Applying static equipment and process metal structure fabrication/installation quotas: process-item determination of site-built tank shells and metal-weight measurement rules
Tank shells fabricated on site from delivered steel plate/section stock by cutting and welding (e.g., powder-silo shells) belong to installation works "static equipment and process metal structure fabrication and installation" — i.e., process items, not civil steel structures. Apply metal tank (storage tank) fabrication/installation or hopper/silo prefabrication/installation sub-items, measured in t (metal weight): computed from the geometric dimensions of the design nesting drawing / approved cutting and plating layout, including base plates, shell plates, roof plates, curb angles, and stiffening rings, without deducting hole areas; capacity by the nearest quota step.
Applicable Codes
- DB11/T 2382-2024 建设工程施工消耗量标准 第6.3章 静置设备与工艺金属结构制作安装工程
- 江西省通用安装工程消耗量定额 第五册
Topic Positioning
Quota attribution and measurement of site-built tank shells: whether vessels fabricated and installed on site from delivered raw stock (e.g., powder-silo shells) count as process items, which quota volume applies, and how quantities are computed.
Core Conclusions
- Tank shells fabricated and installed on site from delivered raw stock belong to installation works "static equipment and process metal structure fabrication and installation" (process items), not civil steel structures; apply metal tank (storage tank) fabrication/installation or hopper and silo prefabrication/installation sub-items.
- Measured in t (metal weight), not m3 or per unit: computed from the geometric dimensions of the design nesting drawing / approved cutting and plating layout; the oil tank proper includes base plates, shell plates, roof plates, curb angles, stiffening rings, wind girders, and pads/reinforcing plates, without deducting hole areas; hoppers and silos do not deduct manhole, inspection, or cleanout openings.
- Capacity by the nearest quota step.
- Accessories: ladders, platforms, and railings computed separately as process metal structures; derusting, painting, anti-corrosion, and insulation, foundation casting, and grouting follow the painting/insulation, building-decoration, and machinery-installation chapters respectively; for installation above 30 m, the labor above is x 1.10.
Applicable Boundaries
Based on that chapter of the general installation quota system (Beijing DB11/T 2382-2024, Chapter 6.3, as a same-system reference); sub-item codes and capacity steps follow the current provincial installation consumption quota, Volume 5. Not applicable to whole installation of finished equipment, pipelines outside equipment flanges (industrial piping chapter), or electrical/instrument systems (their own chapters).
Further Reading
DB11/T 2382-2024, Chapter 6.3: 6.3.11 piece/segment assembly and material coefficients, 6.3.25 metal oil tank proper measurement, 6.3.41-6.3.42 super-height coefficients, 6.3.44 member weight including bolts without deducting holes and cut angles, 6.3.45 platforms, 6.3.46 hoppers and silos; provincial counterpart "Jiangxi General Installation Works Consumption Quota", Volume 5.
Keywords
- 静置设备
- 工艺金属结构
- 粉料库罐体
- 金属油罐制作安装
- 料斗料仓预制安装
- 工艺件
- pricing by applying quota line items
- 按金属重量计量