Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-25

Preventing double counting of pipes and fittings in fire water extinguishing systems: length by centreline without deducting fittings, threaded fittings absorbed into the pipe quota line items, grooved fittings counted separately per 'set' (with clamp duplication checks and size-band omission checks)

Fire piping has a single layer of length measurement: by the pipe centreline length shown on the design drawings, without deducting valves, fittings and components (DB11/T 2382-2024 clause 6.9.13; Beijing 2021 volume 10 chapter 2 measurement rules: 'pipes are measured by length along the centreline shown on the drawings, without deducting fittings, valves and attachments; fitting installation is measured by the quantities shown'). Fittings split into two bases: for galvanized steel pipe (threaded), the pipe consumption already includes fitting installation, and fitting material quantities follow the drawn quantities or table 6.9.14 contents (pieces/m: DN25 total 0.590, DN50 0.808, DN100 0.520) - threaded fitting installation or main material must not be listed again; for steel pipe (grooved), the pipe item covers only the grooved straight coupling, and grooved elbows, tees and crosses are separate fitting installation items counted per 'set' by drawn quantity, each set including the clamp and seal ring (clause 6.9.16, matching the two item sets of volume 9 fire works, 'fitting installation (grooved coupling)' and 'fitting installation (cut-in connection)', e.g. DN100 grooved 9-1-35, cut-in 9-1-25). The only source of duplication is listing the 'clamp' three times: the sensible clamp ceiling = pipe length x grooved-coupling content of the pipe item (about 0.1667 set/m) + fitting count x grooved-coupling content of the fitting item (1.005 set/set); for DN100, 100m and 20 fittings that is 16.67 + 20.1 = 36.77 sets - a markedly higher figure signals duplication.

Applicable Codes

  • DB11/T 2382-2024 第6.9.13、6.9.14、6.9.15、6.9.16、6.9.17、6.9.22、6.9.24 条
  • DB11/T 2382-2024 第6.8.24~6.8.33 条(低压管件安装)
  • 京建发〔2021〕201号 通用安装第十册 给排水采暖燃气工程 第二章 室内管道
  • 京建发〔2021〕201号 通用安装第九册 消防工程 第一章 水灭火系统
  • GB 50261-2017 第5.1.11条
  • GB/T 50856-2024 App. H 工业管道工程(Table H.4.1、Table H.5.1 说明)
  • GB 5135.11、GB/T 1348、ISO 6182-12

Topic positioning

This card addresses frequent errors in measuring and pricing fire (water extinguishing) piping: listing fittings again after pipes are measured by extended metres, or listing clamps three times. It gives the paired rule 'no deduction on the length side, separate count on the quantity side', the dividing line between threaded and grooved fittings, a quantified check for duplicated grooved clamps, and checks for omitted size bands and for shop-fitted versus site-fabricated fittings.

Core conclusions

1 Length measurement: no deduction for fittings (the basis of the paired rule)

DB11/T 2382-2024 clause 6.9.13: 'Pipe installation quantities shall be computed by the pipe centreline length shown on the design drawings, without deducting the lengths occupied by valves, fittings and components of all kinds.' Beijing 2021 budget consumption standard, general installation volume 10 (water supply, drainage, heating and gas), chapter 2 interior piping, measurement rules: '1. Pipes are measured by length along the centreline shown on the drawings, without deducting fittings, valves and attachments; 2. Fitting installation is measured by the quantities shown on the drawings.' The two sit in the same volume and do not conflict - no deduction on the length side (the pipe length occupied by fittings is already inside the pipe quantity: neither repeated nor deducted), separate count on the quantity side. Cutting fitting items on the ground that 'pipe length already includes fittings', or deducting pipe length on the ground that 'fittings are counted separately', both misread the rule.

