BOQ measurement of system commissioning versus single-machine trial runs: heating and air-conditioning water system commissioning (code 031008) and ventilation works inspection, commissioning and testing (code 030704) listed 'by system', while equipment installation items already include commissioning of the unit and single-machine trial runs and are not separately payable
GB/T 50856-2024 Clause 3.0.11 provides that the equipment installation work content of this standard includes commissioning of the equipment itself and single-machine trial runs - single-machine trial runs may therefore not be listed as a separate BOQ item nor priced under a separate commissioning quota item; what is listed separately and measured 'by system' is the system (interlock) commissioning group of BOQ items: heating and air-conditioning water system commissioning per Table K.8.1 (code 031008), ventilation works inspection, commissioning and testing per Table G.4.1 (code 030704), and fire protection system commissioning under Annex J code 030909.
Applicable Codes
- GB/T 50856-2024 · Standard for measurement of general mechanical, electrical, plumbing and fire services 第3.0.11条
- GB/T 50856-2024 App. K Table K.8.1(code 031008)
- GB/T 50856-2024 App. G Table G.4.1(code 030704)
- GB/T 50856-2024 App. J(code 030909 消防系统调试)
Scope
Locating 'commissioning' in the BOQ of installation works: which commissioning content belongs to the equipment installation work (included, not separately payable) and which is listed as a separate 'system' BOQ item; covering the three systems of heating and air-conditioning water, ventilation and air-conditioning, and fire protection.
Core Conclusions
1. Negative conclusion: single-machine trial runs are inside the equipment installation items
GB/T 50856-2024 Standard for Quantity Take-off of General Installation Works, Clause 3.0.11, original text: 'The equipment installation work content of this standard includes commissioning of the equipment itself and single-machine trial runs.' The clause also states: 'This clause states that the equipment installation work content of this standard includes commissioning of the equipment itself and single-machine trial runs.'
Corollary: for any equipment installation item listed under this standard, the cost of commissioning the unit and of its single-machine trial run is already within the all-in unit rate of the equipment installation item - no separate 'single-machine trial run' BOQ item may be listed, and no separate single-machine trial run quota item may be applied for extra payment. The wording 'commissioning of the unit itself' in local consumption standards is likewise an included basis (e.g. Beijing DB11/T 2382-2024 items for automatic fire alarm and for intelligent emergency lighting and evacuation indication installation include commissioning of the unit).
2. Positive conclusion: system (interlock) commissioning is a separate 'system' BOQ item
1 Heating and air-conditioning water: 'the setting of the heating and air-conditioning water system commissioning BOQ items, the content of item description, the units of measurement and the quantity take-off rules shall follow the provisions of Table K.8.1.' Table K.8.1 is 'heating and air-conditioning water system commissioning (code 031008)' - measured by system, applying to the interlock commissioning of heating systems and of air-conditioning water systems. 2 Ventilation and air-conditioning: 'the setting of the ventilation works inspection, commissioning and testing BOQ items, the content of item description, the units of measurement and the quantity take-off rules shall follow the provisions of Table G.4.1.' Table G.4.1 is 'ventilation works inspection, commissioning and testing (code 030704)' - measured by system (air system), covering inspection, commissioning and testing. 3 Fire protection: system commissioning is itemised under GB/T 50856-2024 Annex J code 030909.
3. Decision path (avoiding the two error types)
- 'Pipe pressure testing / flushing / disinfection' and 'unit commissioning / single-machine trial run' take one path: they are work content of existing BOQ or quota items and are not listed separately - the former is inside the pipework items (Table K.1.1 note 9), the latter inside the equipment installation items (Clause 3.0.11).
- 'System commissioning' takes the other path: it has its own codes (031008 / 030704 / 030909) and is listed separately, measured by system or by plant room - omitting it produces a 'missing system commissioning item', while additionally listing single-machine trial runs produces 'duplicate commissioning charging'.
- Commissioning runs from single machine, to sub-system, to no-load interlock, to loaded combined operation, and the measurement boundaries follow in order: included in the installation items (the first two) - the system commissioning BOQ item (no-load interlock) - the combined trial run cost among project costs other than the works (loaded).
Applicability Boundaries
- This card works at the BOQ level (GB/T 50856-2024), on itemisation and measurement; at quota level (whether separate commissioning items exist, whether charges are taken by coefficient) the volume notes of the applied quota govern; the two levels do not substitute for each other.
- 'System commissioning' is measured by system: one system, one unit of measurement; the division of systems follows the design (air-conditioning water by heat and cold source system, heating by riser system or by zone), and system counts must not be repeated per machine.
- 'Included' unit commissioning and single-machine trial runs presuppose that the equipment installation is itemised under this standard; separately procured specialist commissioning services, performance testing or third-party inspection are not covered and are matters for the contract.
- The item setting of fire system commissioning code 030909 is in GB/T 50856-2024 Annex J; whether local standards set separate system commissioning items varies by region (Beijing DB11/T 2382-2024 Chapter 6.9 shows no separate fire system commissioning item).
Further Reading
GB/T 50856-2024 Standard for Quantity Take-off of General Installation Works, Clause 3.0.11 (equipment installation work content includes commissioning of the unit and single-machine trial runs); Annex K Table K.8.1 'heating and air-conditioning water system commissioning (code 031008)'; Annex G Table G.4.1 'ventilation works inspection, commissioning and testing (code 030704)'; Annex J fire protection system commissioning (code 030909); local consumption basis compared in DB11/T 2382-2024 Chapter 6.9, fire protection works.