Pricing boundary of fire sprinkler system commissioning: equipment installation already includes commissioning of the equipment itself and single-machine trial runs (the negative conclusion, not separately payable), while system interlock commissioning is separately itemised under code 030909 with its point-counting rules, and water extinguishing commissioning and fire alarm commissioning are itemised separately
GB/T 50856-2024 Clause 3.0.11: 'the equipment installation work content of this standard includes commissioning of the equipment itself and single-machine trial runs' - single-machine trial runs and commissioning of the unit may never be charged outside the equipment installation items; only interlocking across equipment and across systems is listed separately under Annex J Table J.9.1 fire protection system commissioning (code 030909): water extinguishing control devices counted in points (branches) by the number of water flow indicators (sprinkler systems), hydrant pump-start buttons and fire monitors; automatic alarm and the other systems take their points from the device and component counts and are measured as 'systems'; gaseous extinguishing counts points by the cylinder head valves; fire barrier control devices by the piece and fire lifts by the lift; water extinguishing commissioning and fire alarm commissioning must be itemised separately.
Applicable Codes
- GB/T 50856-2024 第3.0.11 条(工程计量)
- GB/T 50856-2024 App. J Table J.9.1(消防系统调试,code 030909)
- GB/T 50856-2024 App. J J.11.9 消防系统调试有关问题说明
- GB 50261-2017 第7.2.1 条(系统调试内容)
Scope
The boundary of commissioning costs for fire sprinkler (water extinguishing) systems: what is already included in the equipment or component installation items (commissioning of the equipment itself, single-machine trial runs), what must be separately itemised and measured under GB/T 50856-2024 code 030909 (system interlock commissioning), and how water extinguishing system commissioning and fire alarm system commissioning are listed separately and how the points are counted.
Core Conclusions
(1) Negative conclusion (single-machine trial runs not separately payable): GB/T 50856-2024 Clause 3.0.11: 'the equipment installation work content of this standard includes commissioning of the equipment itself and single-machine trial runs.' - every equipment installation item (fire pumps, pressure-maintaining pumps, alarm valves, pressure tanks and the like) carries commissioning of the unit itself and its single-machine trial run within its all-in unit rate; no separate 'single-machine trial run' or 'unit commissioning' item may be set up, and no separate site instruction record may be certified for them. Only interlocking across equipment and across systems enters 030909.
(2) System commissioning must be separately itemised: GB/T 50856-2024 Annex J Table J.9.1 fire protection system commissioning (code 030909): 'the setting of the fire protection system commissioning BOQ items, the content of item description, the units of measurement and the quantity take-off rules shall follow the provisions of Table J.9.1.' - commissioning stands in the bill of quantities as its own item and is not charged as a percentage of the works cost.
(3) Points and units (essence of the explanatory notes J.11.9): 1 'Automatic alarm systems: alarm systems composed of detectors, alarms, alarm buttons, alarm control panels and the like; measured by the corresponding number of points as a system, the points counted from the number of devices and components'; 2 'Water extinguishing control devices: sprinkler systems counted by the number of water flow indicators in points (branches); hydrant systems by the number of hydrant pump-start buttons in points; fire monitor systems by the number of monitors in points'; 3 'Fire barrier control devices: devices including fire roller shutters, positive-pressure supply air dampers, smoke exhaust dampers, fire control dampers and fire lifts; the commissioning of roller shutters, positive-pressure supply dampers, smoke exhaust dampers and fire control dampers is counted by the piece, and fire lifts by the lift'; 4 'Gaseous extinguishing system commissioning: extinguishing systems composed of heptafluoropropane, IG541, carbon dioxide and the like; counted in points by the cylinder head valves of the gaseous extinguishing installations'; 5 to 9 The air-sampling detection and alarm system, the fire door monitoring and alarm system, the electrical fire monitoring system, the fire power supply monitoring system and the fire voice alarm system are each 'measured by the corresponding number of points as a system'.
(4) Separate itemisation: water extinguishing control device commissioning (points from flow indicators, pump-start buttons or monitors) and fire alarm system commissioning (points from device and component counts, measured as a 'system') are two independent commissioning systems; they must be listed separately under the corresponding 030909 items with their own point counts, not merged into one item nor lending each other points; gaseous extinguishing counts by the cylinder head valves and fire barrier devices by the piece, likewise separately listed.
(5) Process boundary between interlock commissioning and single-machine trial runs: a single-machine trial run is the powered trial operation of one machine on its own, included in the equipment installation item; the interlock test is the interlocked action of alarm valves, fire pumps, end test assemblies and the fire alarm system - system-level interlock commissioning under 030909. GB 50261-2017 Clause 7.2.1 requires system commissioning to cover: '1 water source test. 2 fire pump commissioning. 3 pressure-maintaining pump commissioning. 4 alarm valve commissioning. 5 drainage facilities commissioning. 6 interlock test.' The commentary to that clause notes that the interlock test 'is in effect a test of the interlocked action between the system and the automatic fire alarm system' and reflects whether the components of the system work together - interlock action is system-level behaviour, on a different pricing tier from commissioning of a single unit.
Applicability Boundaries
- 030909 is measured in points, systems, pieces and lifts; it is a measured BOQ quantity item, not a rate item; the points follow the component counts fixed by J.11.9 and must be checked against the equipment schedules of the drawings.
- The point basis of the BOQ and the point bands of the applied quota (e.g. per 100 points, per additional 50 points) are two different bases; conversion follows the quota steps and the two cannot be interchanged; some local or sectoral quotas state the unit as 'system' yet band internally by points - read the quota item notes.
- 'Commissioning of the unit included' covers only the single unit and its single-machine trial run; the interlock commissioning of the water, gaseous and foam extinguishing systems and the joint commissioning with the alarm systems remain separate BOQ items.
- Commissioning takes place after the pipework has passed pressure testing and flushing (component quotas are compiled on installation after passing test and flush); pressure testing costs must not be booked to the commissioning items.
- Third-party inspection and fire acceptance testing are commissioned testing services and do not belong to the contractor's 030909 commissioning items; they must not be mixed in.
Further Reading
GB/T 50856-2024 Clause 3.0.11 (equipment installation work content includes commissioning of the equipment itself and single-machine trial runs); Annex J Table J.9.1 (code 030909 fire protection system commissioning) and the J.11.9 explanatory notes on fire protection system commissioning, items 1 to 9; Table J.1.1 (code 030901 water extinguishing systems); GB 50261-2017 Code for Construction and Acceptance of Sprinkler Fire Extinguishing Systems, Clause 7.2.1 (content of system commissioning: water source test, fire pump commissioning, pressure-maintaining pump commissioning, alarm valve commissioning, drainage facilities commissioning, interlock test). The general concepts and the sequence of single-unit commissioning versus system interlock commissioning are covered in existing cards.