2 Threaded fittings: installation cost and contents inside the pipe item, no separate BOQ item

DB11/T 2382-2024 clause 6.9.14: 'The consumption for galvanized steel pipe (threaded) shall include the work content of fitting installation; fitting material quantities may be computed from the drawn quantities or per table 6.9.14.' Table 6.9.14 (unit: pieces/m, nominal diameter within mm), subtotals: DN25 0.590, DN32 0.687, DN40 0.861, DN50 0.808, DN70 0.756, DN80 0.741, DN100 0.520 (DN100: crosses 0.200, tees 0.050, elbows 0.020, couplings 0.100, reducing couplings 0.150). Beijing 2021 volume 10 chapter 2 note 4: 'Steel pipe (welded), stainless steel pipe, copper pipe, water-supply plastic pipe (fusion), buried water-supply plastic pipe, drainage plastic pipe (fusion), steel-plastic composite and aluminium-plastic composite pipe installation all include fitting installation; fitting contents may be taken from the appendix reference table or from the design drawings.' Item-level evidence: the interior galvanized steel pipe (threaded) items (2-1 to 2-6, DN15 to 50) list the work content 'on-site hauling, inspecting and cleaning pipe, cutting, threading, fitting up, straightening, bending, painting threads, installing pipe and fittings, hydraulic test, flushing', and the material column lists 'interior galvanized steel pipe fittings (threaded) (1.4040) pcs' - the bracketed figure is the unpriced material content, quantity only, priced separately. Determination: unions, tees, elbows, couplings, reducing couplings and other threaded fittings never get separate BOQ items; their main material cost enters the pipe all-in unit rate as 'content (pcs/m) x pipe length x published price information'. Listing 'threaded fitting installation' or 'threaded fitting main material' is duplication (the content comes from the same item). Steel pipe (flanged) consumption shall include fitting and flange installation work content (clause 6.9.15) - likewise no separate fitting installation item.

3 Grooved: the pipe item covers straight couplings only; fittings are separate items counted per 'set'

DB11/T 2382-2024 clause 6.9.16: 'The consumption for steel pipe (grooved) shall include the work content of installing grooved straight couplings; grooved fittings such as elbows, tees and crosses shall be set up as separate fitting installation items by size, measured by the drawn quantities, and each set of grooved fittings shall include the clamp and the seal ring.' Beijing 2021 volume 9 fire works / chapter 1 water extinguishing systems / section 1 piping splits grooved work into two fitting item sets, both in 'sets', not interchangeable:

  • Fitting installation (grooved fitting coupling) - for grooved elbows, tees and crosses, split by size band (e.g. DN100 item 9-1-35: all-in labour class II 0.160 workday, grooved couplings 1.005 set/set, graphite lubricant 0.0112kg, cutting discs 0.037 pcs, grooving machine 0.004 machine-shifts);
  • Fitting installation (cut-in connection) - for mechanical tees and crosses, split by size band (e.g. DN100 item 9-1-25: labour 0.147 workdays, grooved mechanical couplings 1.005 set/set, PTFE tape 0.904m, hole-cutting machine 0.0209 machine-shifts + grooving machine 0.0125 machine-shifts). Cut-in adds a hole-cutting machine - misapplying the item creates deviation. The grooved pipe item itself contains only the 'grooved straight coupling (with rubber ring)', about 0.1667 set/m (one coupling about every 6m).

4 Quantified check for clamp duplication (three steps)

  1. Straight-pipe clamps = pipe length x grooved-coupling content of the pipe item (about 0.1667 set/m; take the measured content of the item used);
  2. Fitting-borne clamps = drawn grooved fitting count x grooved-coupling content of the fitting item (1.005 set/set);
  3. Sensible clamp total = 1 + 2. Example: DN100, 100m of pipe, 20 grooved fittings -> 16.67 + 20.1 = 36.77 sets; a clamp quantity on the BOQ or enquiry clearly above this signals duplication (typical shapes: pipe main material claims clamps, fitting main material claims clamps again, and a third listing under a standalone 'clamp' item). Also check the fitting conversion per metre = fitting count / pipe length (0.20 pcs/m in the example), against table 6.9.14 reference contents and comparable-project benchmarks - an abnormally high ratio indicates duplicated fittings or a wrong size band.

