- GB/T 50854-2024
- bill of quantities (BOQ)
- 梁板分别列项
- 空心楼板