5 Construction compliance limits on grooved coupling (where grooved fittings are mandatory and mechanical tees barred)

GB 50261-2017 clause 5.1.11: grooved fittings shall comply with GB 5135.11 Sprinkler systems part 11 grooved couplings; the body shall be ductile iron to GB/T 1348; rubber seal rings shall be EPDM to ISO 6182-12. For mechanical tee connections, check the gap between mechanical tee and hole and tighten only once all parts are even: 'the spacing of mechanical-tee holes shall be no less than 500mm and of mechanical-cross holes no less than 1000mm; the branch diameter for mechanical tee and cross connections shall satisfy table 5.1.11'; 'the connection of distribution mains (risers) to distribution pipes (horizontal runs) shall use grooved fittings, not mechanical tees'; the bolts and nuts of buried grooved fittings shall be corrosion-protected, and buried pipes in pump rooms shall use flexible joints (this item is checked in full). So riser-to-horizontal junctions must be priced as grooved fittings (elbows / tees) under 'grooved fitting coupling' items; misusing mechanical tees (cut-in connection) is both non-compliant and under-counts the hole-cutting machine and labour.

6 Checking omitted sizes and pressure classes (sources of pricing deviation)

  • Reducers follow the fitting installation item of the larger diameter (DB11/T 2382-2024 clause 6.8.29); GB/T 50856-2024 appendix H note 2: 'tees, crosses and reducers are all measured by the larger diameter'.
  • Field-cut branch tees: clause 6.8.26 'where the branch of a cut-in tee exceeds half the main diameter, the fitting installation item of the main diameter applies; where it is smaller than half, the branch diameter applies; branch stubs and bosses welded onto the main follow the fitting diameter of the accessory, and no further tee main material consumption is counted'; GB/T 50856-2024 appendix H adds 'where the branch of a cut-in tee is smaller than half the main diameter, it is not counted'.
  • Flanged fittings follow the flange installation item with the fitting itself as main material, and fitting installation is not counted again (clause 6.8.32; GB/T 50856-2024 appendix H note 5). Check with three columns: drawn fitting size / pressure class vs size band of the applied item vs the attribution rules of the chapter notes (larger diameter, branch / main, flange exception), closing each line. Omissions cluster at reducers, cut-in tees and flanged fittings - showing up as under-sized bands, branch-diameter pricing of large-size items, and flanged fittings charged both as fitting installation and as flange installation (duplicated).

7 Shop-fitted versus site-fabricated fittings

Clause 6.8.24: low-pressure fitting installation items are set by material, size and connection method; clause 6.8.25: quantities follow the drawn count. Site fabrication bases (all as coefficient x the fitting installation item):

  • primary instrument parts on pipes: fitting installation item, consumption x 0.70 (clause 6.8.27);
  • welded blind plates: fitting installation item, consumption x 0.60 (clause 6.8.28);
  • thermometer enlargement pipes, fabricated and installed: fitting installation item, consumption x 1.50, quantity by the larger diameter (clause 6.8.30);
  • outer jacket fittings of fully heated jackets follow two half-fittings (two longitudinal and two girth welds); two-half closure stubs follow the two-half elbow item (clause 6.8.31);
  • half-heated jacket outer pipes swaged and welded to the inner pipe: each weld counts as one fitting; where a carbon-steel outer pipe welds to a stainless inner pipe, a stainless spacer stub is added between welds - each weld counts as two fittings, the spacer by drawn length or, absent design rules, 50mm (clause 6.8.33). GB/T 50856-2024 appendix H note 1 defines the fitting scope: 'fittings include elbows, tees, crosses, reducers, couplings, caps, square-expansion-bend elbows, primary instrument parts on pipes, and fabricated thermometer enlargement pipes'. Shop fittings are counted in 'pieces (sets)'; site-fabricated fittings convert to fitting counts (welds / coefficients) with no separate fabrication cost or main material (cut-in case).

8 Other error-prone attributions in the fire chapter (chapter 6.9)

  • Alarm device installation consumption includes assembly piping, release-test piping and alarm-bell outlet piping; the alarm-bell inlet pipe follows pipe installation items by drawn size; the air compressor, air-maintenance piping and valves of pre-action alarm valves follow the mechanical equipment and industrial piping chapters respectively (clause 6.9.17).
  • Threaded flow switches follow the threaded valve items of the water supply, drainage, heating and gas chapter (clause 6.9.18).
  • Sprinkler, alarm device and flow switch installation consumption is compiled for installation after successful pressure test and flushing of the network, allowing for plugs, temporary stubs and their installation, removal and amortisation (clause 6.9.19).
  • Combined fire cabinets follow the interior hydrant items (clause 6.9.20); electric fire monitors and simulated end devices include the body, the steel base fabrication and installation follows the water supply, drainage, heating and gas chapter, and the concrete foundation the building and decoration chapter (clause 6.9.21).
  • Quantities by drawn count: sprinklers, flow switches, orifice plates, heat-collecting hoods (clause 6.9.22); flexible sprinkler hoses, alarm devices, interior hydrants, underground exterior hydrants and fire department connections, with alarm devices, interior and exterior hydrants and fire department connections treated as complete sets (clause 6.9.23 and table 6.9.23: the wet alarm device comprises wet valve, supply pressure gauge, device pressure gauge, test valve, release test valve, test-line flow meter, strainer, retard chamber, alarm bell, alarm stop valve, funnel, pressure switch and so on); end-of-line test devices, extinguishers and electric fire monitors by count (clause 6.9.24).

Applicability boundaries

  • Directly applicable to construction projects in Beijing priced with DB11/T 2382-2024 and the Beijing 2021 budget consumption standard (Beijing housing and construction commission document [2021] No. 201); other provinces share the principles (no length deduction, fittings counted separately) but item codes and the existence of standalone grooved-fitting items must be checked against the local quota.
  • Counting grooved fittings per 'set' presupposes that the standard / quota carries fitting installation (grooved coupling / cut-in) items; where a region rolls grooved-fitting content into the pipe item, separate fitting items are barred.
  • The coefficients and criteria of section 6.8 (industrial low-pressure fittings: x 0.70, x 0.60, x 1.50, 50mm spacer) belong to the industrial piping chapter; the fire chapter does not state them directly - borrowing them for analogous cases must cite the source and reason in the pricing notes.
  • The clamp check thresholds (0.1667 set/m, 1.005 set/set) are measured contents of the cited items; re-measure when the size band or regional quota changes - do not reuse these figures directly.
  • This card does not cover specific prices or published price information values.

Further reading

  • DB11/T 2382-2024 Consumption standard for construction works, chapter 6.9 fire works / II water extinguishing systems, 6.9.12 to 6.9.24 (incl. table 6.9.14 threaded-fitting reference contents for galvanized pipe, table 6.9.23 complete-set products); chapter 6.8 industrial piping works / V low-pressure fitting installation, 6.8.24 to 6.8.33.
  • Beijing 2021 budget consumption standard (Beijing housing and construction commission document [2021] No. 201), general installation volume 10 water supply, drainage, heating and gas, chapter 2 interior piping (notes 1 to 14, measurement rules, items 2-1 to 2-6); volume 9 fire works, chapter 1 water extinguishing systems, section 1 piping (grooved pipe items, grooved-coupling and cut-in fitting items).
  • GB 50261-2017 Code for construction and acceptance of sprinkler systems, clause 5.1.11 (grooved couplings, incl. table 5.1.11 maximum branch diameters).
  • GB/T 50856-2024 Standard for quantity take-off of general installation works, appendix H industrial piping (table H.4.1 low-pressure fittings, table H.5.1 notes on medium-pressure fittings), appendix K water supply, drainage, heating and gas.
  • GB 5135.11 Sprinkler systems part 11 grooved couplings; GB/T 1348 Ductile iron castings; ISO 6182-12 Quick couplings for metal pipe systems - performance requirements and test methods.

Keywords

  • 消防管道工程量
  • 沟槽管件安装
  • 卡箍重复计算
  • 镀锌钢管螺纹连接管件含量
  • 不扣除管件所占长度
  • DB11/T 2382-2024
  • 机械三通开孔连接
  • 北京2021预算消耗量标准